Skip to content
  • 8,082 federal solicitations are open right now. How many of them are yours?
  • New solicitations are posted every day. The ones you never saw are the ones you cannot win.
  • Stop checking SAM.gov every morning. Let the contracts that fit your business come to you.
  • Tell Abierto what you sell in one sentence. AI reads every open solicitation for you.
  • Deadlines are short. Hear about a solicitation the day it is posted, not the week it closes.
  • Amendments move deadlines. Watch a solicitation and Abierto tells you when it changes.
  • See which contracts in your field are about to end, and who holds them today.
  • Plans from $39 a month. See your matches before you pay.
See plans
AbiertoGet started

Special notice, total small business set-aside

Amend 01 Bldg 45 Porches and Brick Restoration

W91QF425BA0130001

Department of the Army, W6QM Micc-Ft Leavenworth. Commercial and Institutional Building Construction.

Response deadline

September 18, 2025 at 3:00 PM EDT

Closed 416 days ago. Posted September 10, 2025. Scheduled to archive October 3, 2025.

Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities

This one closed in 2025

189 like it are open now in commercial and institutional building construction

All 189 open in commercial and institutional building construction

Description

As published on SAM.gov.

This is an amnedment to publicize all the questions from the site vist for Bldg. 45 Porches and Brick Restoration.

DPW Responses to Contractor Questions for Solicitation W91QF425BA013 Ft. Leavenworth Bldg. 45 Porches & Brick Renovation
1. Do the Superintendent, SSHO and QC Manager need to be 3 separate
individuals?
DPW: Only the SSHO and the QC Manager may be the same person.
2. Can the period of performance be extended after award once the material/equipment
lead times are confirmed due to current market conditions for the equipment for this project?
DPW: Yes, the period of performance may be extended, but it may not be necessary.
3. Please provide the site visit attendee sign in sheet.
DPW: As discussed during the walk-thru meeting, DPW will not be able to provide the signsheets.This is a government document.
4. Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.
“DPW: We can find no records of the existing standing seam roofing on the north or south porch roofs.”
5. Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
DPW: No asbestos is known to be on or near the scope area of this project.
6. Is this project tax exempt?
DPW: Yes, this project is tax exempt. We will request a tax exemption when the award is issued.
7. When do you anticipate on site work starting?
DPW: We anticipate on-site construction activities starting as early as 2 – 3 weeks after proposals are received.

8. Are third party inspections required?
DPW: No third party inspections are required, but DPW will generally review Construction and SHPO or others may come by to inspect.
9. Is permitting required?
DPW: No permitting is required.

Attachments

Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. September 10, 2025

    Special notice

    Due September 18, 2025 at 3:00 PM EDT. SAM.gov, notice 0c55a8ff2b7f412783eee235ffcdd5be

    1 revisions on SAM
    • September 10, 2025: publish, special notice

Points of contact