FY26 Brazos Island Harbor (BIH) Texas, Entrance and Jetty Channel Hopper Maintenance Dredging, Cameron County, Texas

W912HY26X1B38

Department of the Army, W076 Endist Galveston. Other Heavy and Civil Engineering Construction.

Response deadline

February 4, 2026 at 11:00 AM EST

Closed 227 days ago. Posted January 20, 2026. Scheduled to archive February 19, 2026.

Description

As published on SAM.gov.

The scope of the FY26 Brazos Island Harbor (BIH) Entrance and Jetty Channel maintenance dredging job will consist of dredging approximately 450,000 cubic yards of the Brazos Island Harbor, with five projected (5) options that relate to trail suction dredging and beach placement on South Padre Island. Schedule No. 1, Hopper dredging of BIH Entrance Channel station -13+000 to station -6+00; estimated volume; 125,000 CY. And Hopper dredging of BIH Jetty Channel station -6+000 to 0+000; estimated volume: 225,000 CY.

Placement Area:

Near Shore Feeder Berm 1A/1B Options 1-3: Sea Turtle Trawling 15 days each. No additional time added to contract duration if awarded.

Option 4: Beach Placement at two locations on South Padre Island in lieu of Near Shore Feeder Berm 1A/1B. If awarded, additional time of 14 calendar days will be added to contract duration.

Option 5: Sea Turtle Trawling 15 days. No additional time added to contract duration if awarded. Dredging and beach placement option are subject to environmental windows for swimming and nesting sea turtles.

Period of Performance: Complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the Notice to Proceed. Completion time for Options 1-5 is 14 calendar days.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. January 20, 2026

    Sources sought

    Due February 4, 2026 at 11:00 AM EST. SAM.gov, notice 153c06c654c24ddcb37d5c148fdfa10f