Vendor, Las Cruces, NM
Sedona- Nasco Joint Venture
UEI GLSLZ75HV2T5, CAGE 8GKA5
64 awards and $44,125,979 obligated between January 4, 2024 and June 3, 2026, 100% under full and open competition, against 9.0 offers on average where reported.
Industries
NAICS on the awards, by dollars.
| Industrial Building ConstructionNAICS 236210 | $44,128,479 |
| Commercial and Institutional Building ConstructionNAICS 236220 | -$2,500 |
How it wins
Awards by competition, set-aside and type.
| Full and Open Competition After Exclusion of Sources | 64 |
| 8A Competed | 1 |
| Delivery Order | 63 |
Hear when Sedona- Nasco Joint Venture wins an award and when a contract it holds is about to end.Follow it
Contracts ending soon
Contracts Sedona- Nasco Joint Venture holds whose performance ends in the next 19 months, by published end date. Each one is a recompete to prepare for.
- Ending
- 5
- Obligated so far
- $12,972,127
- Soonest
- November 23, 2026
The 5 contracts, the office behind each one and the dates are in the workspace. See them
Competes with
Vendors selling industrial building construction to Department of the Army, by dollars.
| Parsons Government Services Inc.Pasadena, CA | $174,366,697 |
| Cci Prime Contractors, LLCAnchorage, AK | $92,491,468 |
| SK Construction and Management Inc.Cortlandt Manor, NY | $36,033,860 |
| Greenland Enterprises, Inc.Newport News, VA | $5,590,677 |
| Chugach Pacific Solutions LLCDededo, GU | $2,899,615 |
| Amana Contracting and Steel Buildings Company LLCDubai | $973,924 |
Awards
Every award in the window, by dollars obligated.
| Contract | Awarding office | Described as | Obligated |
|---|---|---|---|
| W911KF26FA008Delivery Order, December 17, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Modernization of Building 114 Facilities in Conjunction with the Usec Project.NAICS 236210, PSC Z1AA | $4,904,827 |
| W911KF25FA012Delivery Order, August 19, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Building 409 Roof and Havc System RepairNAICS 236210, PSC Z1AA | $3,956,726 |
| W911KF24F0052Delivery Order, April 17, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Fire Suppression Repair in BLDG 1500NAICS 236210, PSC Z1AA | $3,373,788 |
| W911KF24F0123Delivery Order, September 27, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QE16 Fall ProtectionNAICS 236210, PSC Z1AA | $2,459,305 |
| W911KF24F0100Delivery Order, August 20, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Replace Chiller and Boilers at BLDG 31NAICS 236210, PSC Z1AA | $2,219,000 |
| W911KF25F0067Delivery Order, July 15, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Fire Alarm System Repair (Bldg 474&475)NAICS 236210, PSC Z1AA | $2,083,247 |
| W911KF25F0062Delivery Order, May 28, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD38 Railroad RepairsNAICS 236210, PSC Z1AA | $1,894,772 |
| W911KF24F0062Delivery Order, May 20, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | FY24 Railroad RepairsNAICS 236210, PSC Z1AA | $1,861,437 |
| W911KF24F0084Delivery Order, July 25, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Satoc Minor Construction 2ND Option YearNAICS 236210, PSC Z1AA | $1,790,229 |
| W911KF24F0061Delivery Order, May 20, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD66 Building 130 RenovationNAICS 236210, PSC Z1AA | $1,706,538 |
| W911KF24F0030Delivery Order, February 13, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Replace Regulators at Nichols SubstationNAICS 236210, PSC Z1AA | $1,632,500 |
| W911KF24F0122Delivery Order, September 25, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD22 Building 104 and 522 Roof RepairsNAICS 236210, PSC Z1AA | $1,620,545 |
| W911KF25F0022Delivery Order, January 14, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Overhead DoorsNAICS 236210, PSC Z1AA | $1,415,634 |
| W911KF26FA033Delivery Order, March 16, 2026, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Contractor Shall Provide All Material, Transportation, Labor, Equipment, Coordination, Planning, and Supervision Necessary to Repair DamagedNAICS 236210, PSC Z1AA | $1,278,578 |
| W911KF25F0047Delivery Order, April 16, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD56 Ampv New Open ShedNAICS 236210, PSC Z1AA | $1,131,237 |
| W911KF24F0121Delivery Order, September 25, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Anad Power Pole ReplacementNAICS 236210, PSC Z1AA | $1,102,336 |
| W911KF25F0061Delivery Order, June 2, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QE43-25 Replace Water Main Feed LineNAICS 236210, PSC Z1AA | $1,098,135 |
| W911KF24F0093Delivery Order, August 14, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Repair BLDG 114 Water Treatment PlantNAICS 236210, PSC Z1AA | $868,465 |
| W911KF24F0107Delivery Order, September 12, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Building 47 Roof and Wall RepairNAICS 236210, PSC Z1AA | $799,401 |
| W911KF26FA003Delivery Order, December 10, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Dpw, Satoc, QD40-23, FY25 Igloo Grubbing,NAICS 236210, PSC Z1AA | $748,749 |
| W911KF24F0102Delivery Order, August 27, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Anmc Igloo GrubbingNAICS 236210, PSC Z1AA | $710,848 |
| W911KF24F0118Delivery Order, September 24, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD73 Building 130 West Section RepairsNAICS 236210, PSC Z1AA | $640,174 |
| W911KF24F0032Delivery Order, February 22, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Floor Repair and Crane Install, BLDG 55NAICS 236210, PSC Z1AA | $515,500 |
| W911KF24F0117Delivery Order, September 23, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Resurface Ra RoadsNAICS 236210, PSC Z1AA | $486,131 |
| W911KF26FA042Delivery Order, May 4, 2026, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Replace Emergency Power at Access Control Points and Visitor Control Center. All Work Shall Be Performed in Accordance with the Contract SpeNAICS 236210, PSC H230 | $464,499 |
| W911KF25F0041Delivery Order, April 8, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD14 BLDG 38 Turn LaneNAICS 236210, PSC Z1AA | $431,531 |
| W911KF26FA010Delivery Order, January 14, 2026, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | The Work Shall Be Performed Under This Contract Consists of Furnishing All Material, Transportation, Labor, Equipment, Coordination, PlanninNAICS 236210, PSC Z1AA | $416,340 |
| W911KF24F0058Delivery Order, May 13, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Bldg. 401B Salt Crock RepairNAICS 236210, PSC Z1AA | $395,092 |
| W911KF26FA012Delivery Order, January 15, 2026, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Contractor Shall Provide All Material, Transportation, Labor, Equipment, Coordination, Planning, and Supervision Necessary to Perform the ReNAICS 236210, PSC Z1AA | $359,620 |
| W911KF25F0054Delivery Order, April 17, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Replace Generators, Buildings 2 and 107NAICS 236210, PSC Z1AA | $301,387 |
| W911KF24F0023Delivery Order, January 30, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Install Lift Station GeneratorsNAICS 236210, PSC Z1AA | $276,000 |
| W911KF24F0064Delivery Order, June 17, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Provide Power to Anad Wood YardNAICS 236210, PSC Z1AA | $232,962 |
| W911KF25F0007Delivery Order, November 21, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QE05 B35 SLC RepairNAICS 236210, PSC Z1AA | $213,706 |
| W911KF25F0009Delivery Order, November 21, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | RE-PAVE Parking Lot at Building 199NAICS 236210, PSC Z1AA | $194,613 |
| W911KF24F0116Delivery Order, September 23, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QC25 Building 31 Saret TransitionNAICS 236210, PSC Z1AA | $152,734 |
| W911KF24F0042Delivery Order, March 19, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD28 Truss RepairsNAICS 236210, PSC Z1AA | $148,513 |
| W911KF26FA005Delivery Order, November 21, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | The Visual, Non-Destructive, Roof Wood Truss Structural Condition Inspections and Recommend Repairs at 27 Buildings and the CDC Building 150NAICS 236210, PSC Z1AA | $100,096 |
| W911KF24F0097Delivery Order, August 21, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | DLA Overhead Door Maintenance (FY24)NAICS 236210, PSC Z1AA | $94,346 |
| W911KF22F0062Delivery Order, June 26, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Repair/Rebuild of CompressorsNAICS 236210, PSC Z1AA | $86,455 |
| W911KF24F0120Delivery Order, September 25, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Building 109 Fire Pump RepairNAICS 236210, PSC Z1AA | $71,519 |
| W911KF26FA002Delivery Order, November 7, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD06-23 Ec Unit Control UpgradeNAICS 236210, PSC Z1AA | $52,314 |
| W911KF25F0019Delivery Order, January 7, 2025, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD47 Upv InspectionsNAICS 236210, PSC Z1AA | $51,056 |
| W911KF24F0051Delivery Order, April 10, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QA66 Sulfuric Acid LineNAICS 236210, PSC Z1AA | $41,268 |
| W911KF24F0081Delivery Order, July 24, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Heat Detector Installation in BLDG 1500NAICS 236210, PSC Z1AA | $32,254 |
| W911KF24F0103Delivery Order, September 9, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Acwa Igloo GrubbingNAICS 236210, PSC Z1AA | $24,454 |
| W911KF22F0098Delivery Order, March 19, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Roof Repairs, Building 130NAICS 236210, PSC Z1AA | $14,066 |
| W911KF24F0016Delivery Order, August 8, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QC15 Repair HVAC System, BLDG 134NAICS 236210, PSC Z1AA | $6,000 |
| W911KF24F0031Delivery Order, February 20, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Lightning Detection System FenceNAICS 236210, PSC Z1AA | $3,050 |
| W911KF22F0014Delivery Order, March 26, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QB87-21 Winch Test Bolt PlateNAICS 236210, PSC Z1AA | $0 |
| W911KF23F0054Delivery Order, March 18, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Install Water Enclosure, Building 503NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0057Delivery Order, March 7, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Construct Camera Cooling SystemNAICS 236210, PSC Z1AA | $0 |
| W911KF23F0063Delivery Order, January 18, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | FY23 Igloo GrubbingNAICS 236210, PSC Z1AA | $0 |
| W911KF23F0072Delivery Order, January 8, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QC50 Water Flow Gauging Station, Extend Pop 31 Jan 24NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0082Delivery Order, March 11, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QD01 Upgrade Power, Building 106NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0091Delivery Order, January 31, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Open Shed BLDG 4NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0092Delivery Order, June 5, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QC72 Lightning Protection SystemNAICS 236210, PSC Z1AA | $0 |
| W911KF23F0099Delivery Order, January 11, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Fire Shutters Installation Building 1500NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0100Delivery Order, January 11, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Roof Repair Building 201NAICS 236210, PSC Z1AA | $0 |
| W911KF23F0101Delivery Order, September 16, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Satoc Minor Construction 1ST Option YearNAICS 236210, PSC Z1AA | $0 |
| W911KF24F0002Delivery Order, January 4, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Replace Rolling Service Doors, BLDG 79NAICS 236210, PSC Z1AA | $0 |
| W911KF22D0001October 9, 2024, Full and Open Competition After Exclusion of Sources, 9 offers | W6QK ACC AnadDepartment of the Army | Satoc Minor Construction Base YearNAICS 236210, PSC Z1AA | $0 |
| W9126G21F0017Delivery Order, March 7, 2024, Full and Open Competition After Exclusion of Sources | W076 Endist FT WorthDepartment of the Army | Deobligate Minimum Guarantee as IT Was Met Under an FY23 Task Order.NAICS 236220, PSC Y1PZ | -$2,500 |
| W911KF23F0041Delivery Order, April 3, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | QB91 Replace Chillers and BoilersNAICS 236210, PSC Z1AA | -$105,677 |
| W911KF23F0088Delivery Order, January 22, 2024, Full and Open Competition After Exclusion of Sources | W6QK ACC AnadDepartment of the Army | Test Stand Contingency FundsNAICS 236210, PSC Z1AA | -$227,821 |
- Product and service codes
- Z1AA Maintenance Of Office BuildingsH230 Equipment and Materials Testing: Mechanical Power Transmission EquipmentY1PZ Construction Of Other Non-Building Facilities
- Transactions
- 197 across 64 awards