Solicitation, total small business set-aside
LOWER BOOTH RIPRAP
1282B124Q0107
Forest Service, USDA Forest Service-Spoc Im. Highway, Street, and Bridge Construction.
Response deadline
September 3, 2024 at 5:00 PM EDT
Closed 789 days ago. Posted August 21, 2024. Scheduled to archive September 18, 2024.
Get the next one like this from Forest Service by email, the day it is posted.Find my opportunities
This one closed in 2024
36 like it are open now in highway, street, and bridge construction
- FY27 NRM - Correct Mather Loop Road and Install Speed Bumps
Department of Veterans Affairs, 261-Network Contract Office 21
Sources soughtNAICS 237310Mather, CA36C26127Q0112Closes tomorrowNov 2 - BRCA 310427 Southbound Shuttle Stop
National Park Service, DSC Contracting Services Division
SolicitationNAICS 237310Utah140P2026R0065Closes in 2 daysNov 3 - TX FW LGA 10(5) Steve Thompson Wildlife Drive
Federal Highway Administration, 6982AF Central Federal Lands Divisi
SolicitationSmall businessNAICS 237310Los Fresnos, TX6982AF27B000006Closes in 2 daysNov 3
Description
As published on SAM.gov.
This contract is for the furnishing, hauling and placement of South Dakota Class B riprap at four (4) designated locations on and near the dam as described in the Specifications and shown on the Drawings. Before the riprap is to be placed, minor excavation of the identified streambed and head-cut areas described in the Specifications and shown on the Drawings will occur and drainage fabric will be placed according to the Specifications and shown on the Drawings.
Additional South Dakota Class B riprap will be stockpiled at a location designated by the Government. After all ground disturbance activities have been completed, seeding and the placement of erosion control materials as described in the Specifications and shown on the Drawings will be the responsibility of the contractor. Work for the Lower Booth Dam Riprap project consists of the following:
Furnish, haul, and place South Dakota Class B ripap at four (4) designated locations on and near the dam as described in the Specifications and Shown on the Drawings. Furnish and place Type B Drainage Fabric under the riprap as described in the Specifications and Shown on the Drawings. Additional South Dakota Class B riprap will be stockpiled at a location designated by the Government. Excavate the streambed and head-cut areas as described in the Specifications and Shown on the Drawings. Seed and place erosion control materials at locations as described in the Specifications.
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
August 21, 2024
Solicitation, originally presolicitation
Due September 3, 2024 at 5:00 PM EDT. SAM.gov, notice 97ab02f26348423aa71a92fd97f0e605
Points of contact
- Steven Dahlgrensteven.dahlgren@usda.gov
- JESSICA LYN H. RASMUSSENJESSICA.RASMUSSEN@USDA.GOV