Award notice, total small business set-aside, first published as presolicitation
LOLO NATIONAL FOREST - Upper West Fork Fish Creek Trail Bridge Replacement
1240LU25R0011
Forest Service, Lolo National Forest. Highway, Street, and Bridge Construction.
Awarded
$575,450.00 on the award notice, August 20, 2025, contract 1240LU25C0016
Get the next one like this from Forest Service by email, the day it is posted.Find my opportunities
This one was awarded in 2025
34 like it are open now in highway, street, and bridge construction
- Custer Gallatin National Forest Ashland and Sioux Road Maintenance
Forest Service, Wallowa Whitman National Forest
Combined synopsis and solicitationSmall businessNAICS 237310Billings, MT1240BE27Q0003Closes in 371 daysNov 10, 2027 - PRIMARY RUNWAY AND PAVEMENT REPAIRS LOCATED AT JOINT RESERVE BASE NEW ORLEANS, LOUISIANA.
Department of the Navy, Navfacsyscom Southeast
PresolicitationNAICS 237310New Orleans, LAN6945027R0007Closes todayNov 4 - WY BR WYAO US20(1) US 20 and Hayden Arch Bridge Repairs
Federal Highway Administration, 6982AF Central Federal Lands Divisi
Sources soughtNAICS 237310Cody, WY6982AF27SS00001Closes todayNov 4
Description
As published on SAM.gov.
The intent of the contract is to remove and replace an existing trail bridge and substructure elements on Trail 101, milepost 3.1 on the Ninemile Ranger District, Lolo National Forest, within the Great Burn Proposed Wilderness. The structure is located in Section 19, Township 13 North, Range 25 West, Mineral County, Montana. The contractor is to furnish the replacement trail bridge structure and substructure.
This project includes, but is not limited to, removing and disposing of the existing trail bridge and substructure elements, structural excavation and installation of foundation components, furnishing, loading, hauling and erecting the bridge, adjustment of adjacent trail grades to match design plans, and all other incidental items necessary to complete the work according to the contract. This project is located within a proposed wilderness area therefore a list of Resource Protection Measures and Restricted Equipment is required for this project
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Oregon Woods, Inc.
- UEI
- DWBRENSC9MM3
- CAGE
- 1XBA2
- Vendor location
- Eugene, OR
- Contract
- 1240LU25C0016, definitive contract
- Obligated
- $575,450.00
- Actions
- 1 between August 18, 2025 and August 18, 2025
- Competition
- Full and Open Competition After Exclusion of Sources, 6 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- Gaoa Upper West FK Fish Creek Trail Bridge: Construction, Fabrication, and Assembly of a New Stock Bridge to Replace the Current Deteriorating Bridge.
- Match
- award number 1240LU25C0016 equals the contract number; same sub-agency 12C2 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 16, 2025
Presolicitation
SAM.gov, notice 310eadbac9314e60a2557189128610ac
June 2, 2025
Solicitation, originally presolicitation
Due July 7, 2025 at 6:00 PM EDT. SAM.gov, notice 23566c41a3dc448aa9bbf18ae19239a6
June 20, 2025
Solicitation
Due July 7, 2025 at 6:00 PM EDT. SAM.gov, notice ff37966d55d64712b4368cac73d6066d
August 20, 2025
Award notice, originally solicitation
Awarded to Oregon Woods, Inc. for $575,450. SAM.gov, notice 5b68d1a1183e4cd59b32a24fac93ddae
2 revisions on SAM
- August 20, 2025: publish, award notice
- June 20, 2025: publish, solicitation
Points of contact
- Alisha Knaubalisha.knaub@usda.gov4064382981