Solicitation, first published as special notice
Holt Lock Monolith R14 Restoration
W9127825RA015
Department of the Army, W074 Endist Mobile. Other Heavy and Civil Engineering Construction.
Response deadline
June 10, 2025 at 3:00 PM EDT
Closed 510 days ago. Posted June 2, 2025, first published March 27, 2025. Scheduled to archive May 16, 2026.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed in 2025
131 like it are open now in other heavy and civil engineering construction
- SOURCES SOUGHT NOTICE FOR PROJECT LABOR AGGREEMENTS (PLAs) TO COASTAL STORM RISK MANAGEMENT (CSRM) FOR CAPE MAY TO LOWER TOWNSHIP, NEW JERSEY, BRIGANTINE INLET TO GREAT EGG HARBOR INLET (ABSECON ISLAND), NEW JERSEY, AND BARNEGAT INLET TO LITTLE EGG, INLET
Department of the Army, W074 Endist Wilmington
Sources soughtNAICS 237990New JerseyW912PM27BA004Closes todayNov 2 - SOURCES SOUGHT NOTICE FOR PROJECT LABOR AGGREEMENTS (PLAs) TO COASTAL STORM RISK MANAGEMENT (CSRM) FOR BETHANY BEACH AND SOUTH BETHANY BEACH, DE (CSRM - BEACHFILL), FENWICK ISLAND, DE (CSRM – BEACHFILL), REHOBOTH BEACH & DEWEY BEACH, DE (CSRM – BEACHFILL)
Department of the Army, W074 Endist Wilmington
Sources soughtNAICS 237990Bethany Beach, DEW912PM27BA005Closes todayNov 2 - Sources Sought:Neopit Dam Remediation Construction
Bureau of Indian Affairs, Bureau of Indian Affairs
Sources soughtNAICS 237990WisconsinDOIASAM270004Closes todayNov 2
All 131 open in other heavy and civil engineering construction
Description
As published on SAM.gov.
The objective of this project is for the Contractor to provide all labor, materials, and equipment necessary to repair monolith R14 in accordance with the plans and specifications. Work includes but not limited to horizontal drilling, installing horizontal post tension anchor bars, internal pressure grouting, epoxy injection of surface cracks, installing water stops, underwater concrete placement, and dewatering the lock chamber at Holt Lock.
Amendment 0001 is posted 16 May 2025 to update the Table of Contents, Bid Schedule, Explanation of Bid Schedule, and several sections within the specifications as well as drawings. The response date has been extended to 4 June 2025.
Amendment 0002 posted 2 June 2025 updates the Bid Scheule, Bid Schedule Notes, Explanation of the Bid Scheudle, Section 01 00 00, Section 13 51 00.10, Section 31 68 13, and extends the response date to 10 June 2025.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
March 27, 2025
Special notice
Design-Bid-Build Holt Lock Monolith R14 Restoration
SAM.gov, notice 34587c8a46ca411bacd83e98ee164e7f
March 27, 2025
Special notice, originally sources sought
Advance Notice Design-Bid-Build Holt Lock Monolith R14 Restoration
SAM.gov, notice 819af132b0b948629277c4523dfb2703
April 15, 2025
Special notice
Design-Bid-Build Holt Lock Monolith R14 Restoration
SAM.gov, notice bf5b7d81b6a048298f583b5026e1421f
April 24, 2025
Solicitation
Due May 28, 2025 at 3:00 PM EDT. SAM.gov, notice 76e7b5a6edcc48cabb73e055881f5253
May 9, 2025
Solicitation
Due May 28, 2025 at 3:00 PM EDT. SAM.gov, notice 8c171e52716f44c7a415abce29d6edac
May 16, 2025
Solicitation
Due June 4, 2025 at 3:00 PM EDT. SAM.gov, notice 1038779d775642b2895880d105a0a804
June 2, 2025
Solicitation
Due June 10, 2025 at 3:00 PM EDT. SAM.gov, notice a6efa1080f064442b662085b4cb4583e
Points of contact
- Jennifer SuitJennifer.H.Suit@usace.army.mil2514416466
- Elizabeth Trimbleelizabeth.m.trimble@usace.army.mil2516903329