Solicitation, total small business set-aside
Copper Creek - Road Repaving
1282B124R0058
Forest Service, USDA Forest Service-Spoc Im. Highway, Street, and Bridge Construction.
Response deadline
August 19, 2024 at 12:00 PM EDT
Closed 804 days ago. Posted August 12, 2024, first published July 18, 2024. Scheduled to archive September 3, 2024.
Get the next one like this from Forest Service by email, the day it is posted.Find my opportunities
This one closed in 2024
36 like it are open now in highway, street, and bridge construction
- Custer Gallatin National Forest Ashland and Sioux Road Maintenance
Forest Service, Wallowa Whitman National Forest
Combined synopsis and solicitationSmall businessNAICS 237310Billings, MT1240BE27Q0003Closes in 374 daysNov 10, 2027 - FY27 NRM - Correct Mather Loop Road and Install Speed Bumps
Department of Veterans Affairs, 261-Network Contract Office 21
Sources soughtNAICS 237310Mather, CA36C26127Q0112Closes tomorrowNov 2 - BRCA 310427 Southbound Shuttle Stop
National Park Service, DSC Contracting Services Division
SolicitationNAICS 237310Utah140P2026R0065Closes in 2 daysNov 3
Description
As published on SAM.gov.
**AMENDMENT 0002 - Change to Period of Performance and change to Section L, Factor 2, Proposed Construction Schedule and Work Plan of the Solicitation. Please see the following attachments:
Amendment 0002 attachment, Attachment 1, Revision 1, Statement of Work and Revision 1 Solicitation **AMENDMENT 0001 - Consolidated questions and answers, please see Amendment 0001 attachment** Project Title: Road Repaving – Copper Creek, Helena-Lewis and Clark National Forest, Montana 1. Background: The project consists of rehabilitation of existing asphalt as well as portions of new pavement. Specific improvements to Forest Road 330, M.P.
0.0-2.80 include, but are not limited to pulverizing existing asphalt; new pavement over pulverized base; new pavement sections; replacing base and subbase in select areas; culvert replacement; new chip seal; placing dust palliative from M.P. 2.8 to 4.75; and all other incidental items necessary to complete the project in accordance with the plans and specifications.
The contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and shall perform all work required to complete the project as shown on the plans, shown on the manufacturer’s shop drawings, and as described in the Standard Specifications (FP-14) and Forest Service Supplemental Specifications (FSSS).
2. Project Location: The project site is located in the Lincoln Ranger District of the Helena-Lewis & Clark National Forest - approximately 7 miles west of Lincoln in Lewis and Clark County, Montana. Refer to the location map on the title sheet of the plans.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 18, 2024
Solicitation, originally presolicitation
Due August 19, 2024 at 12:00 PM EDT. SAM.gov, notice 87e2ded3965b4436ada2cbe432888183
July 24, 2024
Solicitation
Due August 19, 2024 at 12:00 PM EDT. SAM.gov, notice eef497fd554e4c6e853bc48437066800
August 12, 2024
Solicitation
Due August 19, 2024 at 12:00 PM EDT. SAM.gov, notice adf382f881da4157b2c9233db329c014
Points of contact
- Holly Hlavacholly.hlavac@usda.gov
- Lucas Dahlmanlucas.dahlman@usda.gov