Award notice, total small business set-aside, first published as combined synopsis and solicitation
EWP Kanawha County Streambank Stabilization Sharon Hollow and Ohley Hollow Road, WV
12FPC326B0010
Farm Production and Conservation Business Center, Fpac Bus Cntr-Acq Div. Other Heavy and Civil Engineering Construction.
Awarded
$120,440.71 obligated so far on USAspending
Description
As published on SAM.gov with the combined synopsis and solicitation of June 24, 2026.
See changes to Ohley Hollow Rd. Drawings and to Specification document - updated 6/15/2026.
Changes to the Ohley Hollow Road Drawings: Note showing the potential that an abandoned septic tank (unknown location) may be encountered and will need to be decommissioned if it is disturbed. Note showing the location of a pet cemetery and to avoid this location. Note showing a temporary fence must be constructed between the corner of the house and the fence along the road. Changes to the specs:
Seeding Spec: Added a different seed mixture for the Ohley site. Added note showing the maximum rock size shall be ½” in top 1-1/2” where the special seedbed preparation is required. Added note specifying compacted and disturbed areas must be loosened and blended into adjacent area to remove depressions.
Mob Spec: Added procedure for decommissioning an abandoned septic tank if one is disturbed. Added requirement to remove concrete from chain link posts if they are going to be reused. Added requirement that temporary fence must be constructed at the Ohley site Please see attachments and comibined synopsis solicitaiton for further deatails. Kanawha County EWP 5091-001 Streambank Stabilization Sharon Hollow and Ohley Hollow Road for USDA NRCS-WV.
The project consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish and the shaping of the channel. Installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities. Preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
The work consists of the mobilization and demobilization of the contractor’s forces and equipment necessary for performing the work required under the contract. Establishing traffic control and maintaining safe, convenient use of public roads and right of way. Removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It must include:
(1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions;
(2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required. Excavation required by the drawings and specifications, as well as the disposal of the excavated materials. Construction of earth embankments, other earthfills, and earth backfills required by the drawings and specifications. *See Specifications document attached to posting for full details of required work.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Focused Asset Management LLC
- UEI
- JW91W3WWJY45
- CAGE
- 9WUP4
- Vendor location
- Gary, IN
- Contract
- 12FPC326C0006, definitive contract
- Obligated
- $120,440.71
- Actions
- 1 between August 14, 2026 and August 14, 2026
- Competition
- Competed Under SAP, 9 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- Streambank Stabilization Measures for the Emergency Watershed Protection Program (Ewp) Nrcs-Wv
- Match
- solicitation number 12FPC326B0010 equals the FPDS solicitation identifier; same sub-agency 12D0 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
June 24, 2026
Combined synopsis and solicitation
NRCS-WV Kanawha County EWP Streambank Stabilization Sharon Hollow and Ohley Hollow Road
Due June 24, 2026 at 1:00 PM EDT. SAM.gov, notice 0ec4d4e34472444b8ecd52cecf88bcd6
August 14, 2026
Award notice
Awarded to FOCUSED ASSET MANAGEMENT LLC Gary for $120,441. SAM.gov, notice d984ef1bb7e04c3db5955c5efa0e2fc9
Points of contact
- Mark Domingomark.domingo@usda.gov
Also open from this buyer
- Long-Term Seed Storage: Climate Controlled Walk-In CoolerCombined synopsis and solicitationSmall businessNAICS 333415Hawaii12FPC326Q0054Closes todaySep 16
- Portable Mainline Inspection System (Pipe Cameras)Combined synopsis and solicitationSmall businessNAICS 33399812FPC126Q0040Closes todaySep 16
- Janitorial Services - Kenton Service Center, Hardin County, OHCombined synopsis and solicitationSmall businessNAICS 561720Ohio12FPC426Q0074Closes todaySep 16
- USDA NRCS Puerto Rico Moving Relocation Services_Post-Closing Amendment 0002Combined synopsis and solicitationSmall businessNAICS 484210Puerto Rico12FPC426Q0062Closes todaySep 16
- Desiccant Dehumidifier System Replacement Project Plant Material Center, Tucson, AZCombined synopsis and solicitationSmall businessNAICS 238220Arizona12FPC322Q0049Closes todaySep 16