Skip to content
Abierto

Solicitation, first published as presolicitation

Supply: ABB HVAC VFD's

36C24824Q0301

Department of Veterans Affairs, 248-Network Contract Office 8. Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment Manufacturing.

Awarded

Results Sales & Service, L.L.C.

$221,018.00 obligated so far on USAspending

Description

As published on SAM.gov.

The purpose of this amendment is to post the responses to the questions posed.

Q&A window will close 02/14/2024.

Q&A We will need to know if these are pumps/fans/variable torque loads or constant torque loads. The VFD s will serve as the power source between the main service panel and fan motors of each air handler, the load varies during a power outage or voltage drop, the fans will constantly run at a set parameter within the VFD. We also need to know the required short circuit rating desired e.g 65KAIC, etc. and if an input circuit breaker or disconnect is needed as well.

The required short circuit rating desired current rating must be followed by the manufacture s recommendations and specifications chart that s provided with each VFD purchase, current, size, and voltage, we will utilize the I/O terminals for the motor control. Do you need a circuit breaker or fusible disconnect switch? ABB ACH550 VFD s has a disconnect switch/Circuit breaker mounted on the VFD, non-Fusible. What is the required SCCR for the panel? The required SCCR for the panel 100KA.

Do you want the VFD keypad mounted on the enclosure door? The VFD will be mounted on the opposite side of the wall or the air handler, designated mounting brackets. What pilot devices are required (H-O-A switch, VFD-Off-Bypass switch, Run light, Fault light, etc.). AAB VFD has and, H-O-A switch and VFD bypass switch with run/fault indicators. Is the application for variable torque or constant torque? Constant torque, the VFD at times will ramp down however the horse power remains the same.

The specification mentions 0.5Hz to 200Hz as the frequency range. Is this just a typical manufacturer spec or do you really need frequency above 60Hz? If the answer is above 60Hz, then the application details are critical. As you know available torque rolls off linearly above 60Hz, so by the time they hit 200Hz, the motor would theoretically only be able to produce about 60 / 200 = 30% of its rated torque. The real number will be lower because higher speeds increase the friction and windage losses. My best guess is that 20% is more realistic.

This is the manufactures specifications, we operate under 60 hertz we average our motors at 35 to 45 hertz, the manufacture specifies what the VFD capabilities can achieve if needed. I have a question regarding the VFD s on this request. I am assuming you are replacing existing Installed VFD s, would you happen to know or have the unit information that these VFD s are installed on? ABB is a manufacturer of VFD drives, but the drives are installed in bigger Air Conditioning assemblies.

If the existing unit information is provided, I may be able to locate the exact VFD that works for said unit. The VFD s are installed on Air Handler #12-2C Service Bay 2-5, building 100.

The contract, on USAspending

Federal procurement data the awarding office reported to FPDS, matched to this solicitation by its number.

UEI
HXNZFWKKHG38
CAGE
7JZL1
Vendor location
Clearwater, FL
Contract
36C24824P1110, purchase order
Obligated
$221,018.00
Actions
1 between April 4, 2024 and April 4, 2024
Competition
Competed Under SAP, 14 offers received
Set-aside reported
No Set Aside Used.
Described as
Abb HVAC VFDS
Match
solicitation number 36C24824Q0301 equals the FPDS solicitation identifier; same awarding office 36C248 (high confidence)

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. February 2, 2024

    Presolicitation

    Due February 21, 2024 at 1:00 PM EST. SAM.gov, notice 788e3901a3f940fd9cb97012c406d0e8

  2. February 2, 2024

    Solicitation, originally presolicitation

    Due February 19, 2024 at 1:00 PM EST. SAM.gov, notice da14dd094d4943bdb9a4cc5f7a624ea4

  3. February 12, 2024

    Solicitation

    Due February 21, 2024 at 1:00 PM EST. SAM.gov, notice 5bd35b1051a5439e88c829257b828b94

Points of contact