Proposal for Renovation - Renovation - HVAC (VRV/VRF) System at 75, Gregory's Road Col 7
PR15989443
Department of State, U.S. Embassy Colombo. Construction.
Response deadline
May 22, 2026 at 8:00 AM EDT
Closed 167 days ago. Posted May 7, 2026. Scheduled to archive June 6, 2026.
Get the next one like this from Department of State by email, the day it is posted.Find my opportunities
This one closed in 2026
3 like it are open now in construction
- Non-Complex Construction and Design Build Construction, Basic Ordering Agreement RAF Lakenheath, Suffolk
Department of the Air Force, FA5587 48 Cons (Admin Only No Req)
Sources soughtNAICS 23Outside the USFA558723GXXXXCloses in 825 daysFeb 7, 2029 - FLETC Cheltenham Construction IDIQ
Federal Law Enforcement Training Center, FLETC Procurement Cheltenham Office
Sources soughtNAICS 23Maryland70LCHE27RPFB00001SSCloses in 13 daysNov 18 - Schofield Barracks, HI - Care Care Center w/Gas Express Image Update (SB80)
Army Air Force Exchange Service, PZ - K Ofc of DIR-PROCU 1018572
SolicitationNAICS 23Schofield Barracks, HIGNFR-FC-SCH-26-27662Closes in 28 daysDec 3
Description
As published on SAM.gov.
Dear Prospective Offeror:
Subject: Request for Quotes 19CE2026Q0010
Enclosed is a Request for Quotes (RFQ) for Renovation - Renovation - HVAC (VRV/VRF) System at 75, Gregory's Road Col 7. If you would like to submit a quotation, follow the instructions in Section J of the solicitation, complete the required portions of the attached document, and submit it to the address shown on the Standard Form that follows this letter.
Description
Provide all labor, materials, equipment, and supervision to design, supply, install, test, and commission a complete HVAC (VRV/VRF air conditioning and mechanical ventilation) system for the Recreation Center Clubhouse, serving an average occupancy of 120 persons. Scope includes indoor and outdoor units, refrigerant piping with specified insulation, condensate drainage, fresh air integration, ducted exhaust systems, controls, electrical coordination, and all incidental works required for full functionality. Contractor shall verify design adequacy, reconcile drawings with site conditions, and execute all necessary adjustments to meet performance requirements. Work shall comply with applicable codes and standards, include TAB and commissioning, and deliver a fully operational system. Provide a minimum two-year warranty (or manufacturer’s longer warranty) covering all parts and labor at no cost to the Government
Attachments
- Attachment 1 Statement of Work
- Attachment 2 Electrical Drawings
- Note: The drawings will be made available only to attendees at the mandatory/pre-proposal site visit and conference. No drawings will be distributed electronically.
The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.
Quotations are due by 1700 hours 22nd May 2026. No quotations will be accepted after this time. Quotations must be in English and incomplete quotations will not be accepted.
The Embassy intends to conduct a pre-proposal conference at No. 75, Gregory’s Road, Colombo 7, at 10:15 a.m. on 12th May 2026.
Prices should be duty free and VAT exempt.
Both quotation and technical proposal should be submitted and addressed to:
Contracting Officer, American Embassy Colombo, 210 Galle Road, Colombo 03, Sri Lanka
Email: sundaravelyg@state.gov
In order for a quotation to be considered, you must also complete and submit the following:
1. SF-18
2. Section A, Pricing
3. Section L Representations and Certifications
4. Additional information as required in Section J
Local Execution, Responsiveness, and On-Site Requirements
To ensure timely execution, quality assurance, and effective project coordination, the following mandatory requirements apply:
- Local Project Execution Capability
- The Contractor shall have an established local presence in Sri Lanka, either as a registered company, joint venture, or formally authorized local representative.
- Proof of local office, operational base, or permanent technical support facility shall be provided.
- On-Site Supervision and Mobilization
- Contractor must provide qualified on-site supervision throughout the project duration.
- Mobilization of personnel, materials, and equipment must be completed within the agreed project timeline and in no case exceed 5 to 10 calendar days from notice to proceed.
- Response Time and Project Support
- The Contractor must ensure technical response within 24–48 hours for all site coordination, installation issues, and clarification requests.
- Emergency or critical site support shall be available on call within Sri Lanka during execution phase.
- Travel, Logistics, and Cost Responsibility
- All travel, accommodation, transport, customs clearance, and logistical costs associated with project execution shall be fully borne by the Contractor.
- The Embassy will not be responsible for international travel or mobilization expenses.
- Site Familiarization and Attendance
- Attendance at the pre-proposal conference and site visit is strongly encouraged and may be required for technical qualification.
- Failure to demonstrate familiarity with site conditions may result in technical non-responsiveness.
- After-Sales Support and Warranty Service
- Contractor shall maintain local warranty support capability in Sri Lanka for the full warranty period.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- Attachment 1 Statement of Work.pdf220 KB, May 7, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 7, 2026
Solicitation
Due May 22, 2026 at 8:00 AM EDT. SAM.gov, notice ef47b326251f418d85f40fbf88c28d9c
1 revisions on SAM
- May 7, 2026: publish, solicitation
Points of contact
- Yogaganesh Sundaravelsundaravelyg@state.gov94112028525
- Danujaya Muthugalamuthugaladr@state.gov94112028816