Skip to content
Abierto

Combined synopsis and solicitation, total small business set-aside

Loch Raven VAMC Bldg. 6 Boiler Replacement REQUEST FOR QUOTE

36C24526Q0118

Department of Veterans Affairs, 245-Network Contract Office 5. Plumbing, Heating, and Air-Conditioning Contractors.

Awarded

Integrated Combustion Solutions LLC

$79,976.00 obligated so far on USAspending

Description

As published on SAM.gov.

Page 1 of 1 SCOPE OF WORK LR Bldg 6 Boiler Replacement Project:

512-25-052 GENERAL SCOPE OF WORK: The contractor will provide all material, labor, equipment, and supervision necessary to complete the above-named project at the VA Maryland Health Care System (VAMHCS), Loch Raven Campus. Contractor is to remove the existing boiler in the Building 6 mechanical room a Weil McClain Water Tube Boiler rated at 209MBH and replace it with a CSD-1 compliant boiler on the existing equipment pad.

The old boiler should be properly disposed of after removal with disposal receipts provided to VA. New boiler should use existing utility lines for tie-in s where possible except for the existing Vent line. Per NBCI code, the vent line must be PVC and the atmospheric metal duct deteriorate. Contractor to confirm feasibility of utility line tie-ins and vent line replacement during pre-bid walk through. Utility tie-ins may require minor modifications to fit the existing space and new boiler.

Contractor to follow boiler manufacturer install instructions for proper installation. Contractor will provide materials to meet ICRA requirements set forth by safety based on the work to be completed. Contractor to provide warranty and start-up after install of new boiler to confirm proper operation. Remove and dispose of existing Weil McClain Water Tube Boiler (209MBH). Provide disposal receipts to VA. Provide and install CSD-1 compliant Boiler sized to match existing boiler.

Utilize existing utility lines for tie-ins where possible except for the vent line. New PVC vent line must be installed. Contractor to adhere to any and all local, state, federal, and VA specifications and guidelines. Work will be completed in 30 calendar days from Notice To Proceed.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
CAB7S2EULDG8
CAGE
16RE4
Vendor location
Mount Airy, MD
Contract
36C24526P0521, purchase order
Obligated
$79,976.00
Actions
1 between July 17, 2026 and July 17, 2026
Competition
Competed Under SAP, 3 offers received
Set-aside reported
Small Business Set Aside - Total
Described as
Replace Boiler Loch Raven Building 5
Match
solicitation number 36C24526Q0118 equals the FPDS solicitation identifier; same awarding office 36C245 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. November 14, 2025

    Combined synopsis and solicitation

    Due December 3, 2025 at 11:00 AM EST. SAM.gov, notice db1c8c50026d464eba2a05b417f0a918

Points of contact