Award notice, total small business set-aside, first published as presolicitation
BITTERROOT NATIONAL FOREST - Little Rock Creek Trail Bridge Replacement
1240LU24Q0059
Forest Service, Bitterroot National Forest. Highway, Street, and Bridge Construction.
Awarded
$259,670.00 obligated so far on USAspending
Description
As published on SAM.gov with the solicitation of August 27, 2024.
PROJECT DESCRIPTION: The project is for the removal of an existing 35-ft single log foot bridge over Little Rock Creek on Forest Service Trail #580 at milepost 2.87, and installing a new 41-ft glulam stringer pack/pedestrian trail bridge with rock-filled gabion basket foundation. This project includes:
1) Dispose of an existing approximate 35-ft long single log foot bridge, 2) Construction of a new 41-ft, glulam stringer bridge, including associated trail approach work, footings, and drainage improvements.
PROJECT LOCATION: This project is located at milepost 2.87 over Little Rock Creek on Forest Trail # 580 on the Darby Ranger District, USFS, in Ravalli County, MT, Section 35, Township 4 North, Range 22 West. The project is approximately 3 miles west of the Lake Como Recreation Area, which is located approximately 8 miles northwest of Darby, MT. This project is located three miles from the closest road. Helicopter flights and mechanized/motorized use is allowed at the site. There is no vehicular access to the bridge site.
PERIOD OF PERFORMANCE: It is anticipated that work can begin September 15, 2025 with work being completed by November 14, 2025. Contract period of performance is 60 days. MAGNITUDE OF CONSTRUCTION (per FAR 36.204(b)): Between $100,000 and $250,000. AMENDMENT 001 - Updated Attachment J-2 Standard Glulam Stringer Trail Bridge Drawings Question and Answers as of 8/23/2024 Updated Questions and Answers as of 8/27/2024
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Oregon Woods, Inc.
- UEI
- DWBRENSC9MM3
- CAGE
- 1XBA2
- Vendor location
- Eugene, OR
- Contract
- 1240LU24C0053, definitive contract
- Obligated
- $259,670.00
- Actions
- 1 between September 24, 2024 and September 24, 2024
- Competition
- Competed Under SAP, 4 offers received
- Set-aside reported
- Small Business Set Aside - Total
- Described as
- Little Rock Creek Trail Bridge Replacement
- Match
- award number 1240LU24C0053 equals the contract number; same sub-agency 12C2 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
July 2, 2024
Presolicitation
SAM.gov, notice 9e280bebf3cc4c4091121cece3b00247
August 2, 2024
Solicitation, originally presolicitation
Due August 26, 2024 at 6:00 PM EDT. SAM.gov, notice 659932bb4f9e4a67a39cb87f71a27148
August 23, 2024
Solicitation
Due September 3, 2024 at 6:00 PM EDT. SAM.gov, notice 030ead39089740a797ffc3ba414b7890
August 27, 2024
Solicitation
Due September 3, 2024 at 6:00 PM EDT. SAM.gov, notice 164bae2796f64aefa6e4409aad6f3e2b
September 24, 2024
Award notice, originally solicitation
Awarded to OREGON WOODS, Inc. Eugene for $259,670. SAM.gov, notice 6bf1b2f68a29459184aa53f0ad59cdd6
Points of contact
- Alisha Knaubalisha.knaub@usda.gov406-438-2981