Advance Notice - Design and construction of the Port Monmouth Phase II, Contract 1 Mitigation project in Middletown Township, Monmouth County, New Jersey.
W912DS26RA0017
Department of the Army, W2SD Endist New York. Other Heavy and Civil Engineering Construction.
Response deadline
April 6, 2026 at 12:00 PM EDT
Closed 210 days ago. Posted March 26, 2026, first published March 20, 2026. Scheduled to archive April 21, 2026.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed in 2026
129 like it are open now in other heavy and civil engineering construction
- Sources Sought:Neopit Dam Remediation Construction
Bureau of Indian Affairs, Bureau of Indian Affairs
Sources soughtNAICS 237990WisconsinDOIASAM270004Closes todayNov 2 - USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA
Department of the Army, W075 Endist Sacramento
SolicitationNAICS 237990Sacramento, CAW9123826BA013Closes tomorrowNov 3 - Belle Fountain Ditch Cleanout Phase 2
Department of the Army, W07V Endist Memphis
SolicitationSDVOSBNAICS 237990MissouriW912EQ26BA002Closes tomorrowNov 3
All 129 open in other heavy and civil engineering construction
Description
As published on SAM.gov.
As of 26 March 2026: the advance notice has been corrected to indicate that this contract doesn’t include the purchase of wetland mitigation credits.
ADVANCE NOTICE: Port Monmouth Phase II, Contract 1 Mitigation, New Jersey
Design and construction of the Port Monmouth Phase II, Contract 1 Mitigation project in Middletown Township, Monmouth County, New Jersey. This notice is for informational and planning purposes only and does not constitute a solicitation for bids or proposals.
PROJECT DESCRIPTION
The Port Monmouth project includes shore protection components (Phase 1) as well as flood risk management components (Phase II). The project provides for reduction of storm damages to low-lying residential and commercial structures from coastal erosion, tidal flooding, and inland flooding along Pews and Compton Creeks caused by high surface events in Raritan Bay. Phase II flood risk management components consist of a tide gate, levees, floodwalls, two pump stations, three road closure structures, road raising and regarding, and wetland mitigation. The State of New Jersey, acting through the New Jersey Department of Environmental Protection (NJDEP), is the non-Federal sponsor for the project..
This design-build construction contract scope includes the design and construction services of forested and emergent wetlands at the Pews site, scrub-shrub and herbaceous tidal wetlands at the Compton Creek site.
Acquisition Strategy: This is a two-phase "Best Value Trade Off" solicitation in accordance with Federal Acquisition Regulation (FAR) 15.101-1 for Port Monmouth Phase II, Contract 1 Mitigation at Monmouth County, NJ. The Government will evaluate the proposals in accordance with the Source Selection Criteria, and award a firm fixed price contract to the responsible firm, whose proposal conforms to all the terms and conditions of the solicitation and is fair and reasonable and offers the best overall value to the Government.
The formal Design-Build Best Value Trade Off (DB BVTO) is anticipated to be issued on or about April 2026 .
The period of performance for this project is 746 calendar days from the Notice to Proceed date.
CLASSIFICATION
- NAICS Code: 237990 (Other Heavy and Civil Engineering Construction)
- Place of Performance: Port Monmouth, NJ
- Project Magnitude: Between $15,000,000 and $30,000,000
- This project will be acquired via Full and Open Competition – Unrestricted
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
March 20, 2026
Special notice, originally sources sought
Due April 6, 2026 at 12:00 PM EDT. SAM.gov, notice a2c172ec241d4a29affcc806026fabc5
3 revisions on SAM
- March 26, 2026: publish, special notice
- March 20, 2026: publish, special notice
- January 21, 2026: publish, sources sought
March 26, 2026
Special notice
Due April 6, 2026 at 12:00 PM EDT. SAM.gov, notice f926fc276e2e407495e51121db61abd9
4 revisions on SAM
- September 17, 2026: publish, solicitation
- March 26, 2026: publish, special notice
- March 20, 2026: publish, special notice
- January 21, 2026: publish, sources sought
Points of contact
- Adrian Stafford-Browneadrian.j.stafford-browne@usace.army.mil
- Nicholas P. Emanuelnicholas.p.emanuel@usace.army.mil