Award notice, first published as combined synopsis and solicitation
DB Simulation Facility, at Fort Magsaysay (FMSS), Nueva Ecija, Philippines
N6274224R6713
Department of the Navy, Navfacsyscom Pacific. Commercial and Institutional Building Construction.
Awarded
$1,953,188.84 obligated so far on USAspending
Description
As published on SAM.gov with the combined synopsis and solicitation of September 4, 2024.
Amendment 0005 to Solicitiation N6274224R6713 is issued, per attached. Proposal due date is changed to 9 September 2024, no later than 11:00 a.m. Thailand time. Please acknowledge reciept of this Amendment.
Amendment 0004 of Solicitation N6274224R6713 is released per attached. Proposal due date is unchanged and remains of 23 August 2024 no later than 11:00 a.m. Thailand time. Please acknowledge receipt of the amendment.
Amendment 0003 of Solicitation N6274224R6713 is released per attached. Proposal due date is changed to 23 August 2024 no later than 11:00 a.m. Thailand time. Please acknowlege receipt of the amendment.
Amendment 0002 of Solicitation N6274224R6713 is released per attached. Proposal due date is extended to 20 August 2024 no later than 11:00 a.m. Thailand time.
Amendment 0001 of Solicitation N6274224R6713 is released per attached. Proposal due date is extended to 15 August 2024 no later than 11:00 a.m. Thailand time.
Solicitation N6274224R6713 is released per attached. Proposal due date is 9 August 2024, no later than 11:00 a.m. Thailand time. Exhibit A PPI form and Exhibit D Blank BOQ (excel files) are attached for your use. Pre-solicitation Site Visit (PPSV)) is scheduled on 17 July 2024 at 09:00 a.m. local time, meeting point at North Gate of Fort Magsaysay, Palayan City, Nueva Ecija, Philippines, GPS Coordinates: 15°26'25.27"N, 121° 4'59.78"E.
NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS ANNOUNCEMENT OR ANY FOLLOW-UP INFORMATION REQUESTS. No telephone calls will be accepted requesting a bid package or solicitation. There is no bid package or solicitation currently available. In order to protect the integrity of any future procurement that may arise from this announcement, information regarding the technical point of contact will not be given and no appointments for presentations will be made.
Notice Type:
Combined Synopsis/Solicitation Response Date: May 21, 2024, 11:00 am Thailand Time This notice aims to provide public notice of a forthcoming project at Fort Magsaysay (FMSS), Nueva Ecija, Philippines. The government plans to issue a solicitation approximately June or July 2024. This notice also aims to collect names of contractors interested in attending the site visit for the Base Access Request (BAR) that will be facilitated by the US Government.
Projects Description: This is a Design-Build project for a new construction located within the boundaries of Fort Magsaysay (FMSS), Nueva Ecija, Philippines. These facilities must be designed and constructed in accordance with either Unified Facilities Criteria (UFC), International Building Codes (IBC), or Philippines Codes as stated in the Request for Proposal (RFP). The proposed projects are as follows:
Simulation Facility. Construct a single-story concrete masonry unit (CMU) structure with steel c-channel members supporting the roof structure. The overall concrete building slab area shall be 38 m x 9 m (125ft x 30 ft). The facility structure is constructed of 0.3 m x 0.3 m (1 ft x 1 ft) reinforced concrete columns and reinforced concrete masonry unit (CMU) infill. The roof structure is constructed of steel supported on concrete roof beams.
The interior areas will be constructed of 100 mm (4 in) reinforced CMU block walls infilled between the concrete columns, with cement plaster on each side to extend 150 mm (6 in) above the ceiling. Clear ceiling height shall be a minimum of 2.70 m (8 ft-10 in), and ceiling material shall consist of 610 mm x 610 mm (2 ft x 2 ft) acoustical tile ceiling on a painted ceiling grid system. The maintenance bay requires 820 feet (250 meters) of powerline addition.
Project Magnitude is between US$1,000,000 and US$5,000,000 (FAR 36.204 Disclosure of the magnitude of construction projects). A Pre-Proposal Site Visit (PPSV) for this project is tentatively scheduled for June through July 2024. The site visit is to provide Offerors with an opportunity to familiarize themselves with the job sites and conditions to be encountered and is not for the purpose of answering questions.
Offerors interested in the project are required to submit the attached Base Access Request (BAR) and fill in your information in the attached Base Access Request (BAR) form / provide required information for the PPSV. Submit it to the site access coordinators listed below by May 21, 2024. To:
Ms. Marivic Marquez (Site Access Coordinator)
Email: MarquezMM@state.gov cc: nitiwate@state.gov; williamsrg@state.gov Note: -Contractors may submit up to 4 names (2 primaries and 2 alternates), but only 2 participants, 1 driver, and 1 vehicle, per company shall be allowed to attend the PPSV. The driver can enter the base but must remain in the vehicle throughout the site visit.
The driver is not permitted to attend the site visit or replace any of the attendees during the site visit and must present a valid form of identification or passport for base access. -This base access process is only for the list of attendees the US Government is facilitating. Contractors that request access after the required date will not be added to the US Government list but will still be allowed to attend the site visit with two attendees if they can get access to the base on their own.
This is a limitation imposed by the host nation. Contractors are not allowed to inspect the project sites outside of the scheduled site visits. Any Contractor that does a site inspection outside of the scheduled site will be disqualified and ineligible for award due to having a competitive advantage. - All information relevant to the site visits will be posted on SAM.gov.
Emails requesting confirmation for site visit times, locations, and other information that is clearly stated on SAM.gov will not be answered. -The tentative schedule of the site visit is on June 26-28, 2024.
The contract, on USAspending
Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.
- Recipient
- Capbuild Construction Corp.
- UEI
- LUD9THNJVCV9
- CAGE
- SAMX0
- Vendor location
- Makati
- Contract
- N6274224C6713, definitive contract
- Obligated
- $1,953,188.84
- Actions
- 1 between September 22, 2024 and September 22, 2024
- Competition
- Full and Open Competition, 12 offers received
- Set-aside reported
- No Set Aside Used.
- Described as
- Construct Simulation Facility
- Match
- award number N6274224C6713 equals the contract number; same awarding office N62742 (high confidence)
- Record
- USAspending award page
Publications
Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.
May 6, 2024
Combined synopsis and solicitation
Due May 21, 2024 at 12:00 AM EDT. SAM.gov, notice a1c030e5eca744f38108e866367d1851
June 3, 2024
Combined synopsis and solicitation
Due May 21, 2024 at 12:00 AM EDT. SAM.gov, notice 1b7db141ccec4f0ead3a50dfaa41f6cf
July 9, 2024
Combined synopsis and solicitation
Due May 21, 2024 at 12:00 AM EDT. SAM.gov, notice 13d709382e4340cda5afcf2c83d8052f
July 9, 2024
Combined synopsis and solicitation
Due May 21, 2024 at 12:00 AM EDT. SAM.gov, notice 2690a5e6c7984f8f90827605b36bd232
August 7, 2024
Combined synopsis and solicitation
Due August 15, 2024 at 12:00 AM EDT. SAM.gov, notice 904435b2eaae471495d3001763500310
August 13, 2024
Combined synopsis and solicitation
Due August 20, 2024 at 12:00 AM EDT. SAM.gov, notice 8c3ebe3a521b4a28954674bed7af9e95
August 18, 2024
Combined synopsis and solicitation
Due August 23, 2024 at 12:00 AM EDT. SAM.gov, notice 45a3fa0b01844db2b8113c78d2757b2c
August 20, 2024
Combined synopsis and solicitation
Due August 23, 2024 at 12:00 AM EDT. SAM.gov, notice 40c707a3000c4ccdb0207ec2df933771
September 4, 2024
Combined synopsis and solicitation
Due September 9, 2024 at 12:00 AM EDT. SAM.gov, notice 8ef30e4eacd7421d91387d8bd1b5fc4c
September 4, 2024
Combined synopsis and solicitation
Due September 9, 2024 at 12:00 AM EDT. SAM.gov, notice ba017597fba94debbe7542cc673fe3a0
September 26, 2024
Award notice, originally combined synopsis and solicitation
Awarded to CAPBUILD CONSTRUCTION Corp. Makati PHL for $1,953,189. SAM.gov, notice f132bcc14bea410d933068f7ecc52611
Points of contact
- Artitar Uditartitar@state.gov6622871036124
- Rondel WilliamsWilliamsRG@state.gov
Also open from this buyer
- Add Fuel Hydrant at Pumphouse 3 and 4, US NAVSUPPACT Andersen AFB, GuamSources soughtNAICS 237120GuamN62742DBBP722Closes in 6 daysSep 24
- RFP N62742-26-R-3601 Enterprise Construction Management Support Multiple Award Contract (ECMS MAC)SolicitationNAICS 541330N6274226R3601Closes in 11 daysSep 29
- WON 1665555, FY24 AJJY183012 (P-012), PDI: NORTH AIRCRAFT PARKING RAMP, ANDERSEN AIR FORCE BASE, GUAMSolicitationNAICS 237310GuamN62742-26-R-1300Closes in 21 daysOct 9