Upper Baker Installing Trailer Pads and Utilities
1240LT26Q0126
Forest Service, Manti-Lasal National Forest. Water and Sewer Line and Related Structures Construction.
Response deadline
August 10, 2026 at 7:00 PM EDT
Closed 83 days ago. Posted July 7, 2026. Scheduled to archive August 25, 2026.
Get the next one like this from Forest Service by email, the day it is posted.Find my opportunities
This one closed in 2026
25 like it are open now in water and sewer line and related structures construction
- Ross Springs Waterline Replacement
Forest Service, Ashley National Forest
Combined synopsis and solicitationSmall businessNAICS 237110Utah1240LT27Q0022Closes in 20 daysNov 21 - YOSE 22866 Rehabilitate Hodgdon Meadows Water System and YOSE 196755 Extend Hod
Departmental Offices, National Park Service Contracting Activity
Sources soughtNAICS 237110Location not published140PP027R0009Closes tomorrowNov 2 - Request for Information/Market Intelligence Notice: Use of Progressive Design Build (PDB) with Other Transaction Authority (OTA) - Fort Hunter-Liggett Water System Improvements
Department of the Army, W072 Endist Louisville
Sources soughtNAICS 237110Lockwood, CAW912QR-PDB-FHLWATERCloses in 2 daysNov 3
All 25 open in water and sewer line and related structures construction
Description
As published on SAM.gov.
This contract is comprised of installing utility lines, connections to existing lines and connections to trailer pads. Utilities included are electrical, water and sewer. Option items included are trenching, providing and spreading gravel and installation of an asphalt apron. Water and Sewer lines and connections must be kept 10ft apart. Contractor must work with and is responsible for all communications, supplies and permits with utility companies associated. All utilities will be installed in compliance with State and/or San Juan County code.
Utilities –
Water - The new water line will be connected to the existing water line between the meter and bunkhouse. Main water line will remain same size as existing line. Existing line is a 2” poly line. New water line will be a 2” HDPE blue Poly and connect to existing. One stop and waste to be installed within 5ft of new and existing line connection.
Sewer – The new sewer line will be connected to the existing sewer line at the bunkhouse. Main line will be 6” with trailer connections being 6” to 3” Wye’s. Drainage must remain between 1/8” – ¼” per ft across the entirety of the line. Must meet state code.
Electrical – A transformer and drop-down meter will need to be coordinated and installed with Empire Electric and conduit and wiring ran from meter to the trailer pads. Contractor will be responsible for determining sizing of conduit and wiring. Must meet state code.
Option Items –
Trenching and Backfilling – Trenching will need to be 36” deep to meet frost line requirements.
Crushed Aggregate – Grade G Road Base for the trailer pads and roadway
Attachments
Files listed on SAM.gov. The ones we hold a copy of download from here; the rest open SAM's download, which needs no account.
- C04 WD San Juan County Utah 1240LT26Q0126.pdf62 KB, July 7, 2026
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 7, 2026
Combined synopsis and solicitation
Due August 10, 2026 at 7:00 PM EDT. SAM.gov, notice 951967d44bd44757925a825597357cf3