Solicitation, total small business set-aside
BUILDING 725 SCIENTIFIC DATA AND COMPUTING CENTER (SDCC) 1.2-MEGAWATT (MW) POWER AND COOLING UPGRADES
JF458021
Department of Energy, Brookhaven Natl Lab -Doe Contractor. Power and Communication Line and Related Structures Construction.
Response deadline
April 1, 2025 at 4:00 PM EDT
Closed 582 days ago. Posted March 7, 2025. Scheduled to archive April 16, 2025.
Get the next one like this from Department of Energy by email, the day it is posted.Find my opportunities
This one closed in 2025
9 like it are open now in power and communication line and related structures construction
- CSSC Utility Feed Transformer Replacement
Department of the Army, W072 Endist Chicago
Sources soughtNAICS 237130IllinoisW912P627SSA001Closes tomorrowNov 5 - B21 Utilities & Site Improvements, Communications & Electrical Infrastructure, Dyess AFB OT Feasibility & Business Feedback
Department of the Army, W076 Endist FT Worth
Sources soughtNAICS 237130TexasW9126G27R1CSYCloses in 8 daysNov 12 - COTP Series Capacitor Two-Phase Design Build
Department of Energy, Western-Sierra Nevada Region
SolicitationNAICS 237130Location not published89503326RWA000049Closes in 9 daysNov 13
All 9 open in power and communication line and related structures construction
Description
As published on SAM.gov.
GENERAL: Brookhaven Science Associates, L.L.C. (“BSA”) has entered into a Prime Contract with the United States of America (“the Government”), as represented by the United States Department of Energy (“DOE”), to operate the Brookhaven National Laboratory (“BNL”). In furtherance of the Prime Contract, BSA desires to contract for certain work described below.
Offers for this work shall be submitted electronically to Joseph Famiglietti at jfamiglie@bnl.gov by 4:00 P.M. on April 1, 2025. BSA reserves the right to reject any or all offers, consider late or incomplete offers, and to waive irregularities. Any or all offers may be rejected if BSA determines such action is in its best interest. Offers will be opened in private.
SUMMARIZED SCOPE OF WORK: The Contractor must provide all material, labor, tools, plant, supplies, equipment, transportation, superintendence, temporary construction of every nature, and all other services and facilities necessary to complete the Building 725 Scientific Data and Computing Center (SDCC) 1.2-Megawatt (MW) Power and Cooling Upgrades project, including all incidental work described in the contract documents.
KEY DATES: Solicitation Overview Meeting (attendance is encouraged): 9:00 AM on 3/13/25 (RSVP by 3/12/25) Mandatory Site Visit (attendance is mandatory): 11:00 AM on 3/17/25 (RSVP by 3/14/25)
Questions Deadline:
5:00 PM on 3/19/25 Offer Deadline: 4:00 PM on 4/1/25 (electronic submissions only) SOLICITATION DOCUMENTS CAN BE ACCESSED USING THE FOLLOWING LINK: COPY AND PASTE THE FOLLOWING LINK INTO A WEB BROWSER https://brookhavenlab-my.sharepoint.com/:f:/g/personal/jfamiglie_bnl_gov/EgNzoP_aHQNHllgxN2XxgrkBGk_7sqvTpgvb32JBW624LQ?e=6TuFqS
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
March 7, 2025
Solicitation
Due April 1, 2025 at 4:00 PM EDT. SAM.gov, notice 42b03ea50e9246fcb54788e118229bb3
Points of contact
- Joseph Famigliettijfamiglie@bnl.gov