Skip to content
  • 6,816 federal solicitations are open right now. How many of them are yours?
  • New solicitations are posted every day. The ones you never saw are the ones you cannot win.
  • Stop checking SAM.gov every morning. Let the contracts that fit your business come to you.
  • Tell Abierto what you sell in one sentence. AI reads every open solicitation for you.
  • Deadlines are short. Hear about a solicitation the day it is posted, not the week it closes.
  • Amendments move deadlines. Watch a solicitation and Abierto tells you when it changes.
  • See which contracts in your field are about to end, and who holds them today.
  • Plans from $39 a month. See your matches before you pay.
See plans
AbiertoGet started

Award notice, 8(a) sole source

Bldg. 1025 HVAC at Kirtland AFB

W912PP26QA045

Department of the Army, W075 Endist Albuquerque. Plumbing, Heating, and Air-Conditioning Contractors.

Awarded

Colt Builders Inc.

$207,214.00 on the award notice, September 29, 2026, contract W912PP26PA040

Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities

This one was awarded in 2026

44 like it are open now in plumbing, heating, and air-conditioning contractors

All 44 open in plumbing, heating, and air-conditioning contractors

Description

As published on SAM.gov.

This action was awarded as an 8(a) Sole Source Set-Aside under the authority of section 8(a) of the Small Business Act.

The contractor shall furnish all parts, material, labor, equipment and supervision necessary to complete the work for Building 1025 HVAC.

  1. Construction
    1. Contractor to provide and install an 8.5”x20.5” duct hood over the air compressor heat exhausts that transition to 14” ø round duct. Duct hood must be detachable to allow for the removal of the compressor top plate for maintenance.
    2. Contractor to remove SF-1 and wall louver. Expand existing 12”x18” wall penetration to 18”x18” penetration on the South wall.
    3. Install wall mounted exhaust fan rated for 1500 CFM @ 1” W.C. with using single phase 208V with soft start motor. Fan and motor must be rated to handle 140°F exhaust air. Provide 18”x18” ducted exhaust plenum 2’ into the mechanical room.
    4. Route 14”ø duct from each compressor into the 18”x18” plenum. Utilize conical fittings for branch take-offs and 30° minimum rectangular to round transitions and 1.5D round elbows.
    5. Provide gasketed low leakage motorized control dampers on each 14”ø duct between the hood and the exhaust plenum.
    6. Contractor to provide a 3-ton (36,000 BTU/hr) wall mounted mini split air conditioning unit on west wall above the compressed air desiccant driers. Mount wall mounted unit on available space without moving existing compressed air piping or conduit. Secure unit to wall per manufacturer instructions. Route condensate to nearest floor sink. Terminate condensate pipe above floor sink rim. Size per manufacturer requirements.
    7. Contractor to provide mini split condensing unit with high ambient kit by the same manufacturer. Locate exterior unit between stairs to electrical room and mechanical room. Secure unit to the ground per manufacturer instructions or mounted on C-channel with concrete anchors. Mini split must be 208V single phase.
    8. Contractor to provide and install refrigerant line sets between mini split per manufacturer instructions. Flash and seal new penetration for line set.
    9. Provide controls for equipment as follows: Exhaust fan must start when either compressor activates. Fan must remain on for at least 5 minutes (adjustable up to at least 15 minutes) after compressor turns off. Motorized control dampers must open when associated air compressor is activated. Damper must stay open until the exhaust fan turns off. Provide duct access panel for each damper on the bottom of the duct. Provide thermostat for new mini split. Set temperature to 85°F (adjustable).
    10. All new duct and duct connections shall be sealed to Class A and hung from the structure or mechanical room walls (where allowed) per SMACNA HVAC Duct Construction Standards.
    11. Provide 1in. W.C. Duct Pressure Classification on all exhaust duct systems, provide a minimum 22 Ga. Galvanized sheet metal meeting ASTM A924/A924M and ASTM A653/653M for all exhaust duct as indicated on the supplemental drawings.
    12. Provide power to the new exhaust fan and motorized control dampers from Panel P1. Reuse of conduit from demolished supply fan is acceptable provided it meets all NEC requirements. Provide power to mini split air conditioner from panel LM1. All wiring must be provided per NEC. Provide disconnects to exhaust fan, condensing unit and indoor unit per UFC 3-410-01.
    13. Contractor will need to be escorted at all times with the construction schedule coordinated with the facility user. 
    14. All new penetrations between the electrical and mechanical rooms must be sealed with fire caulk.
    15. The North and East walls in the Mechanical Room cannot have any new penetration or be utilized to mount hang or hang any new equipment.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. September 29, 2026

    Award notice

    Awarded to Colt Builders Inc. for $207,214. SAM.gov, notice 40af08092fb74ec19f2255df1ca9efb6

    1 revisions on SAM
    • September 29, 2026: publish, award notice