Solicitation
KAUTZ ROAD SUBSTATION CONSTRUCION, UIP SUBPROJECT 2- KRS
RFP-383167-CD
Department of Energy, Fermilab - DOE Contractor. Power and Communication Line and Related Structures Construction.
Offers due
December 18, 2026 at 5:00 PM EST
45 days from now. Posted November 2, 2026.
Get an email when this is amended, when the deadline moves and when it is awarded.Watch it
Next from this buyer
- PIP-II CM 2K Reclosable Pressure Safety Relief ValvesSolicitationNAICS 332911Anywhere in the US387881-DSFCloses tomorrowNov 4
- Leica Absolute Tracker ATS800 and AccessoriesSolicitationNAICS 334516Anywhere in the US387869swkCloses tomorrowNov 4
- Enclosed Electronics RacksSolicitationNAICS 332999IllinoisRFP387713Closes in 7 daysNov 10
Similar, open now
- CSSC Utility Feed Transformer Replacement
Department of the Army, W072 Endist Chicago
Sources soughtNAICS 237130IllinoisW912P627SSA001Closes in 2 daysNov 5 - FCI Marion - Emergency Repair Tornado Damage
Federal Prison System / Bureau of Prisons, Fao
Combined synopsis and solicitationSmall businessNAICS 237130Marion, IL15BBNF26Q40900001Closes in 30 daysDec 3 - Request for Quotations (RFQ) - Trenching, Underground Conduit Installation and Associated Civil Works
Department of State, American Consulate Cape Town
SolicitationNAICS 237130Outside the US19SF2027Q0001Closes todayNov 3
All 10 open in power and communication line and related structures construction
Description
As published on SAM.gov.
This scope of work is to rebuild and renovate the Kautz Road Substation (KRS), which is UIP subproject SP-2. The KRS supplies electricity to various lab buildings and systems. These systems serve both conventional facility needs, as well as process utility requirements. It is vital to Fermilab’s mission that KRS be revitalized and expanded, ensuring the ability to serve existing and future loads.
The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein.
The critical schedule constraint for construction of this project is Fermilab’s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract, within the shutdown window.
This project includes the following milestones: Milestone 1 – 60 Calendar Days after issuance of Notice to Proceed (NTP). This milestone is intended for completion of necessary submittals and RFIs, approval of shop drawings for fabrication and procurement. Milestone 2 – 4th January 2028; This milestone marks the point where access is permitted inside Kautz Road Substation yard and construction work may begin.
Milestone 3 – 31st of March 2028; This milestone marks the completion of building foundation and ready for placement of the new prefabricated control house building (provided by FermiForward). Milestone 4 – 2nd July 2029; This milestone marks the formal issuance of an Authorization for Use and Possession (AUP) of the KRS Substation facility, including all remedial work following removal of site trailers, but not including seasonal work and all final punch list items addressed.. Milestone 5 – 30th September 2029; This milestone marks the completion of the project.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
November 2, 2026
Solicitation
Due December 18, 2026 at 5:00 PM EST. SAM.gov, notice 0d455f653c70449796f54eea428f0d56
Points of contact
- Chris Daleycdaley@fnal.gov6308404256