Skip to content
Abierto

Solicitation, total small business set-aside

Amend 0001 Mussel survey and relocation efforts

W9126G24Q0043

Department of the Army, W076 Endist FT Worth. Environmental Consulting Services.

Awarded

Howard Roark, LLC

$49,301.02 obligated so far on USAspending

Description

As published on SAM.gov.

Amendment 0001 is to extend response due date from 17 May 2024 to 24 May 2024 1000am CDT.-------------------------Mussel survey and relocation efforts. Fort Worth District has drafted a plan to mitigate channel erosion caused by flooding through bank stabilization in order to protect local, state, and federal interest for the Waco Treatment Facility, Texas.

Proposed construction for this project is scheduled to start late spring or early summer of 2024. There is one state threatened (TAC 2020), federally proposed mussel species (USFWS 2021), Texas Fawnsfoot (Truncilla macrodon), that inhabit the middle Brazos River and the project area falls within the range of the proposed critical habitat A survey upstream of the Waco Treatment Facility by BioWest indicated that Texas Fawnsfoot are present near the project area (BioWest Personal Communication).

USACE Worth Districts approach is to have surveys conducted for freshwater mussels at the construction sites along the streambanks and main channel of the Brazos River near the Waco Treatment Facility for relocation efforts with a focus on minimizing risk to Texas Fawnsfoot. Sampling activities will follow approved standardized protocols and will be coordinated with the Texas Parks and Wildlife Department and the U.S. Fish and Wildlife Service.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
KXAVF9FE5MW9
CAGE
8Q7M9
Vendor location
San Marcos, TX
Contract
W9126G24P0065, purchase order
Obligated
$49,301.02
Actions
2 between September 6, 2024 and November 20, 2024
Competition
Competed Under SAP, 3 offers received
Set-aside reported
Small Business Set Aside - Total
Described as
Base Mussel Survey. Fort Worth District Has Drafted a Plan to Mitigate Channel Erosion Caused by Flooding Through Bank Stabilization in Order to Protect Local, State, and Federal Interest for the Waco Treatment Facility, Texas.
Match
solicitation number W9126G24Q0043 equals the FPDS solicitation identifier; same awarding office W9126G (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. April 30, 2024

    Solicitation

    Mussel survey and relocation efforts

    Due May 17, 2024 at 11:00 AM EDT. SAM.gov, notice 825ce8b21fc24e0da24d5565a1a78f69

  2. April 30, 2024

    Solicitation

    Mussel survey and relocation efforts

    Due May 17, 2024 at 11:00 AM EDT. SAM.gov, notice cef5bfaa90b04c2dbe60bc9746437843

  3. May 16, 2024

    Solicitation

    Due May 24, 2024 at 11:00 AM EDT. SAM.gov, notice 1f6462035e824c8fa38888fdfdcfc36b

  4. May 16, 2024

    Solicitation

    Due May 24, 2024 at 11:00 AM EDT. SAM.gov, notice 3ab48c812228488aa7c38f763a0361c5

Points of contact