Solicitation, service-disabled veteran-owned small business set-aside, first published as presolicitation

Replace iDXA C211 539-26-505

36C25026Q0375

Department of Veterans Affairs, 250-Network Contract Office 10. Commercial and Institutional Building Construction.

Awarded

Calvary Contracting Inc.

$88,963.00 obligated so far on USAspending

Description

As published on SAM.gov.

REPLACE iDXA C211 FOR THE VETERANS AFFAIRS MEDICAL CENTER (VAMC)

CINCINNATI, OH PROJECT NUMBER: 539-26-505 QUESTIONS AND ANSWERS (RFIs) TO REQUEST FOR QUOTE (RFQ)

NUMBER 36C25026Q0375 QUESTIONS AND ANSWERS RFI #1 Question: Given the size of the project, is a dedicated SSHO and the CQ education requirements required? Typically, the Superintendent can be the SSHO and CQC on this size of project, and a superintendent is not going to be a graduate engineer.

1.9 A - 01 35 The Prime Contractor shall provide a minimum of one Full-Time SSHO at each project site, for each shift (with no other duties) that holds as current, a professional safety certification with at least 3 years of dedicated construction safety related experience.

3.4 B 01 45 The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of PM or SRE to determine qualifications based on project complexity at construction review 5 years construction.

Answer: The superintendent may serve as the SSHO and CQC System Manager. A graduate degree is not required. SSHO must be 30 hours of OSHA training (see spec 01 35 26 parts 1.5F).

RFI #2 Question: The solicitation and drawings reference Room C211, while portions of the specifications reference C214. Could you please confirm the correct room designation and whether all documents apply to C211?

Answer: The majority of contract documents, including the Statement of Work and full drawing set, identify Room C211 as the correct project location. The specifications, however, contain an incorrect header reference to C214. This appears to be an error in the header only; the specifications do not assign any scope to C214.

RFI #3 Question: The SOW indicates that hazardous material testing and abatement will be performed if required. Has a hazardous materials survey already been completed? Should bidders include abatement costs in the base bid, or will this be handled separately by the owner?

Answer: The Statement of Work requires the contractor to perform hazardous materials testing and abatement if required. No hazardous materials survey is included in the solicitation, and bidders are not directed to include abatement in the base bid. Contractors should therefore include testing only in their proposals. If hazardous materials are identified during construction, the VA will address any required abatement separately at that time.

RFI #4 Question: The drawings don t describe anything about the fume hood for disconnecting. There is power and some other type of gas or air ports and controls on the hood. We need to know how the hood is connected and what is connected to it. Is there piping or conduit behind the hood to be capped and or removed. Is there a drawing of the hood to reference connections?

Answer: There are no existing as-built or construction drawings for this fume hood, and its installation date and project of origin are unknown. The fume hood has electrical power and medical gas connections. These utilities must be disconnected and capped.

RFI #5 Question: Is there a fan on the roof? If so, does that need to be removed along with any duct in the walls?

Answer: There is no roof-mounted fan associated with this fume hood. The hood is not currently connected to any exhaust fan and does not have ductwork running to the roof or through the walls that would require removal therefore no fan removal is required. See picture below of disconnected unit.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
JN57WU75KM29
CAGE
3HME5
Vendor location
Tipp City, OH
Contract
36C25026P0659, purchase order
Obligated
$88,963.00
Actions
1 between May 14, 2026 and May 14, 2026
Competition
Full and Open Competition After Exclusion of Sources, 2 offers received
Set-aside reported
Service Disabled Veteran Owned Small Business SET-ASIDE
Described as
Replace Idxa 539-20-505
Match
solicitation number 36C25026Q0375 equals the FPDS solicitation identifier; same awarding office 36C250 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. March 12, 2026

    Presolicitation

    Due April 28, 2026 at 1:00 PM EDT. SAM.gov, notice 96808bd78a2b48a39f8cd275b3e99b01

  2. March 27, 2026

    Solicitation, originally presolicitation

    Due April 28, 2026 at 1:00 PM EDT. SAM.gov, notice e115266b892d4a42ab37c005243638d6

  3. April 20, 2026

    Solicitation

    Due April 28, 2026 at 1:00 PM EDT. SAM.gov, notice fa3ec2698606494a9a5a3c0533536f29

Points of contact