Skip to content
Abierto

Award notice, total small business set-aside

Repair and Renovate Storm Water Lift Station, Bldg. 986, NAS Lemoore, CA

N62473-24-R-J503

Department of the Navy, Navfacsyscom Southwest. Water and Sewer Line and Related Structures Construction.

Awarded

FRAWNER CORPORATION Anchorage

$8,995,000.00 on the award notice, May 9, 2024, contract N62473-19-D-1202

Description

As published on SAM.gov.

1.3.1.1 Base Contract:

a. Remove trash, and drain the inlet basin and the sump pits.

b. Provide temporary bypass pumping service from inlet basin to outlet basin during the work until successful commissioning of new electrical system.

c. Remove existing Lift pump D2, associated motor, appurtenances, pipe supports and piping other than the section embedded in the concrete wall. Existing Lift pumps D1 and D3 and their associated motor, appurtenances and piping remain during Base Contract (see appendix B1: Contract drawings).

d. Remove existing Sump pumps (S1 and S2), associated motors, appurtenances and suction piping. The discharge piping must remain.

e. Remove the existing fencing around electrical substation and equipment.

f. Remove all electrical equipment and components, including but not limited to unit substation enclosure, transformers, disconnect switches, HV fuses, cables to pump motors, control cables, and existing aboveground and underground conduits.

g. Demolish existing concrete foundation of electrical equipment.

h. Provide the following items:

1. one new Lift pump package (D2) including, but not limited to electromotor, pump, coupling and appurtenances . The pump must be axial flow type with total dynamic head (TDH) of 14 feet and capacity of 47,000 gallon per minutes (GPM). Consider 200 to 250 horsepower (hp) for the associated electromotor rating. Apply coating to exposed metal surfaces, if any.

2. Lift pump discharge piping, supports and connections. Connect the new discharge lines to the existing pipes embedded in the concrete wall. Repair the embedded pipe as needed. Apply coating.

3. Two new Sump pump packages (S1 and S2) including electromotors, pumps, couplings and appurtenances. The pumps must be axial flow type with TDH of 25 feet and capacity of 1400 GPM. Consider 15 hp for the associated electromotors rating. Connect the new pumps discharge to the existing discharge piping. Apply coating to exposed metal surfaces, if any.

4. Build new concrete foundation for electrical equipment.

5. New electrical components for all three Lift pumps and both Sump pumps, including but not limited to electromotors, unit substation enclosure, transformers, disconnect switches, HV fuses, cables to pump motors, control cables, and aboveground and underground conduits in accordance with Contract drawings and specifications.

6. New fence around the electrical equipment on the new concrete foundation.

i. Connect the new electrical system to Lift pumps D2 and D3 as well as Sump pumps S1 and S2, supply power and make pumps D2, D3, S1 and S2 ready for normal operation.

1.3.1.2 Option 1:

a. Remove trash and drain the inlet basin.

b. Disconnect the existing Lift pump D3 from the electrical system. Remove existing Lift pumps D1 and D3, associated motors, appurtenances, pipe supports and piping other than the section embedded in the concrete wall.

c. Provide the following items:

1. Two new identical Lift pump packages D1 and D3, including, but not limited to electromotors, pumps, couplings and appurtenances. The pumps must be axial flow type with total dynamic head (TDH) of 14 feet and capacity of 47,000 gallon per minutes (GPM). Consider 200 to 250 horsepower (hp) for the associated electromotors rating. Apply coating to exposed metal surfaces, if any.

2. Lift pumps discharge piping, supports and connections. Connect the new discharge lines to the existing pipes embedded in the concrete wall. Repair the embedded pipes as needed. Apply coating.

d. Connect the new electrical system to the new Lift pumps D1 and D3, supply power and make pumps D1 and D3 ready for normal operation. 1.3.1.3 Option 2 a. Provide and install new catwalk. b. Remove rust, clean and prepare the existing stair, ladder, railings, trash rack brackets, catwalk and flap gates for coating. Apply coating. 1.3.1.4 Option 3 a. Remove trash and drain the inlet basin. b. Inlet Basin: Clean concrete surfaces and remove loose concrete.

Where the rebars are exposed, remove the rust and coat the steel surfaces with coating. Repair the damaged concrete surfaces and seal the cracks. Apply Epoxy coating to concrete surfaces from floor to high level alarm water elevation. Perform the work in accordance with section 03 01 00 REHABILITATION OF CONCRETE and section 09 96 00 HIGH-PERFORMANCE COATINGS. c. Outlet Basin: Clean concrete surfaces and remove loose concrete.

Where the rebars are exposed, remove the rust, clean and coat the metal surfaces with coating. Repair the damaged concrete surfaces and seal the cracks. Apply Epoxy coating to concrete surfaces from floor to high level alarm water elevation. Perform the work in accordance with section 03 01 00 REHABILITATION OF CONCRETE and section 09 96 00 HIGH-PERFORMANCE COATINGS. d. Transport the existing trash racks from stored location to the job site. Remove rust, clean and prepare for coating. Apply coating.

Provide the missing wall bracket. Install the trash racks. 1.3.2 Location The work is located at Naval Air Station Lemoore (NASL) Stormwater Lift Station (B-986), approximately as indicated on the Contract drawings. The exact location will be shown by the Construction Manager (CM).

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. May 24, 2024

    Award notice

    Awarded to FRAWNER CORPORATION Anchorage for $8,995,000. SAM.gov, notice 633ab980591c4f54992df86fa2d5fb03

Points of contact