Award notice, service-disabled veteran-owned small business set-aside, first published as presolicitation
Replace roofing 607-22-106 (VA-24-00091745)
36C25224B0009
Department of Veterans Affairs, 252-Network Contract Office 12. Roofing Contractors.
Awarded
$1,187,483.00 obligated so far on USAspending
Description
As published on SAM.gov with the solicitation of August 6, 2024.
Accompanying Amendment 36C25224B0009 0001 Accompanying Amendment 36C25224B0009 - 0001 Replace Roofs William S. Middleton VA Hospital, Madison, WI I. bid opening information: the bid opening date remains changed at 13 august 2024. a. VIRTUAL BID OPENING INFORMATION:
1) Reminder, there will be no in-person public bid opening process this will be conducted as a public virtual activity.
2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number; Join the meeting now (Meeting will be available to be accessed 15 min prior to bid opening) Meeting number (access code):
872-701-0185 Conference ID: 434540725# 3) IAW FAR 52.214-5 Submission of Bids and 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Officer at john.meyers2@va.gov as follows; Vendor bids are due via email as shown above at 12:00 PM local time on 8/13/2024. The virtual public bid opening will be held at 1:00 PM local time on 8/13/2024 at the link and/or the phone # provided above. A hard copy submission is not required.
Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999). 4) Ensure your complete bid including bid bond are provided in your submission. The successful low bidder is required to furnish their original bid bond within five (5) days after notification by the Contracting Officer.
5) It is highly recommended that Bidders submit their bid at least one hour prior to bid opening to avoid any transmission issues. II. The following changes are made to the Drawings: The following changes/clarifications are made to the notes on the drawing;
2. Section B: 2.6. Remove and replace all material down to substrate as well as replace all flashing in the area.
4. Section D: 4.6. Replace all flashing. Remove and replace all material down to substrate. III. The following Questions and Answers / Clarifications are the result of bidders request(s) for information: Q1. Can the VA provide a staging plan for all roofs to include hours and requirements listed? A1. Staging plan would be the contractor s responsibility to prepare and submit for VA review and approval. Q2. What is the plan for lightning protection? Not in specs but exists on roofs. A2.
Contractor is responsible for removal and reinstallation of lightning protection system. Removal and reinstallation required to be performed by a certified individual. Q3. Walkway for fully adhered roofs come 30 wide and that is what is specified, would this be sufficient for all walkways? In lieu of 2 and 4 ? A3. 30 is appropriate for 2 . Where 4 is required two 30 side by side is appropriate. Q4. Does the infrared moisture survey apply to this project? A4. Not required, not applicable. All insulation should be replaced.
ROOF A: Q5. Confirm reuse of all metal flashings (counterflashing/coping), install new only where damaged. A5. Yes, reuse all undamaged metal flashings, install new only where damaged. Reinstalled flashing deemed to be damaged by VA to be replaced at contractor s expense.
ROOF B: Q6. Can VA provide layout of where the walkway is to be installed? A6. 4 (or two 30 side by side) wide walk mats to be installed from access door out to and around air handler and exhaust fan. Contractor would be responsible to submit walkway layout for VA review and approval. Q7. Please define replace all flashing areas with a layout to verify roofing scope? A7. Replace all flashing including copper flashing at parapet. Flashing should extend over top of parapet and include top cap.
Railing to be removed and reinstalled to facilitate replacement of parapet flashing. Refer to main drawing G000 to verify roofing scope. Q8. What is the type of coating on this roof? A8. Roof coating to be field verified by contractor.
ROOF C: Q9. Please provide 2 walkway layouts for this roof? A9. Provide 4 (or two 30 side by side) walk mats from access ladder to the air handlers. Provide 2 wide walk mats around all roof mounted exhaust fans and chillers and connecting to the main walk mats. Contractor would be responsible to submit walkway layout for VA review and approval.
Q10: Confirm reuse of all metal flashings (counterflashing/coping), install new only where damaged? A10. Yes, reuse all undamaged metal flashings, install new only where damaged. Reinstalled flashing deemed to be damaged by VA to be replaced at contractor s expense.
ROOF D: Q11. Please define replace all flashing areas with a layout to verify roofing scope? Does flashing refer to the roof edge? A11. Refer to main drawing G000 for roofing scope. Replace ALL flashing. Yes, flashing refers to roof edge. Q12. Can this roof take fastener penetration with it being high voltage (is there any safety issues)? A12. Specs call for a fully adhered system. Q13. Can all work be completed during normal (0700-1530) daytime shifts? A13.
Crane operation will need to be coordinated and is restricted to Saturdays, Sundays, and federal holidays. Q14. Can the Site Superintendent fulfill the duties of the SSHO as well? A14. Yes Q15. What is the anticipated award date for this project? A15. Contract award will not be delayed after bid opening and is anticipated within approximately 2-3 weeks from opening. Q16. When is the Notice to Proceed anticipated to be issued? A16.
Notice to proceed will be scheduled based on award date and is not expected to be delayed. Q17. When is the anticipated Start of Construction for this project? Will this project need to be completed during the upcoming winter? A17. Start of construction will be dependent on submission/approval of contractor s submittals. No, this project will not need to be completed during the upcoming winter. The VA anticipates some roofs to begin replacement next spring. Q18.
In section 01 00 00 1.11.C, referring to delivering two electronic copies of complete As-Builts after each completed phase. Does this also apply to shop drawings? If electronic, does the VA require two? A18. Provide electronic and one hard copy. Q19. What does (how many) the VA require for hard copies of the completed O&M? Do the manuals require delivery when the equipment arrives or at substantial completion? Q19. At completion of the job two (2) hard copies and one (1) electronic copy is sufficient. Q20.
Specification Section 01 33 23, Will submittal exchange be used for this project and who is responsible for the cost of submittal exchange? A20. VA intends to pursue purchasing Submittal Exchange for this project, at cost to the government. Q21. Is a submittal log/register required for submission by the contractor for this project? Reference 01 33 23 1.3C, the VA provides the initial register. A21. Contractor shall develop and maintain submittal register for the project.
VA anticipates procuring submittal exchange for use on this project. Q22. Reference 01 35 26.1.13, is Tuberculosis Screening required on this project? Can the Department of Health Services Wisconsin risk assessment TB questionnaire satisfy this requirement for this project? A22. TB screening is not required. Q23. Will crane picks for the rigging of equipment and materials be restricted to federal holidays and weekends? A23. Yes. See question 13. Q24.
Is there an area planned for the use of a crane to set up for the sections of roof? The crane size is TBD but will need areas to set up at each area for use during the work. A24. Areas for crane set up to be submitted by contractor for VA review and approval. Q25. Will the crane need to be lowered to the ground nightly to not interfere with Flight for Life This will require space for the boom. A25. Yes. Information will be provided to the contractor after award concerning flight operations. Q26.
Please confirm there are no new steel steps, ladders or railings required for this roof work project. A26. Confirmed, there are no new steel steps, ladders or railings required for this roof work project. Q27. There are a number of lightning protection systems installed on various roofs. These will need to be removed, reworked and or altered to complete the work. What is the required scope for this work? Will the system need to be recertified after the work? Who is responsible for this certification? A27.
See question 2. Q28. Who is responsible for the design of the lightning protection system? Can drawings and a clear defined scope be provided for bidding? A28. See question 2. Q29. What electrical requirements should be included as there are no electrical drawings for removal and replacement of conduits, boxes, and devices that are attached to parapets, structures, and walls throughout the area. A29. Electrical conduits, boxes and devices shall be removed, retained, and reinstalled by a certified individual. Q30.
Area B was noted as replacing the flashings as required. Does this include the Parapet flashing that appears to wrap up the parapet wall and terminate on the top of the existing stone cap. Can a new detail for the flashing required be provided? A30. Area B requires ALL flashing to be replaced including parapet flashing. See Answer 7. Q31. At area B there is a HM Door and frame that leave the building to enter the roof area. How is the contractor to flash this existing opening? Please provide a detail.
Should the door and frame be removed/ replaced to flash the roof? A31. Door and frame to be removed, modified, or replaced as needed to accommodate installation of new insulation, roofing material and flashing. VI. general information: Pre-Bid/Site Visit attendance attached There are no further changes.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Ameritech Contracting LLC
- UEI
- CADSMUE9J2M4
- CAGE
- 8HBD7
- Vendor location
- Middletown, CT
- Contract
- 36C25224C0050, definitive contract
- Obligated
- $1,187,483.00
- Actions
- 2 between September 13, 2024 and September 24, 2025
- Competition
- Full and Open Competition After Exclusion of Sources, 5 offers received
- Set-aside reported
- Service Disabled Veteran Owned Small Business SET-ASIDE
- Described as
- Replace Roofs, 607-22-106, at the WM S. Middleton VA Hospital, Madison Wi
- Match
- award number 36C25224C0050 equals the contract number; same awarding office 36C252 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
June 25, 2024
Presolicitation
Due August 13, 2024 at 1:00 PM EDT. SAM.gov, notice b8c196a620134ab5aacbeb33f627c95c
July 11, 2024
Solicitation, originally presolicitation
Due August 13, 2024 at 1:00 PM EDT. SAM.gov, notice b671578803e741fe88b7dca1f28d44a8
August 6, 2024
Solicitation
Due August 13, 2024 at 1:00 PM EDT. SAM.gov, notice 874d1a195ec04c00af1eed8b2cc016be
September 13, 2024
Award notice
Awarded to AmeriTech Contracting LLC MIDDLETOWN 06457 CTE for $1,187,483. SAM.gov, notice 0bebd0420e424c55b5eab0dc408be618
Points of contact
- John Meyers, Contracting Officerjohn.meyers2@va.gov414-844-4862
Also open from this buyer
- Formlabs Surgical Guide Resin Cleaning ValidationSolicitationSmall businessNAICS 811210Milwaukee, WI36C25226Q0713Closes todaySep 17
- Patient Celling Lift Slings – Brand name onlySolicitationNAICS 339113Tomah, WI36C25226Q0665Closes todaySep 17
- Bowling Lanes Repair and Resurfacing for the Tomah VA Medical Center, Tomah, WisconsinSolicitationSmall businessNAICS 238990Tomah, WI36C25226Q0515-0001Closes todaySep 17
- Bowling Lanes Repair and Resurfacing for the Tomah VA Medical Center, Tomah, WisconsinPresolicitationSmall businessNAICS 238990Tomah, WI36C25226Q0515Closes todaySep 17
- Unrestricted Solicitation Brand Name Only Guldmann CeilingPresolicitationNAICS 339112Milwaukee, WI36C25226Q0712
Awarded to Johnson Controls, Inc. Milwaukee 53209-4408 for $26,004
Closes tomorrowSep 18