Skip to content
Abierto

Award notice, total small business set-aside, first published as presolicitation

Military Ocean Terminal Concord (MOTCO) Main Street Repair

W9123824B0013

Department of the Army, W075 Endist Sacramento. Highway, Street, and Bridge Construction.

Awarded

Martin Brothers Construction

$5,250,526.78 obligated so far on USAspending

Description

As published on SAM.gov with the solicitation of September 13, 2024.

AMENDMENT 0003 - Update Wage Determination Rates to rates updated on September 6th, 2024.AMENDMENT 0002 - Adds attachments: GP 102, Geotech Report and updated DBA Construction Rates.AMENDMENT 0001 - extends the bid due date to 9/13 and incorporates the latest wage determination.

The United States Army Corps of Engineers (USACE) Sacramento District (SPK) anticipates soliciting for design-bid-build construction services to be performed in support of the Military Ocean Terminal Concord (MOTCO) Main Street repairs at Concord, CA.

The contractor will be required to provide all labor, material, equipment, and supervision to repair Main Street, a cantonment area road, to an acceptable condition to support the movement of ammunition-laded vehicular traffic between the three ocean piers located at MOTCO and the ammunition staging and transfer areas.

The maximum load capacity for the roads is eighty-six (86) tons per vehicle (TEREX) for the entire length of the road, and all repair, replacement, or upgrade must meet applicable California Department of Transportation (CALTRANS) specifications regarding subgrade preparation, compaction, materials, and placement. Street lighting will be installed along the road.

The new road geometry and street lighting may require the relocation of some existing utilities inclusive of electrical, communication, water, sewer, and storm drain, and crossing of railroad tracks. Contractor will need to provide ground penetrating radar to check for underground utilities.

Currently MOTCO base access is restricted to those individuals holding United States citizenship and who have been vetted through the MOTCO security office.The Government anticipates a 384-day Period of Performance for this project.

In accordance with Federal Acquisition Regulation Supplement (FAR) 36.204(f), the Government currently estimates the magnitude of the construction for this project to be [$1,000,000 and $5,000,000].This prospective contract action will be conducted using NAICS Code 237310 (Highway, Street, and Bridge Construction). The size standard is $45 Million. Product Service Code is Y1LB (Construction of Highways, Roads, Streets, Bridges, and Railways).

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
YUS3LBSE3WB6
CAGE
1QM33
Vendor location
Sacramento, CA
Contract
W9123824C0027, definitive contract
Obligated
$5,250,526.78
Actions
6 between September 30, 2024 and September 18, 2025
Competition
Full and Open Competition After Exclusion of Sources, 5 offers received
Set-aside reported
Small Business Set Aside - Total
Described as
Pavement 10+91.5 to 30+02.21
Match
solicitation number W9123824C0027 was reused as the contract number; same awarding office W91238 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. July 16, 2024

    Presolicitation

    Main Street Repairs for MOTCO, Concord, CA

    Due July 31, 2024 at 1:00 PM EDT. SAM.gov, notice 98f3fca86a5641a7805d3f3185c9ac5e

  2. August 6, 2024

    Solicitation

    Due September 6, 2024 at 2:00 PM EDT. SAM.gov, notice ff338da2993f4bb1a8d55cb151e25d79

  3. August 27, 2024

    Solicitation

    Due September 6, 2024 at 1:00 PM EDT. SAM.gov, notice 0705d8b5c544457bb9ca2af3bee1d529

  4. August 30, 2024

    Solicitation

    Due September 13, 2024 at 2:00 PM EDT. SAM.gov, notice 0c621dffcf7b413aaefd23bd8d63aa92

  5. September 5, 2024

    Solicitation

    Due September 13, 2024 at 1:00 PM EDT. SAM.gov, notice 8aa2ca101d5148ed9c1723206436318e

  6. September 6, 2024

    Solicitation

    Due September 13, 2024 at 2:00 PM EDT. SAM.gov, notice 0546c23188704024a3a64cb2397ead63

  7. September 9, 2024

    Solicitation

    Due September 13, 2024 at 2:00 PM EDT. SAM.gov, notice 7175efc2a91548ad9b4f0e05a274ca16

  8. September 13, 2024

    Solicitation

    Due September 13, 2024 at 2:00 PM EDT. SAM.gov, notice 373abc85e47c4d79b84ed0d7724060a0

  9. September 30, 2024

    Award notice, originally solicitation

    Awarded to MARTIN BROTHERS CONSTRUCTION Sacramento for $4,997,111. SAM.gov, notice 43cfda65d0204919ab62f5adc812dd67

Points of contact