Skip to content
  • 6,512 federal solicitations are open right now. How many of them are yours?
  • New solicitations are posted every day. The ones you never saw are the ones you cannot win.
  • Stop checking SAM.gov every morning. Let the contracts that fit your business come to you.
  • Tell Abierto what you sell in one sentence. AI reads every open solicitation for you.
  • Deadlines are short. Hear about a solicitation the day it is posted, not the week it closes.
  • Amendments move deadlines. Watch a solicitation and Abierto tells you when it changes.
  • See which contracts in your field are about to end, and who holds them today.
  • Plans from $39 a month. See your matches before you pay.
See plans
AbiertoGet started

Combined synopsis and solicitation, service-disabled veteran-owned small business set-aside

Boiler 3 Oxygen Analyzer and Steam Flow Meter

36C24727Q0050

Department of Veterans Affairs, 247-Network Contract Office 7. Plumbing, Heating, and Air-Conditioning Contractors.

Offers due

October 26, 2026 at 11:00 AM EDT

2 days from now. Posted October 22, 2026, first published October 15, 2026.

Get an email when this is amended, when the deadline moves and when it is awarded.Watch it

Next from this buyer

Similar, open now

All 42 open in plumbing, heating, and air-conditioning contractors

Description

As published on SAM.gov.

Questions and Answers 36C24727Q0050 Boiler #3 Oxygen Analyzer and Steam Flow Meter RFI Responses Where should the output signals from the new steam flow meter and O2 analyzer terminate? For example, the existing building automation system (BAS), the existing Boiler 3 burner/boiler controls, or a local display only. Burner 3 boiler/burner controls where applicable and local display. Does the government require active O2 trim control to the burner fuel/air ratio, or monitoring and display of the O2 only? Oxygen analyzer must send signals/information to combustion controls to control trim. What is the material of construction for the stack? Is it single or double wall? Stack is double walled. Inside material is steel; outside material is galvanized steel. Stack is 36 D Selkirk Metalbestos Model P.S. Current operating pressure and temperature of the system for boiler #3? Design pressure is 200 psi. Typical operating pressure is 82 psi. Typical operating temperature is about 330 degrees Fahrenheit. What are the available outputs on the physical steam flow meter (e.g., 4-20 mA, Modbus RTU, BACnet MS/TP)? 4-20 mA analog. Is the flow meter wired directly into an analog terminal block on the CB Hawk, or is it wired directly to the facility s Building Automation System (BMS)? Steam flow meter is wired into local CB Hawk analog terminal block. Please provide nameplates for the existing oxygen analyzer and steam flow meter. Oxygen analyzer nameplate: Steam flow meter nameplate:

Attachments

Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. October 15, 2026

    Combined synopsis and solicitation

    SRVS-SUP Team 1 | Boiler 3 Oxygen Analyzer and Steam Flow Meter | CO: Sheryl Harris; Assn. Date: 09/30/26; EAD: 11/15/26

    Due October 26, 2026 at 11:00 AM EDT. SAM.gov, notice fce6c9ad5d7e407e9ea31cb61a6881ac

    1 revisions on SAM
    • October 15, 2026: publish, combined synopsis and solicitation
  2. October 22, 2026

    Combined synopsis and solicitation

    Due October 26, 2026 at 11:00 AM EDT. SAM.gov, notice fd26eac21a2a43e9afa95a8149c0c136

    2 revisions on SAM
    • October 22, 2026: publish, combined synopsis and solicitation
    • October 15, 2026: publish, combined synopsis and solicitation

Points of contact