Award notice, total small business set-aside
Craney Island Earthwork IDIQ FY24
W9123624D5001
Department of the Army, W2SD Endist Norfolk. Other Heavy and Civil Engineering Construction.
Awarded
$75,000,000.00 on the award notice, August 13, 2024, contract W9123624D5001
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one was awarded in 2024
132 like it are open now in other heavy and civil engineering construction
- Norfolk Harbor Inner Channel to Newport News Maintenance Dredging located in Hampton Roads, Virginia
Department of the Army, W2SD Endist Norfolk
SolicitationNAICS 237990VirginiaW9123627BA003Closes in 20 daysNov 23 - Fort Eustis Dredge Material Management Area (FEDMMA)
Department of the Army, W2SD Endist Norfolk
SolicitationSmall businessNAICS 237990VirginiaW9123626BA008Closes in 28 daysDec 1 - Fort Eustis Dredge Material Management Area Construction in Newport News, Virginia
Department of the Army, W2SD Endist Norfolk
Sources soughtNAICS 237990VirginiaW91236-26-B-1AVXCloses in 28 daysDec 1
All 132 open in other heavy and civil engineering construction
Description
As published on SAM.gov.
CIDMMA is a confined upland dredge material placement site located in Portsmouth, Virginia, adjacent to the Port of Hampton Roads. Work activities will include borrow area preparation for the purpose of dewatering saturated materials for future use, excavation, and reclamation of dredged material from prepared borrow areas, transport of reclaimed and borrowed materials, and construction of site improvement infrastructure projects with the material. The infrastructure projects on CIDMMA that may be built include, but are not limited to:
1. Construction and maintenance of containment dikes and division dikes to a compaction performance standard with incremental vertical lifts of material.
2. Construction of access roads within containment cells at CIDMMA.
3. Placement of reclaimed material as overburden for the purpose of consolidation of saturated materials.
4. Placement of reclaimed material as stockpile.
5. Excavation of saturated dredged material from around and within existing spillways for the purpose of maintenance of spillway components and structures.
6. Excavation and maintenance spillway effluent discharge pipes, outfalls, and aprons.
7. Steel and Concrete repair at the spillbox structures 8. Replacement of weir boards and repositioning of the gangways at the spillbox structures Contractor shall be responsible for before and after topographic surveys of the dike raising areas. All reclaimed material for the earthwork site improvements will be government supplied from on-site borrow sources. Total material volume placed is not expected to exceed 1,000,000 cubic yards per contract year.
Construction techniques and equipment must accommodate soft and wet subsurface and fill soil conditions with high susceptibility to rapid and long-term settlements under instantaneous and sustained loading conditions. Contract No. W9123624D5001, Craney Island Earthwork IDIQ, Portsmouth, VA is awarded for a total Not-To-Exceed $75,000,000.00.
This award is based on the bid dated 03 June 2024 with acknowledgement of all amendments (0001 through 0003) and constitutes acceptance of your bid (including the construction cost schedule, CLINs 0001–0014) with a total evaluated price of $52,820,155.00. Task Order No. W9123624F0013 is being issued concurrently for the amount $12,016,191.10, satisfying the minimum guarantee for the IDIQ contract.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Three Oaks Construction, Inc.
- UEI
- HWSZR9YRRHV4
- CAGE
- 9PPC1
- Vendor location
- North Sioux City, SD
- Contract
- W9123624D5001
- Obligated
- $0.00, potential $75,000,000
- Actions
- 2 between August 13, 2024 and June 16, 2025
- Competition
- Full and Open Competition After Exclusion of Sources, 3 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- The Government Will Award a Single-Award Task Order Contract (Satoc) to Provide for the Site Improvements at Craney Island Dredged Material Management Area (Cidmma).
- Match
- award number W9123624D5001 equals the contract number; same awarding office W91236 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
August 14, 2024
Award notice, originally solicitation
Awarded to Three Oaks Construction, Inc. North Sioux City for $75,000,000. SAM.gov, notice b58aec12c0ab4291b62b2d6d498c15c3
Points of contact
- AMY COODYamy.h.coody@usace.army.mil757.201.7883
- NICHOLAS LIZOTTENicholas.Lizotte@usace.army.mil7572017310