Skip to content
Abierto

Solicitation, service-disabled veteran-owned small business set-aside, first published as sources sought

612A4-19-016 | Renovate Outpatient Pharmacy and HVAC

36C26126R0036

Department of Veterans Affairs, 261-Network Contract Office 21. Commercial and Institutional Building Construction.

Awarded

Amoroso Overwatch LLC

$8,897,000.00 obligated so far on USAspending

Description

As published on SAM.gov.

AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. CONTINUATION PAGE 2 SOLICITATION NO:

36C26126R0036 ORDER NO:

AMENDMENT NO: 0005 14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED) The purpose of this amendment is to answer three additional RFIs. Section 01 00 00 requires the project schedule to include a minimum of forty-five (45) days for VAÂ relocation of Pharmacy Services into the completed temporary facilities, and a minimum of forty-five (45) days for VA relocation of staff, equipment, and operations from the temporary facilities back into Building 650 upon completion of the renovated outpatient pharmacy suite.

Please confirm: (a) whether both 45-day VA relocation periods are included within the 540-calendar-day period of performance; and (b) whether contract completion for purposes of the period of performance is measured at Government acceptance of the renovated pharmacy suite, or upon completion of temporary facility removal and complete site restoration following the VA's 45-day relocation back into Building 650. ANSWER: The 540-calendar-day Contract Time includes both 45-calendar-day VA relocation periods.

Contract completion is achieved upon completion of all Contract Work, including removal of the temporary facilities and complete site restoration following the VA's final relocation back into Building 650. "Construction start date" refers to commencement of on-site construction activities, including temporary facility construction.

This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation. Section 01 00 00 states: 100% of ALL project submittals shall be approved prior to the construction start date.

Please clarify whether construction start date refers to (a) commencement of temporary facility construction, or (b) commencement of renovation work within Building 650. Please also confirm whether closeout-phase submittals (e.g., O&M manuals, as-built drawings) and late-phase finish material submittals are included in this requirement, or whether it applies to construction-phase submittals only. GLBA appreciates the Government's attention to these questions and remains available for any clarification needed.

ANSWER: "Construction start date" refers to commencement of on-site construction activities, including temporary facility construction. This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation. One of our drywall trade partners has brought up a conflict they have found on the existing walls at the perimeter of the pharmacy.

Per wall type Mbb3 on Sheet A-501 at the corridor it appears that the framing is existing and one new layer of board, the security mesh fire safing and a closure angle is required to be installed. How we would install the 3 slip track at an existing wall? Are they to be cut between the existing studs and fastened to the bottom of the roof deck? Please advise if the slip track is needed.

ANSWER: Install the head-of-wall/slip-track assembly at the existing wall by attaching the slip track to the structure above as required to maintain the specified assembly. Existing studs are not required to be removed or modified except as necessary to complete the installation. ///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
MQUMBM9FXWE5
CAGE
20M21
Vendor location
Anaheim, CA
Contract
36C26126C0064, definitive contract
Obligated
$8,897,000.00
Actions
1 between September 2, 2026 and September 2, 2026
Competition
Full and Open Competition After Exclusion of Sources, 6 offers received
Set-aside reported
Service Disabled Veteran Owned Small Business SET-ASIDE
Described as
Eo 14398 612A4-19-016 | Renovate Outpatient Pharmacy
Match
solicitation number 36C26126R0036 equals the FPDS solicitation identifier; same awarding office 36C261 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. March 16, 2026

    Sources sought

    612A4-19-016 | Renovate Outpatient Pharmacy and HVAC Mather CA

    Due March 23, 2026 at 7:00 PM EDT. SAM.gov, notice 9a6a778b7b784b2285fdfb3fc622635f

  2. March 27, 2026

    Presolicitation, originally sources sought

    Due April 10, 2026 at 1:00 PM EDT. SAM.gov, notice 61cb969e17664f4491ff0c57d23db401

  3. May 29, 2026

    Solicitation

    Due July 1, 2026 at 1:00 PM EDT. SAM.gov, notice 02414ee2795949a99bec9f6696759847

  4. May 29, 2026

    Solicitation, originally presolicitation

    Due June 1, 2026 at 1:00 PM EDT. SAM.gov, notice 0a4cbaab85bc495cbeda6deb4f50b2d7

  5. May 29, 2026

    Solicitation

    Due July 1, 2026 at 1:00 PM EDT. SAM.gov, notice 842c70a65fdf44b9ab54b8f984515154

  6. June 26, 2026

    Solicitation

    Due July 13, 2026 at 1:00 PM EDT. SAM.gov, notice 07a4459064aa4fd1ae85eb5a749a9809

  7. July 10, 2026

    Solicitation

    Due July 20, 2026 at 1:00 PM EDT. SAM.gov, notice 73ef3f11ef2e4a548f7ff5b1c12d0c53

  8. July 17, 2026

    Solicitation

    Due July 20, 2026 at 1:00 PM EDT. SAM.gov, notice 0ef939f7ead84473a560313702841993

  9. September 3, 2026

    Solicitation

    Due July 20, 2026 at 1:00 PM EDT. SAM.gov, notice 310e0097154f4ec9b842207a5d185c13

  10. September 3, 2026

    Solicitation

    Due July 20, 2026 at 1:00 PM EDT. SAM.gov, notice c6d4683b1df847ffbee4dc60be5b32cb

Points of contact