Award notice, first published as presolicitation

TANK,FUEL,AIRCRAFT

N0038324RP256

Department of the Navy, NAVSUP Weapon Systems Support. Other Aircraft Parts and Auxiliary Equipment Manufacturing.

Awarded

Rockmart Fuel Containment, LLC

$1,167,677.00 obligated so far on USAspending

Description

As published on SAM.gov with the solicitation of April 10, 2025.

ITEM UNIQUE IDENTIFICATION AND VALUATION (JAN 2023)|19|||||||||||||||||||| HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT|8|x|||||||| TIME OF DELIVERY (JUNE 1997)|20||||||||||||||||||||| STOP-WORK ORDER (AUG 1989)|1|| FMS DELIVERY AND SHIPPING INSTRUCTIONS|3|||N98111.40| WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)|16|Invoice and receiving report combo type|Source|TBD|N00383|TBD|TBD|SEE SCHEDULE|TBD|||TBD|||||| NAVY USE OF ABILITYONE SUPPORT CONTRACTOR - RELEASE OF OFFEROR INFORMATION (3-18))|1|| VALUE ENGINEERING (JUN 2020)|3|||| EQUAL OPPORTUNITY (SEP 2016)|2||| INTEGRITY OF UNIT PRICES (NOV 2021)|1|| WARRANTY OF SUPPLIES OF A NONCOMPLEX NATURE (JUN 2003)|6|12 Months|60 Days After Discovery of Defect||||| EQUAL OPPORTUITY FOR WORKERS WITH DISABILITIES (JUN 2020)|2||| TRANSPORTATION OF SUPPLIES BY SEA (JAN 2023)|2||| BUY AMERICAN-FREE TRADE AGREEMENTS-BALANCE OF PAYMENTS PROGRAM - BASIC (FEB 2024))|11|||||||||||| LIMITATION OF LIABILITY--HIGH-VALUE ITEMS (FEB 1997)|1|| ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (NOV 2023)|13|||||||||||||| BUY AMERICAN-FREE TRADE AGREEMENTS-BALANCE OF PAYMENTS PROGRAM CERTIFICATE-BASIC (FEB 2024))|5|||||| BUY AMERICAN--BALANCE OF PAYMENTS PROGRAM (FEB 2024)|1|| ROYALTY INFORMATION (APR 1984)|1|| ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2024)|13|336413|1250|||||||||||| FACSIMILE PROPOSALS (OCT 1997)|1|| NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, ANDENERGY PROGRAM USE (APR 2008))|2||x| The purpose of this amendment is to increase the total QTY of this requirement.

The total QTY is hereby increased by QTY 30EA from QTY 6EA to QTY 36EA. \ ALL CONTRACTUAL DOCUMENTS (I.E. CONTRACTS, PURCHASE ORDERS, TASK ORDERSDELIVERY ORDERS AND MODIFICATIONS) RELATED TO THE INSTANT PROCUREMENT ARE CONSIDERED TO BE "ISSUED" BY THE GOVERNMENT WHEN COPIES ARE EITHER DEPOSITED IN THE MAIL, TRANSMITTED BY FACSIMILE, OR SENT BY OTHER ELECTRONIC COMMERCE METHODS, SUCH AS EMAIL.

THE GOVERNMENT'S ACCEPTANCE OF THE CONTRACTOR'S PROPOSAL CONSTITUTES BILATERAL AGREEMENT TO "ISSUE" CONTRACTUAL DOCUMENTS AS DETAILED HEREIN.

Early and incremental deliveries accepted and preferred. \ 1. SCOPE 1.1 Articles to be furnished hereunder shall be manufactured, tested and inspected in accordance with ;320-4-49755-101,MEGGITT (ROCKMART) INC CAGE(56221)LATEST REV; drawing number ( ; 320-4-49755-101,MEGGITT (ROCKMART) INC CAGE(56221)LATEST REV; ) ; 320-4-49755-101,MEGGITT (ROCKMART) INC CAGE(56221)LATEST REV; , Revision ; 320-4-49755-101,MEGGITT (ROCKMART) INC CAGE(56221)LATEST REV; and all details and specifications referenced therein.

1.2 Unless expressly provided for elsewhere in this clause, equipment such as fixtures, jigs, dies, patterns, mylars, special tooling, test equipment, or any other manufacturing aid required for the manufacture and/or testing of the subject item(s) will not be provided by the Government or any other source and is the sole responsibility of the contractor. The foregoing applies notwithstanding any reference to such equipment or the furnishing thereof that may be contained in any drawing or referenced specification.

1.3 If MIL-STD-454 is referenced in the drawings or in the specification, the contractor is expected to show compliance with IPC/EIAJ-STD-001C. 2. APPLICABLE DOCUMENTS - NOT APPLICABLE 3. REQUIREMENTS - NOT APPLICABLE 4. QUALITY ASSURANCE I. First Article Test (FAT) Requirements.The following requirements applyto AMFUEL tank four.

The tests to be performed under the FAT approval clauseof the contract are:Conduct all testing required by AMFUEL Report 2122Rev M:F-18 Acceptance Test Procedure (ATP) non-self-sealing fuelcells with the exceptions.A Vacuum Bag Method Phenolphthalein Test shall be conducted on the fuel cell once all ATP testing has successfully been completed Folding: In lieu of folding the fuel cell at a temperature not less than 70? folding shall take place at 60-65?

Folding: In addition to the test described in the ATP, after fuel cell is confirmed to be folded to the proper size,it shall remain folded for 30min then inspected per MIL-STD-801D.This test must be performed once prior to the final leakage test. II. Samples. The contractor shall present one (1) unit(s) of lot/item 0001 as specified in this contract.At least 45 days before First Article Testing, the contractor shall notify the PCO, in writing, so that the Navy may witness the testing. III.

Testing Location and Estimated Lead-Time. No arrangements will be made for inspection of the sample(s) until the DCMA notifies the PCO that the contractor has inspected the sample and is 100% ready for inspectio by the Government team.The DCMA-QAR shall be present during the inspection team's visit to the manufacturing site to perform the FAT.IV. Test Report.

The contractor shall prepare a FAT Report, which shall be in accordance with the requirements of ISO-9012 (Aerospace First Article Inspection Requirement), MIL-HDBK-831 or equivalent, and shall be submitted via the cognizant DCMA Contract Administration Office to the PCO.

Disposition of First Article Test Sample(s).A.Sample(s) may be considered as production items under the contract providedthe sample(s) can be refurbished to Ready for Issue (RFI) condition and providethe sample(s) have inspection approval of the cognizant QAR. Sample(s) may beshipped as production items only after all other units required under the contract have been produced and are ready for shipment.B.The QAR shall provide comments on Form DD1222 which shall be forwarded with the FAT Report.

The cognizant government inspecting activity shall issue a report accepting or rejecting the FAT sample(s). Final approval of the FAT Report is the responsibility of the PCO. Upon notification of approval/conditional approvalthe QAR shall provide disposition in the Wide-Area(WAWF) system or Form DD250 to indicate Government acceptance of the test report.

5. PACKAGING- MIL-STD 2073 PACKAGING APPLIES AS FOUND ELSEWHERE IN THE SCHEDULE 6. NOTES - NOT APPLICABLE DATE OF FIRST SUBMISSION=ASREQ UPON COMPLETION OF THE FIRST ARTICLE TEST.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
E86UEFDHJWK6
CAGE
56221
Vendor location
Rockmart, GA
Contract
N0038325FNS04 under N0038325GNS01, delivery order
Obligated
$1,167,677.00
Actions
3 between April 15, 2025 and October 23, 2025
Competition
Not Competed, 1 offer received
Set-aside reported
No Set Aside Used.
Described as
Tank,fuel,aircraft
Match
award number N0038325FNS04 equals the contract number; same awarding office N00383 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. March 27, 2024

    Presolicitation

    Due May 13, 2024 at 12:00 AM EDT. SAM.gov, notice 2beeb9a468c44683b40d0132b3d554b6

  2. April 15, 2024

    Solicitation

    Due May 13, 2024 at 2:00 PM EDT. SAM.gov, notice 7a3668415297415b962ea7ee8754cd12

  3. June 6, 2024

    Solicitation

    Due July 5, 2024 at 2:00 PM EDT. SAM.gov, notice 4f44ac29309142d3a1121611b7b6847b

  4. June 6, 2024

    Solicitation

    Due July 5, 2024 at 2:00 PM EDT. SAM.gov, notice 60af301710014aa182e02841ef2b42bb

  5. June 6, 2024

    Presolicitation

    Due July 5, 2024 at 2:00 PM EDT. SAM.gov, notice 86d045db0dc74cd088a4e6a6242ce942

  6. April 10, 2025

    Solicitation

    Due April 10, 2025 at 1:00 PM EDT. SAM.gov, notice 2ed956980c804b9dbab157992cc9f23e

  7. April 10, 2025

    Presolicitation

    Due April 10, 2025 at 1:00 PM EDT. SAM.gov, notice 6f09a708912047b59195c78695469ac1

  8. April 10, 2025

    Solicitation

    Due April 10, 2025 at 1:00 PM EDT. SAM.gov, notice 83fcd7c4da024456b62df9c9ba60bd6c

  9. April 16, 2025

    Award notice

    Awarded to Axillon Aerospace (Rockmart), Inc. for $1,167,677. SAM.gov, notice 26f63028ac1c48b1a565e56f00ff5aa1

Points of contact