ZION 240182, South Entrance and Visitor Center Road Rehabilitation, Zion Nation

140P2025R0115

National Park Service, DSC Contracting Services Division. Highway, Street, and Bridge Construction.

Response deadline

September 2, 2025 at 1:00 PM EDT

Closed 381 days ago. Posted August 18, 2025. Scheduled to archive September 17, 2025.

Description

As published on SAM.gov.

Installation of roadways and a bridge within the project limits, including earthwork, grading, base course, and surfacing. Installation of a roundabout at the entrance to the Visitor Center at Visitor Center Road. This project requires at all times that traffic be maintained to the visitor facilities and bus maintenance facilities. Installation of signs and striping throughout the project site. Installation of drainage infrastructure to accommodate surface flows throughout the site.

The infrastructure includes underground culverts in addition to ditches and swales. Installation of landscaping treatments of impacted areas, including restoration areas of existing hardscaped/paved features to be abandoned. Reconstruction of utilities (water, sanitary, electric, communications) to accommodate the infrastructure identified in this section. Work shall be conducted in 4 phases in the following order, with each phase substantially complete before beginning the subsequent phase:

Phase 1: Phase 1 shall consist of the construction the new roadway, bridge, roundabouts, parking lot, and trail elements that can be constructed outside of the existing roadway and parking lot network.

Phase 2: Phase 2 shall consist of the construction of the connecting pieces of the roadway network crossing the existing roadway network, phased in such a way to maintain access to the Visitor Center parking lot, Watchman Campground, the shuttle bus charging and parking lot, the employee parking lot, and the oversized vehicle lot.

Phase 3: Phase 3 shall consist of the construction of the northern half of the oversized vehicle lot and the eastern half of the employee parking lot. Phase 3 work can occur concurrent with Phases 1, 2, and 4 work, assuming visitor, bus, and employee access is maintained throughout the site.

Phase 4: Phase 4 shall consist of the construction of the southern half of the oversized vehicle lot and the western half of the employee parking lot. Phase 4 work can occur concurrent with Phases 1, 2, and 3 work, assuming visitor, bus, and employee access is maintained throughout the site.

Publications

Every notice SAM.gov issued under this solicitation number, oldest first. Each is a separate record on SAM.

  1. August 18, 2025

    Sources sought

    Due September 2, 2025 at 1:00 PM EDT. SAM.gov, notice 3d694bed812e436c9b719fcf9ca34a95