RSA Primary Substation 4, Redstone Arsenal, AL

W9127825R0020

Department of the Army, W074 Endist Mobile. Power and Communication Line and Related Structures Construction.

Awarded

Cci Facility Contractors, LLC

$69,247,439.99 obligated so far on USAspending

Description

As published on SAM.gov.

Construct a high voltage Electrical Primary Substation on Redstone Arsenal, Alabama. The project includes installation of high voltage electrical power transmission lines that will connect the new substation directly to existing substations, and to the future 3rd Tennessee Valley Authority (TVA) 161,000-volt transmission electrical power transmission feed. Work includes the substation, transformers, primary and secondary voltage switchgear with associated distribution loop, cable vault, control room and all associated duct banks with cabling.The North American Industry Classification System (NAICS) code for this project is 237130.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
EMTHHYMHF7J6
CAGE
7R4R5
Vendor location
Anchorage, AK
Contract
W9127826CA003, definitive contract
Obligated
$69,247,439.99
Actions
2 between December 22, 2025 and February 9, 2026
Competition
Full and Open Competition, 4 offers received
Set-aside reported
No Set Aside Used.
Described as
Rsa Primary Substation 4 Redstone Arsenal, Al
Match
solicitation number W9127825R0020 equals the FPDS solicitation identifier; same awarding office W91278 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. October 30, 2024

    Sources sought

    Substation (Primary 4), Redstone Arsenal, AL

    Due November 13, 2024 at 3:00 PM EST. SAM.gov, notice 0553325c881e4b1bbbb14dd7a83478ab

  2. December 12, 2024

    Special notice

    RSA Primary Substation 4 - Notice of Intent (NOI)

    Due December 20, 2024 at 6:00 PM EST. SAM.gov, notice f8361b1c5ed54067826d155bd38b401b

  3. December 16, 2024

    Sources sought

    Substation (Primary 4), Redstone Arsenal, AL

    Due December 20, 2024. SAM.gov, notice 920d5755efba41abacd206c34b5681d0

  4. December 16, 2024

    Sources sought

    Substation (Primary 4), Redstone Arsenal, AL

    Due December 20, 2024 at 4:00 PM EST. SAM.gov, notice cdc05b2548ec4c6ea6b1adba1188bbae

  5. January 8, 2025

    Presolicitation

    Due January 23, 2025 at 2:00 PM EST. SAM.gov, notice 99ee91ce8d244d1ea99739bd89d57e88

  6. February 26, 2025

    Sources sought

    Substation (Primary 4), Redstone Arsenal, AL

    Due February 28, 2025 at 4:00 PM EST. SAM.gov, notice 69b3b396076546499ce377be43701f07

  7. February 26, 2025

    Sources sought

    Substation (Primary 4), Redstone Arsenal, AL

    Due February 28, 2025 at 4:00 PM EST. SAM.gov, notice 86262feb6f694b01b748158e527b50a2

  8. March 6, 2025

    Solicitation, originally presolicitation

    Due April 14, 2025 at 3:00 PM EDT. SAM.gov, notice 5f65f91fbd20460d84561dadc61cd1b1

  9. March 18, 2025

    Solicitation

    Due April 14, 2025 at 3:00 PM EDT. SAM.gov, notice 3d632f8657a54dafb9ada7b00e609306

  10. March 26, 2025

    Solicitation

    Due April 14, 2025 at 3:00 PM EDT. SAM.gov, notice 0ef6be8cd29c457f92f59c9dd724d469

  11. March 31, 2025

    Solicitation

    Due April 14, 2025 at 3:00 PM EDT. SAM.gov, notice d623e78cac0d4c25a45f32cb5fefe948

  12. April 2, 2025

    Solicitation

    Due April 14, 2025 at 3:00 PM EDT. SAM.gov, notice 6bde18bdf7b74496ab26eb2363265eaf

Points of contact