Solicitation, service-disabled veteran-owned small business set-aside, first published as presolicitation
542-24-108 | Install New CLC Accessible Route Phase 1 | NCO 4 Construction East
36C24425B0022
Department of Veterans Affairs, 244-Network Contract Office 4. Commercial and Institutional Building Construction.
Awarded
$111,109.35 obligated so far on USAspending
Get the next one like this from Department of Veterans Affairs by email, the day it is posted.Find my opportunities
This one was awarded in 2025
184 like it are open now in commercial and institutional building construction
- 642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC
Department of Veterans Affairs, 244-Network Contract Office 4
Closes in 16 daysNov 20 - RM16-1405 BUILDING 592 RENOVATIONS
Department of the Navy, Navfacsyscom Mid-Atlantic
Solicitation8(a)NAICS 236220Philadelphia, PAN4008527R0017Closes in 27 daysDec 1 - General Construction Job Order Contract (JOC)
Department of the Navy, NIWC Pacific
Presolicitation8(a)NAICS 236220San Diego, CAN6600127R0059Closes todayNov 4
All 184 open in commercial and institutional building construction
Description
As published on SAM.gov.
This project is for the installation of a sidewalk from Building 138 CLC along the east side of New York Avenue up to Blackhorse Hill Road, terminating in an 8 ft. wide by 10 ft. deep landing at Blackhorse Hill Road. The work must adhere to the current Architectural Barriers Act Accessibility Standards (ABAAS) and VA Barrier Free Design Guide, as well as VA Specifications. The contractor must provide all supervision, labor, supplies, transportation, and equipment necessary to complete the work. The contractor may work during business days 6:30a 4:00p. The period of performance for this work will be 60 days. This project is to include the installation of approximately 200 feet of reinforced >3000 psi concrete sidewalk six feet wide by 6 inches thick with >6 inches of mechanically tamped gravel base. The sidewalk shall not exceed a 1:20 pitch (5% grade) and shall have 6 ft. x 6 ft. clear flat landings at the proper ABAAS measured distances. Where a guardrail is indicated, extend the sidewalk 12 inches beyond the inside face of the handrail in compliance with ABAAS. Provide a maximum 2% cross slope where required to facilitate rainwater runoff. The sidewalk must not channel rainwater along its surface at any location. The sidewalk shall have soil retention curbs (hardscape) where necessary to prevent wash out. Provide four (4) American with Disabilities Act (ADA) crosswalk matts as required at roads and service drives. Pin with rebar when new sidewalks meet existing sidewalk. Install expansion and construction joints where required. The existing grade will require a cutting and filling as required to achieve an even pitch of the sidewalk route and of adjacent grass-area grades to gradually taper to existing from the edges of the new sidewalk to facilitate lawn maintenance. Grass-area grades are to match the grade of the sidewalk edges as closely as practical. Excavate, level, and finish-rake the surrounding grade. The construction perimeter is to be fenced in with 6-foot-high fence and locking gate. A 12 x40 space will be offered to the contractor for a construction trailer or dumpster at our laydown yard. Dumpsters must be secured to prevent entry. The contractor is to provide their own properly maintained Portable Potty. Contractor is to maintain a clean, orderly, and safe project perimeter to include dirt washouts, grass cutting, and orderly materials and equipment. The contractor shall provide underground utility investigation in consultation with all available VA documentation. The contractor will additionally utilize PA Call before you dig to assess any PECO and PA American Water lines along Blackhorse Hill Road. Contractors are to provide EPA approved concrete washout containers. All demolished concrete will be recycled, and receipts provided to the COR. The contractor shall wash off all vehicles to prevent the spread of mud. The contractor is responsible to identify all utilities underground with ground penetrating radar, keep a paper copy on the jobsite, and provide the digital mapping to the COR for the CVAMC database. The contractor shall repair all damages incurred in the vicinity of the construction site and have all grading to be hand raked, adding four inches of topsoil on the south side of Blackhorse Hill Road, grass-seeded and covered with straw-infused mesh and watered until project completion.
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- 36C24425B0022_1.docx3.4 MB, August 8, 2025
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Home Maintenance Group LLC
- UEI
- ZNA6CVUBL175
- CAGE
- 5E2M4
- Vendor location
- Chadds Ford, PA
- Contract
- 36C24425C0063, definitive contract
- Obligated
- $111,109.35
- Actions
- 2 between September 29, 2025 and July 14, 2026
- Competition
- Full and Open Competition After Exclusion of Sources, 2 offers received
- Set-aside reported
- Service Disabled Veteran Owned Small Business SET-ASIDE
- Described as
- Install New CLC Accessible Route Phase 1
- Match
- solicitation number 36C24425B0022 equals the FPDS solicitation identifier; same awarding office 36C244 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 23, 2025
Presolicitation
Due August 6, 2025 at 10:00 AM EDT. SAM.gov, notice d4eaa00850dd4937b897633e7d0814fc
August 8, 2025
Solicitation, originally presolicitation
Due September 4, 2025 at 10:00 AM EDT. SAM.gov, notice 77ff9da37bc04549bc98055658365682
August 20, 2025
Solicitation
Due September 16, 2025 at 10:00 AM EDT. SAM.gov, notice d9c409d43c294a40be31ed1fcee65917
5 revisions on SAM
- September 30, 2025: publish, solicitation
- September 9, 2025: publish, solicitation
- July 23, 2025: publish, presolicitation
- August 20, 2025: publish, solicitation
- August 8, 2025: publish, solicitation
September 9, 2025
Solicitation
Due September 16, 2025 at 10:00 AM EDT. SAM.gov, notice 1224d3edbdff40c08ad812d5c3652a51
5 revisions on SAM
- September 30, 2025: publish, solicitation
- September 9, 2025: publish, solicitation
- July 23, 2025: publish, presolicitation
- August 20, 2025: publish, solicitation
- August 8, 2025: publish, solicitation
September 30, 2025
Solicitation
Due September 16, 2025 at 10:00 AM EDT. SAM.gov, notice 808824552df645e7b5a9ff90ffb6b42d
5 revisions on SAM
- September 30, 2025: publish, solicitation
- September 9, 2025: publish, solicitation
- July 23, 2025: publish, presolicitation
- August 20, 2025: publish, solicitation
- August 8, 2025: publish, solicitation
Points of contact
- Vanessa V Chmielewski, Contract Specialistvanessa.chmielewski@va.gov