Skip to content
Abierto

Award notice, total small business set-aside, first published as solicitation

Buckhorn Tailwater - Award Notice

W912QR25BA012

Department of the Army, W072 Endist Louisville. Other Heavy and Civil Engineering Construction.

Awarded

Steel Factor Enterprises, LLC

$637,420.00 obligated so far on USAspending

Description

As published on SAM.gov with the solicitation of May 5, 2025.

Amendment 0001

Solicitation W912QR25BA012 is hereby amended as follows on 05 May 2025: Due to the incorrect DoDAAC being selected on the line items, Amendment 0001 hereby updates the DoDAAC from 12Z688 to 964839. *NOTE: The due date for bids has not been updated and remain 08 May 2025 at 10:00 AM ET* *NOTE: All amendments must be signed and submitted with the bid

Amendment 0001

DESCRIPTION: The U.S. Army Corps of Engineers (USACE) Louisville District intends to issue a Invitation for Bid (IFB) for Buckhorn Tailwater Bank Stabilization in Buckhorn, Kentucky. This project is a Design/Bid/Build where the streambank of Squabble Creek on the west side of Buckhorn Campground in Buckhorn, Kentucky was affected by a flood event in 2022. The streambank experienced severe erosion which is now affecting the adjacent camper pads.

Erosion damage to approx. 500-foot-long portion of the streambank along Squabble Creek is to be repaired. Main efforts include the following scope items: The repair will consist of regrading the stream bank and lining with rip rap stone protection. Additional repairs to several campsites will require grading, gravel camping pad and concrete camping pad placement. In addition, asphalt milling and overlay and subgrade repairs to the campground road will be included.

Squabble Creek has endangered darter species and will require erosion control BMPs.Contract duration is 60 calendar days from the Construction Notice to Proceed (NTP).TYPE OF CONTRACT AND NAICS: This IFB will be for one (1) Firm-Fixed-Price (FFP) contract. The North American Industrial Classification System Code (NAICS) for this effort is 237990 ?

Other Heavy and Civil Engineering Construction.TYPE OF SET-ASIDE: This acquisition will be advertised as 100% Small Business.SELECTION PROCESS: This is a Design/Bid/Build procurement, Invitation for Bid, sealed bid.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
Z5P8HZN2MCY8
CAGE
9XVR9
Vendor location
Richmond, KY
Contract
W912QR25CA005, definitive contract
Obligated
$637,420.00, potential $665,420
Actions
4 between May 1, 2025 and May 27, 2026
Competition
Full and Open Competition After Exclusion of Sources, 7 offers received
Set-aside reported
Small Business Set Aside - Total
Described as
Buckhorn Tailwater Bank Stabilization
Match
award number W912QR25CA005 equals the contract number; same awarding office W912QR (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. April 7, 2025

    Solicitation

    Buckhorn Tailwater Stabilization

    Due May 8, 2025 at 11:00 AM EDT. SAM.gov, notice 328115e76d3d47f0a13849d57186c978

  2. April 7, 2025

    Solicitation

    Buckhorn Tailwater Stabilization

    Due May 8, 2025 at 11:00 AM EDT. SAM.gov, notice 49de27f9b3c9489ebccb0a0258fbcf82

  3. April 7, 2025

    Solicitation

    Buckhorn Tailwater Stabilization

    Due May 8, 2025 at 11:00 AM EDT. SAM.gov, notice 63dd51341ac248e0b1102806ddedb1d2

  4. April 17, 2025

    Solicitation

    Buckhorn Tailwater Stabilization

    Due May 8, 2025 at 11:00 AM EDT. SAM.gov, notice 587c739fa34b49368a783cef810beb23

  5. May 5, 2025

    Solicitation

    Buckhorn Tailwater Stabilization - ****Amendment 0001 Issued****

    Due May 8, 2025 at 10:00 AM EDT. SAM.gov, notice bd27e04d455c44c988222a267488d18b

  6. May 19, 2025

    Award notice

    Awarded to Steel Factor Enterprises, LLC Richmond for $498,940. SAM.gov, notice 29d11d13316943439628cab755725730