Combined synopsis and solicitation
(MATOC WORK PLAN ONLY) EXPAND CONC PAD FOR PATRIOT RADAR EQUIPMENT, KUNSAN AB
W90VN724R0011
Department of the Army, 0906 Aq Co Det B Contracti. Commercial and Institutional Building Construction.
Response deadline
August 19, 2024 at 12:00 AM EDT
Closed 811 days ago. Posted August 7, 2024, first published August 6, 2024. Scheduled to archive August 7, 2025.
Get the next one like this from Department of the Army by email, the day it is posted.Find my opportunities
This one closed in 2024
190 like it are open now in commercial and institutional building construction
- Building 143 Concrete Scale Pad Expansion and Dock Leveler Replacement
Department of the Navy, NSWC Carderock
PresolicitationNAICS 236220Location not publishedN00167-27-SIMACQ-CD-102-0003Closes tomorrowNov 9 - Construct North Unit Visitor Center at BADL
National Park Service, Doi, NPS Conops Strategic
SolicitationNAICS 236220Location not published140PS126B0010Closes in 2 daysNov 10 - Medical Repair and Renewal (MRR) Korea
Department of the Army, W2V6 USA Eng SPT CTR Huntsvil
SolicitationNAICS 236220Outside the USW912DY26RA093Closes in 2 daysNov 10
All 190 open in commercial and institutional building construction
Description
As published on SAM.gov.
Project Title:
Expand Conc Pad for Patriot Radar EquipmentProject Location:
Kunsan Air Base, Republic of KoreaTitle:
Expand Concrete Pad for Patriot Radar Equipment, 24-1031Location: 8th CES, Kunsan ABTHIS IS RFP FOR WORK PLAN TASK ORDER FOR THE FOLLOWING MATOC CONTRACTORS ONLYW91QVN-24-D-0039, -0041, -0042, -0043, -0044, -0045, -0046, -0047, -0049, -0050, 0053, 0055, -0056, - 0058, -0081 and -0110.A.
Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend site visit. See Clause FAR 52.236-27 Alt I in Section L. Offerors are required tohave a valid Korean Identification card when attending the site visit orientation.B.
SUBMISSION OF PROPOSAL: Proposal shall be submitted by 13:00 hours on the closing date.a. The PRICING PORPOSALb. Technical proposal:1.Offer Breakdown2. Section K3. Conceptual Drawings4. Technical NarrativesC.
Submission of Proposal: See Section L for details. If the contractor is unable to submit theproposal in response to this RFP, the contractor shall submit the No-offer letter by date and time specified in thissolicitati
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
Points of contact
- Matthew Gridermatthew.r.grider.mil@army.mil
- Kilchae Songkilchae.song.ln@army.mil82-503-355-9310