USACE SPK DBB Construction - Natomas NPP Renovations - Sacramento, CA
W9123826X1BN4
Department of the Army, W075 Endist Sacramento. Water and Sewer Line and Related Structures Construction.
Response deadline
May 19, 2026 at 11:00 AM EDT
Closed 171 days ago. Posted April 29, 2026, first published April 29, 2026. Scheduled to archive June 3, 2026.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed in 2026
28 like it are open now in water and sewer line and related structures construction
- LB Lateral Water Line and Facilities Replacement for Wastewater System
Departmental Offices, Reclamation Contracting Activity
Sources soughtNAICS 237110California140RR027R0014Closes in 6 daysNov 12 - USACE SPK DBB Construction - Calaveras Wastewater Treatment Plant Improvements - Copperopolis, CA
Department of the Army, W075 Endist Sacramento
Sources soughtNAICS 237110Copperopolis, CAW9123827X1CHGCloses in 31 daysDec 7 - BRINE PIPELINE ACCESS IMPROVEMENTS
Department of the Army, W075 Endist Los Angeles
PresolicitationSmall businessNAICS 237110CaliforniaW912PL26BA002Closes in 90 daysFeb 4, 2027
All 28 open in water and sewer line and related structures construction
Description
As published on SAM.gov.
This is a Sources Sought Notice for market research purposes only. This is not a solicitation for proposals/bids, and no contract will be awarded from this notice. The U.S. Army Corps of Engineers (USACE), Sacramento District (SPK), is conducting market research to identify qualified and interested businesses capable of performing the construction project described below.
No reimbursement will be made for any costs associated with providing information or industry response to this notice or any follow-up information requests. Not responding to this notice does not preclude participation in any future procurement. If a solicitation is released, it will be synopsized in the System for Award Management (SAM). It is the responsibility of potential offerors to monitor SAM for additional information pertaining to this requirement.
The acquisition strategy will be determined based on responses received from this notice and/or other market research methods. The planned acquisition strategy will be posted in SAM upon completion of market research analysis.
The purpose of this notice is to gain knowledge of interest, capabilities and qualifications of industry, to include the small business community: Small Business, 8(a) Program Participants, Historically Underutilized Business Zones (HUBZone), Service-Disabled Veteran-Owned Small Business (SDVOSB), Women-Owned Small Business (WOSB). All are highly encouraged to respond.
Prior Government contract work is not required for submitting a response to this notice. However, respondents are reminded that all construction performance must follow the Engineer Manual (EM) 385-1-1, USACE Safety and Health Requirements Manual and any other requirements contained in the solicitation, and must also comply with all Federal, State, and local laws, ordinances, codes and/or regulations.
This announcement provides the detailed information necessary for your firm to prepare its response.
Project Title:
Natomas Named Pumping Plants (NPP)
Project Location:
Sacramento River North of I5 - Natomas, Sacramento, CA
NAICS Code:
237110 - Water and Sewer Line and Related Structures Construction
PSC:
Z2NE - Repair or Alteration of Water Supply Facilities
Estimated Magnitude of Construction:
$10,000,000.00 to $15,000,000.00
Anticipated Solicitation Issuance Date:
July 2026
Estimated Duration of the Project:
780 calendar days from Notice to Proceed
Anticipated Contract Type:
Firm-Fixed Price
Anticipated Acquisition Method:
FAR Part 14, Sealed Bidding
High-Level Project Summary:
The United States Army Corps of Engineers (USACE) Sacramento District (SPK) anticipates a potential requirement for construction services to renovate three (3) pumping stations (the Named Pumping Plants (NPPs)) in the Natomas region of Sacramento, California (CA).
In general, the work for each site is anticipated to consist of removing the discharge pipes that currently go through the levee and installing new discharge piping that will traverse over the levee.
Elkhorn Pumping Plant is an irrigation pumping plant located on the Sacramento River north of Interstate 5 and west of Highway 99 along the Garden Highway Levee at River Mile 73.6. The plant conveys water from the Sacramento River into the Natomas Mutual Water Company’s (NMWC) Elkhorn Irrigation System. The work at this site is anticipated to include levee excavation, removal of existing piping and appurtenances, levee embankment backfill and compaction, installation of new piping, build up area, removal and replacement of a portion of Garden Highway pavement, installation of vacuum system and conduit, and replacement of fiber optic line conduit.
Riverside Pumping Plant is an irrigation pumping plant located on the Sacramento River north of Interstate 5 and west of Highway 99 along the Garden Highway Levee at River Mile 65.78 (Natomas Reach B). The plant conveys water from the Sacramento River into the NCMWC’s Riverside Irrigation Canal. The work at this site is anticipated to include levee excavation, removal of existing piping and appurtenances, levee embankment backfill and compaction, installation of new piping, modification of existing maintenance ramp, removal and replacement of a portion of Garden Highway pavement, installation of vacuum system and conduit, and installation of underground conduit.
Pritchard Pumping Plant is an irrigation pumping plant located on the Sacramento River north of Interstate 5 and west of Highway 99 along the Garden Highway Levee at River Mile 75.0/Levee Mile 5.82 (Natomas Reach C). The plant conveys water from the Sacramento River into the NCMWC’s Elkhorn Irrigation Canal. The work at this site is anticipated to include levee excavation, removal of existing piping and appurtenances, levee embankment backfill and compaction, installation of new piping, installation of vacuum system and conduit, and replacement of fiber optic line conduit.
The Government estimates that construction of the potential requirement can be completed within seven-hundred-eighty (780) calendar days from receipt of Notice to Proceed, with construction occurring sequentially over three (3) years at a rate of one (1) plant per construction season. If market conditions indicate this estimate may be unrealistic, Respondents are encouraged to provide specific information (such as known equipment lead times or other timeline concerns) for Government consideration when responding to this Sources Sought Notice.
Minimum Technical Requirements" and "Critical Features of Work:
The work includes the removal and raising of piping from the plant up and over the levees to connect to existing pipes on the landside that outlet into the Riverside and Elkhorn Irrigation Canals Work must be sequenced and Contractor must have capability to perform levee improvement projects.
Cybersecurity Maturity Model Certification (CMMC) Requirement:
This project will require Level 1 Self Certification.
Other Known Challenges:
Environmental concerns include Giant Garter Snake (GGS) habitat and potential cultural considerations.
Prospective subcontractors are encouraged to submit so the information can be used when developing the potential Small Business Participation Plan percentages if the eventual acquisition is conducted as an unrestricted, negotiated acquisition. If your firm is interested in subcontracting opportunities rather than performing as the Prime Contractor on this future procurement, please identify the feature(s) of work you are interested in and your small business socio-economic category in the Market Survey Form.
All submissions must be made as follows, using the official online Market Survey Form.
AUTHORIZED SUBMISSION METHOD: The only authorized method for responding to this Sources Sought Notice is via the online Market Survey Form. Submissions sent by email or other means will not be accepted.
DEADLINE: All responses must be submitted through the form no later than 0800 / 8:00 AM Pacific Time on 19 May 2026.
ONLINE FORM LINK: Please submit your firm's information using the following link:
Sources Sought Market Survey: Natomas Named Pumping Plants
https://forms.osi.apps.mil/r/LL0im1rXtg
PREPARATION: It is highly recommended that you review all questions in this document and prepare your narrative responses and required documentation offline before beginning the online form.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- Natomas NPP Map - 20260309.pdf759 KB, April 29, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
April 29, 2026
Sources sought
Due May 19, 2026 at 11:00 AM EDT. SAM.gov, notice 05371c0154e54ad0afc981eabfcd7447
3 revisions on SAM
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought
April 29, 2026
Sources sought
Due May 19, 2026 at 11:00 AM EDT. SAM.gov, notice 45ef38c54a3347bba9045b1ddc750481
3 revisions on SAM
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought
April 29, 2026
Sources sought
Due May 19, 2026 at 11:00 AM EDT. SAM.gov, notice e6ba9ad00dbe47748728404c2824e71c
3 revisions on SAM
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought
- April 29, 2026: publish, sources sought