Vendor, Omaha, NE
Midlands Mechanical, Inc.
UEI PU2HJLMR81A9, CAGE 43M22
21 awards and $17,403,130 obligated between January 23, 2024 and October 26, 2026, 100% under full and open competition, against 2.5 offers on average where reported.
Industries
NAICS on the awards, by dollars.
| Industrial Building ConstructionNAICS 236210 | $11,597,925 |
| Plumbing, Heating, and Air-Conditioning ContractorsNAICS 238220 | $5,805,205 |
How it wins
Awards by competition, set-aside and type.
| Full and Open Competition | 21 |
| Delivery Order | 19 |
| Definitive Contract | 1 |
Hear when Midlands Mechanical, Inc. wins an award and when a contract it holds is about to end.Follow it
Contracts ending soon
Contracts Midlands Mechanical, Inc. holds whose performance ends in the next 19 months, by published end date. Each one is a recompete to prepare for.
- Ending
- 4
- Obligated so far
- $8,374,035
- Soonest
- November 5, 2026
The 4 contracts, the office behind each one and the dates are in the workspace. See them
Competes with
Vendors selling industrial building construction to United States Mint, by dollars.
| Lorenzon Construction, Inc.Philadelphia, PA | $9,929,257 |
| The Riff Group, LLCPhoenixville, PA | $3,988,899 |
| SPR Construction Corp.Denville, NJ | $2,386,276 |
| Ash & White Construction Co.Castle Rock, CO | $183,821 |
Awards
Every award in the window, by dollars obligated.
| Contract | Awarding office | Described as | Obligated |
|---|---|---|---|
| 2031JG22C00013Definitive Contract, January 29, 2024, Full and Open Competition, 2 offers | US Mint HeadquartersUnited States Mint | The Purpose of This Modification Is to Update the Contracting Officer'S Representative (Cor) on the Subject Contract from Jennifer Rheaume tNAICS 238220, PSC Z1EC | $5,805,205 |
| 2031JG25F00276Delivery Order, September 29, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | DN Roof Replacement & Cornice Repair ProjectNAICS 236210, PSC Z2EC | $5,280,782 |
| 2031JG26F00054Delivery Order, November 6, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | The Purpose of This Order Is for Construction of the IT Datacenter at the United States Mint-Denver. the Contractor Will Furnish the NecessaNAICS 236210, PSC Z2EC | $2,127,774 |
| 2031JG26F00083Delivery Order, February 27, 2026, Full and Open Competition | US Mint HeadquartersUnited States Mint | Emergency & Critical Power ModernizationNAICS 236210, PSC Z2EC | $2,031,603 |
| 2031JG25F00149Delivery Order, May 1, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | To Construct and Commission an Iso 8 Clean Room as Well as All Utilities/Infrastructure Needed to Support Functionality and Operation of theNAICS 236210, PSC Z2EC | $916,527 |
| 2031JG25F00170Delivery Order, May 5, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | DN Exterior RenovationNAICS 236210, PSC Z2EC | $261,049 |
| 2031JG25F00238Delivery Order, August 13, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | The Purpose of This Order Is to Install Utilities for the New Annealing Furnace AF-02 at the United States Mint-Denver.NAICS 236210, PSC Z2EC | $130,682 |
| 2031JG24F00437Delivery Order, September 20, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Tank 13 RoofNAICS 236210, PSC Z2EC | $125,639 |
| 2031JG23F00152Delivery Order, May 31, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Task Order 2031jg21d00035/2031jg23f00152- Utilities for N2 H2 Generators-Demolition of Exo Generator and Mezzanine-United States Mint- DenveNAICS 236210, PSC Z2EC | $124,088 |
| 2031JG25F00248Delivery Order, September 10, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | The Purpose of This Order Is the Inspection and Mapping of Sanitary Sewer Pipes in the Basement and Subbasement at the United States Mint-DeNAICS 236210, PSC Z2EC | $112,949 |
| 2031JG24F00438Delivery Order, September 20, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Vaf FilterNAICS 236210, PSC Z2EC | $99,912 |
| 2031JG23F00153Delivery Order, February 28, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Modification 2031jg21d00035/2031jg23f00153-P00001-Change Cor from Jared Stephens to Marcel MatosNAICS 236210, PSC Z2EC | $96,575 |
| 2031JG25F00182Delivery Order, June 11, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | The Purpose of This Order Is to Install New Fan Coil Units (Fcus) in Two IT Rooms (Room 112A and Room 112 A/V Closet) at the United States MNAICS 236210, PSC Z2EC | $63,242 |
| 2031JG24F00430Delivery Order, September 11, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Aluminum Grate PlatformsNAICS 236210, PSC Z2EC | $57,451 |
| 2031JG26F00217Delivery Order, September 17, 2026, Full and Open Competition | US Mint HeadquartersUnited States Mint | New Wastewater Line Spaleck 1ST FloorNAICS 236210, PSC Z2EC | $48,952 |
| 2031JG24F00372Delivery Order, August 21, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | AF-01 Flooring the Purpose of This Order Is to Provide Funding for Flooring for the Annealing Furnace Replacement Project at the United StatNAICS 236210, PSC Z2EC | $33,009 |
| 2031JG25F00029Delivery Order, November 21, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | DN Wastewater Treatment Tank RemovalNAICS 236210, PSC Z2EC | $32,237 |
| 2031JG25F00273Delivery Order, September 18, 2025, Full and Open Competition | US Mint HeadquartersUnited States Mint | The Purpose of This Order Is the Patching and Recoating of the Flooring for the Annealing Furnace Replacement Project at the United States MNAICS 236210, PSC Z2EC | $27,182 |
| 2031JG24F00173Delivery Order, January 30, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Task Order 2031jg21d00035-2031jg24f00173-Mechanical Demolition of Abandoned Equipment-United States Mint-DenverNAICS 236210, PSC Z2EC | $21,732 |
| 2031JG23F00338Delivery Order, January 23, 2024, Full and Open Competition | US Mint HeadquartersUnited States Mint | Modification 2031jg21d00035-2031jg23f00338-P00002-Floor Drain Replacement- Replacement of Sanitary Drain Pipes and Additional Piping ServiceNAICS 236210, PSC Z2EC | $6,540 |
| 2031JG21D00035August 13, 2024, Full and Open Competition, 3 offers | US Mint HeadquartersUnited States Mint | Exercise Oy 3 with a Pop of 10/01/2024 to 09/30/2025NAICS 236210, PSC Z2EC | $0 |
- Product and service codes
- Z2EC Repair Or Alteration Of Production BuildingsZ1EC Maintenance Of Production Buildings
- Transactions
- 48 across 21 awards