Presolicitation
HI FLAP CR562(1) Kilauea Point
6982AF27B000008
Federal Highway Administration, 6982AF Central Federal Lands Divisi. Highway, Street, and Bridge Construction.
Status
Presolicitation
Posted October 15, 2026. Scheduled to archive November 15, 2026.
Get the next one like this from Federal Highway Administration by email, the day it is posted.Find my opportunities
This one is not taking offers
36 like it are open now in highway, street, and bridge construction
- FY27 NRM - Correct Mather Loop Road and Install Speed Bumps
Department of Veterans Affairs, 261-Network Contract Office 21
Sources soughtNAICS 237310Mather, CA36C26127Q0112Closes in 2 daysNov 2 - BRCA 310427 Southbound Shuttle Stop
National Park Service, DSC Contracting Services Division
SolicitationNAICS 237310Utah140P2026R0065Closes in 3 daysNov 3 - TX FW LGA 10(5) Steve Thompson Wildlife Drive
Federal Highway Administration, 6982AF Central Federal Lands Divisi
SolicitationSmall businessNAICS 237310Los Fresnos, TX6982AF27B000006Closes in 3 daysNov 3
Description
As published on SAM.gov.
THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPEFICIATIONS ARE NOT AVAILBLE
PROJECT NAME: HI FLAP CR562(1) Kilauea Point
PROJECT DESCRIPTION:
Kilauea Point National Wildlife Refuge (KPNWR) is a 203-acre facility located on the north shore of the Island of Kaua'i. It is part of the Kaua'i National Wildlife Refuge Complex managed by the United States Fish and Wildlife Service. To keep up with the visitation demands, the KPNWR and the USFWS along with the Federal Highway Administration Central Federal Lands Highway Division is proposing to improve the area by providing better access along Kolo Road and Kilauea Road (Route 562) for pedestrians and bicyclists, as well as improvements to the overlook.
The project consists of installation of a sidewalk adjacent the existing roadway from the intersection of Kuhio Highway to the KPNWR Overlook. Work includes pavement rehabilitation and resurfacing of the existing roadway, with full depth pavement on aggregate base course for roadway widening segments, and reconstruction of the existing turnaround. Guardrail, sidewalk, curb, gutter, two mini-roundabouts, striping, and pedestrian crossings will be provided to establish a safe and accessible corridor for pedestrians and bicyclists. Minor utility adjustments and construction is also anticipated. The total project length is approximately 1.70 miles.
PRINCIPAL WORK ITEMS:
- 18,500 square yards of Removal of Pavement, Asphalt
- 3,370 cubic yards of Roadway Excavation
- 2,900 ton of Roadway Aggregate, Method 2
- 4,200 ton of Asphalt Concrete pavement, Type 1
- 630 square yard of minor concrete Pavement, Reinforced
- 1,540 linear feet of Curb, Concrete, 16-Inch Depth (Slotted)
- 5,670 square yards of Sidewalk, Concrete
- 34 Accessibility Ramps, Concrete
ANTICIPATED SCHEDULE:
Advertise: End of October or Early November 2026
Bid Opening: December 2026
Award: January 2027
Construction: January 2027 –January 2028
ESTIMATED COST RANGE: The anticipated cost range is between 10,000,000 and $20,000,000.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
October 15, 2026
Presolicitation
SAM.gov, notice dc14203ba77443638a2488066e588f26
1 revisions on SAM
- October 15, 2026: publish, presolicitation
Points of contact
- Stephanie Navarrocflacquisitions@dot.gov
- Ryan Phillipscflacquisitions@dot.gov