Little Goose Unit 3 Hub Shaft Repair

W912EF25RSS29

Department of the Army, US Army Engineer District Walla Wal. Other Heavy and Civil Engineering Construction.

Response deadline

June 5, 2025 at 2:00 PM EDT

Closed 470 days ago. Posted May 20, 2025. Scheduled to archive June 20, 2025.

Description

As published on SAM.gov.

The project involves sealing a known oil leak on a Kaplan turbine shaft hub, allowing Unit 3 to resume normal Kaplan operations. Little Goose Main Unit 3’s Kaplan turbine runner was forced out of service when the turbine was found to be leaking oil. The main scope of work for this contract addresses the leak found at the turbine shaft to hub flange. The o-ring between the top of the Kaplan hub and the shaft lower flange has failed at this location.

The work detailed will contain the runner leakage and route the leaked oil back to the static oil head. Instead of replacing the failed o-ring (requiring unit disassembly), this job seeks to contain leakage by sealing the outer diameter of the shaft flange where it meets the hub. It will also include welded caps for each coupling bolt, and piping at the shaft jacking bolts to contain leaking within the flange face and routing it back to the static oil head. The work will be completed with the unit partially disassembled (performed by government personnel) and confined to the turbine pit with limited egress.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. May 20, 2025

    Sources sought

    Due June 5, 2025 at 2:00 PM EDT. SAM.gov, notice fe53d7b70cbd4f4d845003c059601ba5