Skip to content
Abierto

Award notice, first published as solicitation

Berlin Tree Removal

W911WN25QA008

Department of the Army, W072 Endist Pittsburgh. Landscaping Services.

Awarded

Evans Land Improvement LLC

$29,200.00 obligated so far on USAspending

Description

As published on SAM.gov with the solicitation of February 19, 2025.

1. GENERAL REQUIREMENTS The purpose of this contract is to remove trees and grind stumps on the East side of Berlin Dam. All trees shall be cut and removed from project lands within the designated clearing area. All stumps shall be ground to 8” below grade. Designated clearing area is described in the Site Map at the end of this Performance Work Statement.

All work shall be conducted in strict accordance with the following standards of practice: ANSI Z133.1 – Tree Care Safety Standard 29 CFR 1910.266 – Logging Operations 29 CFR 1910.269 – Electrical Power Generation, Transmission and Distribution USACE EM 385-1-1 Section 31 Tree Maintenance and Removal 2. GENERAL DESCRIPTION Contractor shall furnish all labor, materials, equipment, tools, transportation, supervision, expertise, and related supplies to safely remove selected trees.

3. SAFETY Hazards may be (but are not limited to) bee stings, snake bites, and overhead electrical hazards. All personal protective gear and safety protocols shall be adhered to by the Contractor and their employees. At any time when the Government representative witnesses a safety violation, work shall immediately be stopped, and the violation documented and corrected before work can resume.

All work shall be performed in accordance with the Corps of Engineers Safety Manual EM385-1-1 Latest version is available online at https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf The Contractor shall develop an Activity Hazard Analysis (AHA) for all work under this contract and submit it to the Contracting Officer’s Representative. A blank AHA form is attached (Attachment 1 – Blank AHA Form).

The following specific Personal Protective Equipment shall be required under this contract: Safety Shoes – All employees engaged in construction operations shall wear safety shoes meeting the requirements of EM 385-1-1, Section 05.E. Protective Eyewear – All workers on the site shall wear, as a minimum, protective eyewear meeting the requirements of EM 385-1-1, Section 05.A. Additional eye protection may be required in accordance with the requirements of EM 385-1-1, Section 05.B.

Hearing Protection – Hearing protection shall be provided for workers in accordance with EM 385-1-1, Section 05.C. Head Protection - Head protection shall be provided for workers in accordance with EM 385-1-1, Section 05.D. Fall Protection - If working from a lift or at heights greater than 6 feet, workers shall use fall protection in accordance with EM 385-1-1, Section 21. The Contractor shall identify and protect all overhead utility lines prior to commencing work in that area.

4. COORDINATION MEETING AND POINTS OF CONTACT (POC) Prior to commencement of any work being performed on site, the contractor shall participate in a meeting with the Berlin Lake Resource Manager and Contracting Officer’s Representative (COR), which will include approving a work progression plan.

Berlin Lake Resource Manager – Vanessa Bishop (330) 654-0879 COR – Waylon Reigle (330) 547-6714 5. VERIFICATION OF FIELD CONDITIONS The Contractor shall verify all conditions in the field and shall advise the COR of any discrepancy before performing any work. 6. WORK AREAS The Contractor's attention is directed to the fact that the work to be performed is located in areas heavily used by the public.

It shall be the responsibility of the Contractor to provide the controls necessary to prevent any interference by the public to his operations. The Contractor shall take all necessary and reasonable precautions to secure the area against vandalism and to ensure the safety and well-being of the public until final acceptance by the Government. 7. TIME OF PERFORMANCE The Contractor shall confine all operations at the work site between the hours of 7:00 AM and 4:00 PM, Monday through Friday, unless otherwise approved.

Work will be permitted on weekends or Federal holidays, with permission of the COR (SCA wage rates will apply). Access guidelines will be provided by the COR. Contractor shall coordinate contract tasks and activities with the COR. 8. SITE VISIT We ask all interested parties please come visit the site on Monday, February 24 at 1:00 PM.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
V493DBJ6X5D6
CAGE
9T0U5
Vendor location
Diamond, OH
Contract
W911WN25CA002, definitive contract
Obligated
$29,200.00
Actions
1 between March 2, 2025 and March 2, 2025
Competition
Competed Under SAP, 17 offers received
Set-aside reported
Small Business Set Aside - Total
Described as
Tree Removal Services at Berlin Lake
Match
award number W911WN25CA002 equals the contract number; same awarding office W911WN (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. February 19, 2025

    Solicitation

    Due February 25, 2025 at 5:00 PM EST. SAM.gov, notice 4c2fbf060e80484a952d2baa4f756544

  2. February 19, 2025

    Solicitation

    Due February 25, 2025 at 5:00 PM EST. SAM.gov, notice 8b3d43cc2898409db3da8c3c680abfc7

  3. February 19, 2025

    Solicitation

    Due February 25, 2025 at 5:00 PM EST. SAM.gov, notice 9a8f93f276b1402aa3fe359224944887

  4. March 4, 2025

    Award notice

    Awarded to Evans Land Improvement LLC Diamond for $29,200. SAM.gov, notice ce186803c14242ad996ccad09bb779e5

Points of contact