Award notice, total small business set-aside, first published as special notice
FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 - Water Line
W912HP24R0004
Department of the Army, W074 Endist Charleston. Water and Sewer Line and Related Structures Construction.
Awarded
Chandler Construction Services, Inc.
$23,336,412.01 obligated so far on USAspending
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one was awarded in 2024
24 like it are open now in water and sewer line and related structures construction
- Request for Information/Market Intelligence Notice: Use of Progressive Design Build (PDB) with Other Transaction Authority (OTA) - Fort Hunter-Liggett Water System Improvements
Department of the Army, W072 Endist Louisville
Sources soughtNAICS 237110Lockwood, CAW912QR-PDB-FHLWATERCloses todayNov 3 - GRCA 318719 North Rim & Roaring Springs Rehabilitation Program
Departmental Offices, National Park Service Contracting Activity
PresolicitationNAICS 237110Location not published140PP027R0005Closes in 3 daysNov 6 - HAVO 326181 Rehabilitate Rainshed&Water Treatment
National Park Service, DSC Contracting Services Division
SolicitationNAICS 237110Hawaii140P2026R0091Closes in 4 daysNov 7
All 24 open in water and sewer line and related structures construction
Description
As published on SAM.gov with the solicitation of September 6, 2024.
The Orangeburg-Berkely Reach Phase II Water Main contract consists of the furnishing, installing, and placing into successful operation approximately 40,703 LF of 20-inch diameter water main pipe, 2,398 LF of 26-inch diameter horizontal directionally drilled pipe, booster pump station, and all associated work.
The contract includes all pipe, valves, appurtenances, roadway bores, horizontally directionally drilled pipe, backfill, compaction, testing, quality control, safety, and all other related work required to place the project into successful operation. This contract will be a portion of the Lake Marion Regional Water System with portions owned, operated, and maintained by both Santee Cooper and Berkeley County. The Contractor will be responsible for coordinating Work with local utility owners, property owners, Lake Marion Water Treatment Plant personnel, and Berkeley County.
MAGNITUDE OF WORK: $10,000,000 to $25,000,000The North American Industry Classification System Code (NAICS) is:
237110 Water and Sewer Line Related . This a TOTAL SMALL BUSINESS SET-ASIDE. This Solicitation is hereby posted as of July 18, 2024. This Amendment 0001 is to clarify the type of Set-Aside and is hereby posted on 7/22/2024. The purpose of this amendment is to update the minimum requirements for Relevancy under Factor 1 - PastPerformance. See Section 00 21 16 - Instructions to Proposers for details. THIS AMENDMENT DOES NOT REOPEN COMPETITION FOR THE SUBJECT REQUIREMENT. ONLY THOSE OFFERORS WHOM SUBMITTED BY THE PREVIOUS DEADLINE ON 20 AUGUST 2024 MAY PARTICIPATE. This amendment is hereby posted on 6 September 2024.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Chandler Construction Services, Inc.
- UEI
- C87FBZZ9D341
- CAGE
- 0M045
- Vendor location
- Ninety Six, SC
- Contract
- W912HP24C0008, definitive contract
- Obligated
- $23,336,412.01
- Actions
- 6 between September 25, 2024 and November 17, 2025
- Competition
- Full and Open Competition After Exclusion of Sources, 3 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- Orangeburg Berkeley Phase 2 Reach Water Line Installation
- Match
- award number W912HP24C0008 equals the contract number; same awarding office W912HP (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 9, 2024
Special notice
FY24 Lake Marion Orangeburg Berkeley (Phase 2) Reach Water Main
Due May 13, 2024 at 12:00 PM EDT. SAM.gov, notice 33f69575c6d446dd927f34e64d7939f0
June 10, 2024
Presolicitation
FY24 Lake Marion Orangeburg Berkeley Phase 2-Water Line
Due June 25, 2024 at 1:00 PM EDT. SAM.gov, notice 1b99de9a2f414540bfc40431d34d81cf
July 3, 2024
Special notice
FY24 Lake Marion Orangeburg Berkeley (Phase 2) Reach Water Main
Due May 13, 2024 at 12:00 PM EDT. SAM.gov, notice 580c08e5180543f6be2bf36262a440a8
July 3, 2024
Presolicitation
FY24 Lake Marion Orangeburg Berkeley Phase 2-Water Line
Due June 25, 2024 at 1:00 PM EDT. SAM.gov, notice 8ecc1e1671714e8fa65de4bc13a8dc3d
July 5, 2024
Presolicitation
FY24 Lake Marion Orangeburg Berkeley Phase 2-Water Line
Due June 25, 2024 at 1:00 PM EDT. SAM.gov, notice 176c156d47354108892f6517111ddcb2
July 18, 2024
Solicitation
FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 ?Water Line
Due August 20, 2024 at 11:00 AM EDT. SAM.gov, notice 686036030edd46b395820e0a5e027e48
July 22, 2024
Solicitation
FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 ?Water Line
Due August 20, 2024 at 11:00 AM EDT. SAM.gov, notice b29a04be4275414fb8441fc43b46f061
September 6, 2024
Solicitation
FY24 Construction Lake Marion Orangeburg Berkeley Reach Phase 2 ?Water Line
Due September 11, 2024 at 12:00 PM EDT. SAM.gov, notice ac7d2a6b73b7488f9751169484268424
September 25, 2024
Award notice, originally solicitation
Awarded to CHANDLER CONSTRUCTION SERVICES, Inc. Ninety Six for $22,983,723. SAM.gov, notice 2e7172b5261c4cf5b4dbeba303eb11ef
Points of contact
- Evelyn HALLIBURTONEVELYN.HALLIBURTON-SHANNON@USACE.ARMY.MIL8433298208
- Addison Layfieldaddison.g.layfield@usace.army.mil8433298194