Solicitation
Trenching, Conduit and Ground-well Installation
19JM3727Q0002
Department of State, U.S. Embassy Kingston. Site Preparation Contractors.
Offers due
November 25, 2026 at 2:00 PM EST
25 days from now. Posted October 28, 2026.
Get an email when this is amended, when the deadline moves and when it is awarded.Watch it
Next from this buyer
- Hydrogen Generator for Gas ChromatographyCombined synopsis and solicitationNAICS 334516Outside the USPR16327481Closes in 13 daysNov 13
Similar, open now
- Instrument Landing Structure (ILS)
Department of the Army, W076 Endist FT Worth
Sources soughtSmall businessNAICS 238910LouisianaW9126G27RA021Closes in 2 daysNov 2 - Demolish Dormitory 2425
Department of the Air Force, FA4897 366 Cons PKP
Sources soughtNAICS 238910Mountain Home AFB, IDFA489727QSS11Closes in 3 daysNov 3 - Hickman Wildlife Water Catchment and Pipe Fence
Bureau of Land Management, New Mexico State Office
Combined synopsis and solicitationSmall businessNAICS 238910New Mexico140L1726Q0054Closes in 9 daysNov 9
Description
As published on SAM.gov.
Description
The United Stated Embassy in Kingston is requesting proposals for Trenching, Conduit And Ground-Well Installation in various locations on the Embassy compound. The contractor will provide all labor, equipment, supervision, material specific to the back filling and compaction and management needed to complete the job
Infrastructure Support System - Handhole / Underground Conduit System
Trenching
- Nine locations have been identified requiring trench work.
- Thirteen locations have been identified requiring trench work.
- Before excavation, the Contractor shall locate and verify all existing utilities in the proposed trench alignment.
- If excavation interferes with existing drains, piping, or structures, the Contractor shall immediately notify, in writing, the COR and provide temporary protection for these systems before proceeding.
Trenching from Handholes
- The Contractor shall make wall penetrations into existing manholes/handholes as required for the number and size of conduits entering and exiting each structure, in accordance with the drawings.
Conduit
- Existing conduit shall remain in place unless the drawings specifically direct removal or modification.
- Under grass, soil, the Contractor shall install Schedule 80 PVC conduit with a minimum cover of 24 inches (610 mm) from finished grade to top of conduit, or as indicated on the drawings, whichever is greater.
- All underground 90 degree bends with a 12inch (305 mm) radius shall use prefabricated sweeping bends.
- Above grade, all underground PVC conduit shall transition to rigid galvanized steel (RGS) using PVC to RGS couplers.
- The Contractor shall install pull lines in all new conduit runs.
Soil and Backfill Materials
Soil Materials
The Contractor shall provide all labor and materials for soil and backfill, where required.
- Select Backfill: ASTM D 2487 soil classification groups SW, SP, and SM, or combinations thereof; free of rock or gravel larger than 3 inches (75 mm), debris, waste, frozen materials, vegetation, and other deleterious matter.
- Asphalt/Concrete Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 95% passing a 11/2inch (40 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
- Base Gravel: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; 100% passing a 1inch (25 mm) sieve and not more than 8% passing a 1/4inch (6.4 mm) sieve.
- Sand Cushion: ASTM C 33 fine aggregate, natural or manufactured sand.
Placement and Compaction
- Place backfill and fill in layers not exceeding:
- 8 inches (203 mm) loose thickness for heavy compaction equipment;
- 4 inches (102 mm) loose thickness when compacted by hand-operated tampers.
- Place backfill and fill evenly to the required elevations, uniformly along their full length.
- Compact soil materials to not less than the following percentages of maximum dry unit weight per ASTM D 1557:
- Under lawns or unpaved areas: scarify and re-compact top 6 inches (152 mm) below subgrade and compact each layer to 85%.
- Utility trenches: compact each layer of initial and final backfill to 85%.
Anticipated Period of Performance: a base period of twenty-one (21) days after contract award
Eligibility and Registration
Offerors must hold an active registration in the System for Award Management (SAM.gov) when they submit a proposal and at award.
Local Insurance and Defense Based Act (DBA) Insurance.
A site visit has been scheduled for Friday, November 06, 2026 at 10 a.m.
Offeror interested in attending must email kingstonquotes@state.gov with the caption ‘TRENCHING - SITE VISIT’. To ensure access you are required to be approved prior to the visit. You are to provide the full names of the attendees, the vehicle information to include make, model, color and plate number of the vehicle being driven. The email must be sent no later than Wednesday, November 04, 2026 by 2 pm.
Completed proposal are to be email to kingstonquotes@state.gov in PDF format by the deadline stipulated.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- 19JM3727Q0002_Trenching and Conduit Installation .pdf1.7 MB, October 28, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 28, 2026
Solicitation
Due November 25, 2026 at 2:00 PM EST. SAM.gov, notice 79b69696ceed4090b5e4db5a94cb31be
1 revisions on SAM
- October 28, 2026: publish, solicitation
Points of contact
- U.S. Embassy Kingston Procurement Officekingstonquotes@state.gov8767026000
- Handel BlakeBlakeHA@state.gov8767026393