Sources sought
Electric Modernization Upgrade
BAA-N6893625S0001-0001
Department of the Navy, Naval Air Warfare Center. Research and Development in the Physical, Engineering, and Life Sciences (except Nanotechnology and Biotechnology).
Offers due
December 1, 2026 at 7:00 PM EST
32 days from now. Posted October 28, 2026, first published October 28, 2026.
Get an email when this is amended, when the deadline moves and when it is awarded.Watch it
Next from this buyer
- MMW Antenna BodyPresolicitationNAICS 332312Anywhere in the USN6893627SIMACQDB0000MEB0000M0027Closes in 2 daysNov 2
- Prometheus Atomic Layer Deposition SystemPresolicitationNAICS 333248Anywhere in the USN6893626SIMACQD550000E5500000441Closes in 3 daysNov 3
- Volumetric KF TitratorPresolicitationNAICS 334516Anywhere in the USN6893626SIMACQD5550000062Closes in 3 daysNov 3
Similar, open now
- SBIR FY26 Phase I Broad Agency Announcement
Environmental Protection Agency, Water, Tribal & Science Division
SolicitationSmall businessNAICS 541715Anywhere in the US68HERW26R0102Closes in 9 daysNov 9 - System of systems Technology Integration Tool Chain for Heterogeneous Electronic Systems (STITCHES) Sources Sought
Department of the Air Force, FA2057 AFLCMC HNJK
Sources soughtNAICS 541715Location not publishedSTITCHES_001Closes in 14 daysNov 14 - Synthesis and Distribution of Drugs of Abuse and Related Compounds
National Institutes of Health, National Institutes of Health Nida
Sources soughtNAICS 541715Anywhere in the US75N98027R00006OTCloses in 20 daysNov 20
Description
As published on SAM.gov.
The Naval Air Warfare Center Weapons Division (NAWCWD) has developed and intends to field a modular, organic capability consisting of commercial-off-the-shelf (COTS) components integrated into custom hardware for the MH-60R Seahawk helicopter. The Government has established a viable system baseline, however, a standardized, repeatable, and supportable production, deployment, and sustainment process is not yet developed. With an initial operational capability target of Q1 FY2028, the program's small scope makes traditional, large-scale support and depot-level sustainment models highly cost-prohibitive.
The current ad-hoc model lacks a process with defined material flow, supply-chain management, quality control, and software deployment process. Consequently, ongoing assembly and support practices require excessive time and specialized personnel that a small team cannot realistically maintain. Furthermore, the existing packaging is not optimized for rapid global air transport, and the chassis design needs human factors optimization for installation and removal in shipboard and austere environments.
As a result, these cumulative limitations reduce overall operational availability, increase the burden on forward-deployed personnel, and raise long-term lifecycle costs. This delays the Navy's critical ability to rapidly produce, transport, install, and sustain this capability worldwide.
Desired Outcomes & Constraints (Submissions may be for one or all requirements)
-
Process Design:
-
Production Process: An operational, production-representative process capable of producing a defined pilot lot using controlled material, assembly, programming, inspection, test, configuration-management, packaging, and acceptance processes that is executable by a small team.
-
Deployment Process: A lightweight, practical support process that enables a small team to provision and deploy the capability with minimal specialized infrastructure.
-
Sustainment Process: A lightweight, practical support process that enables a small team to support, maintain, repair, reconfigure, and reconstitute the capability with minimal specialized infrastructure.
-
Packaging Plan: A rugged, efficient, and reusable packaging plan compatible with Joint Modular Intermodal Containers, Pelican cases, or comparable solutions that enable rapid global air transport and protect the system and associated components during storage, shipment, and operational movement.
-
Human Factors Optimization. The project seeks modified chassis, mounts, and installation/removal processes that reduce the time, tools, personnel, and specialized equipment required to install and uninstall the system in shipboard and austere field environments.
Questions:
Questions should be submitted to jennifer.a.felton.civ@us.navy.mil via email no later than 1600 EST (4:00 PM Eastern Standard Time) by November 09, 2026.
Submission Guidelines, Evaluation, and Eligibility Requirements:
Refer to BAA N6893625S0001 (https://sam.gov/workspace/contract/opp/54d124889d3f423fa900e43c4b041026/view) posted on SAM.gov for submission guidelines and evaluation. While the BAA is an open announcement, the Government is requesting responses for this problem by 1600 EST (4:00 PM Eastern Standard Time) December 01, 2026.
Required Submission Changes:
When submitting the response, the cover page must specifically reference N6893625S0001-0001 to be considered.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 28, 2026
Sources sought
Due December 1, 2026 at 7:00 PM EST. SAM.gov, notice 3b8c3c3c3a2640a6a0d8992a6a36f523
3 revisions on SAM
- October 28, 2026: publish, sources sought
- October 28, 2026: publish, sources sought
- August 20, 2026: publish, solicitation
October 28, 2026
Sources sought, originally solicitation
Due December 1, 2026 at 7:00 PM EST. SAM.gov, notice 8c4c5edd06e8475aaaa363bac8783f31
3 revisions on SAM
- October 28, 2026: publish, sources sought
- October 28, 2026: publish, sources sought
- August 20, 2026: publish, solicitation
Points of contact
- jennifer feltonjennifer.a.felton.civ@us.navy.mil858-978-5811
- ELIZABETH SCHLICKelizabeth.a.schlick.civ@us.navy.mil858-978-1460