Skip to content
  • 8,082 federal solicitations are open right now. How many of them are yours?
  • New solicitations are posted every day. The ones you never saw are the ones you cannot win.
  • Stop checking SAM.gov every morning. Let the contracts that fit your business come to you.
  • Tell Abierto what you sell in one sentence. AI reads every open solicitation for you.
  • Deadlines are short. Hear about a solicitation the day it is posted, not the week it closes.
  • Amendments move deadlines. Watch a solicitation and Abierto tells you when it changes.
  • See which contracts in your field are about to end, and who holds them today.
  • Plans from $39 a month. See your matches before you pay.
See plans
AbiertoGet started

Combined synopsis and solicitation, total small business set-aside

LP-1001CA Antenna Repair

WX01355Y2026T

Federal Emergency Management Agency, National Continuity Section. Power and Communication Line and Related Structures Construction.

Response deadline

February 27, 2026 at 12:00 PM EST

Closed 255 days ago. Posted February 23, 2026, first published February 13, 2026. Scheduled to archive March 14, 2026.

Get the next one like this from Federal Emergency Management Agency by email, the day it is posted.Find my opportunities

This one closed in 2026

11 like it are open now in power and communication line and related structures construction

All 11 open in power and communication line and related structures construction

Description

As published on SAM.gov.

Questions and Answers: 

No additional photos of the antenna can be provided. 

  1. Condition of Antenna Element #19
    Can the Government confirm whether antenna element #19 is structurally intact and requires only re-securing, or if any visible damage has been identified?

Appears to be structurally intact from the ground, believe only needs resecured.

  1. Scope Clarification – Potential Damage
    If the element or mounting assembly is found to be damaged beyond repair during inspection, should the contractor limit the effort to documentation and reporting, or is replacement anticipated under the base scope?

As per SOW Specific 1 d); a spare LP-1001CA is crated on-site. In the event other bolt-on parts are damaged, contractor will replace as needed. The element and mounting assembly are both bolt-on parts to the boom.

  1. Government Furnished Hardware
    Please confirm that all stainless steel hardware required for reinstallation will be provided as Government Furnished Equipment (GFE).

FEMA will provide all hardware to complete the repair.

  1. Tower Configuration & Access
    Can the Government confirm the configuration of the 80-foot Valmont tower (e.g., self-supporting lattice or monopole with ladder access) and whether any special access or escort requirements apply?

Tower is an 80ft Valmont 3002 Self-Supporting lattice. The USAP LP-1001CA is mounted atop the tower. The LP-1001CA is not designed, rated, or certified for personnel climbing, walking on, or otherwise placing body weight on the boom or elements.

The facility is secure and will require government escort at all times. All personnel visiting will have to submit site access requests at least 72 hours prior.

  1. Site Logistics & Work Window
    Are there specific work-hour restrictions, security procedures, or escort scheduling requirements that may affect mobilization and execution timing?

Site hours are M-F 0700-1530, an escort will be provided during those times.

  1. Independent Government Estimate (IGE)
    For pricing alignment purposes, is the Independent Government Cost Estimate available for disclosure, or can the Government provide a not-to-exceed budget range?

This information is not available for disclosure. 

You are requested to provide firm-fixed pricing for the services specified in the Statement of Work (SOW). Funding has been obtained for this proposed procurement in an amount equal to or greater than the Independent Government Cost Estimate (IGCE). The Government requests pricing for the services listed in the SOW to be in effect for thirty (30) days after the date of your RFQ response. Award will be made to the lowest priced, technically acceptable proposal. The technical approach should not include prices. The price breakdown should be provided as a separate document.

Attachments

Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. February 13, 2026

    Combined synopsis and solicitation

    Due February 27, 2026 at 12:00 PM EST. SAM.gov, notice 675d37311b994d2f9b3bb1e25e9e9eb0

    2 revisions on SAM
    • February 23, 2026: publish, combined synopsis and solicitation
    • February 13, 2026: publish, combined synopsis and solicitation
  2. February 23, 2026

    Combined synopsis and solicitation

    Due February 27, 2026 at 12:00 PM EST. SAM.gov, notice ce2ad27c60b14b4a85462d3b0fe88563

    2 revisions on SAM
    • February 23, 2026: publish, combined synopsis and solicitation
    • February 13, 2026: publish, combined synopsis and solicitation

Points of contact