# Ncs/Eml Joint Venture II LLC

Canonical: https://abierto.us/vendors/ncs-eml-joint-venture-ii-llc-qxg5bgv1cq61

- UEI: QXG5BGV1CQ61
- CAGE: 7XQ32
- Location: Louisville, KY
- Awards in window: 5 (6 transactions), -$31,601 obligated, January 9, 2024 to September 18, 2024

## Awarding agencies

- Public Buildings Service: 5 awards, -$31,601

## Industries

- 561210 Facilities Support Services: -$31,601

## Competition

- Full and Open Competition After Exclusion of Sources: 5 awards

## Largest awards

- 47PJ0019D0001: $22,992, PBS R8 Acquisition Management Division. 1 Month Cba Increase, Team West O&m, Denver Federal Center, Lakewood, Colorado. https://www.usaspending.gov/award/CONT_IDV_47PJ0019D0001_4740/
- 47PJ0023F0232 (delivery order): $3,397, PBS R8 Acquisition Management Division. The Pop Is Extended by 31 Days. the Mod Is to Pay for After Hours Work Required by the Funding Agency. Usbr Ups Replacement in Building 67 at the Denver Federal Center in Lakewood Colorado. https://www.usaspending.gov/award/CONT_AWD_47PJ0023F0232_4740_47PJ0019D0001_4740/
- 47PJ0023F0093 (delivery order): -$3,883, PBS R8 Acquisition Management Division. Mod Descoping This Task Order to the Original Amount and Original Sow. the Original Part of the Task Order Has Already Been Completed. Rooftop Unit Valve Replacement in Building 85 at the Denver Federal Center in Lakewood Colorado. https://www.usaspending.gov/award/CONT_AWD_47PJ0023F0093_4740_47PJ0019D0001_4740/
- 47PJ0023F0336 (delivery order): -$11,900, PBS R8 Acquisition Management Division. Project Is Complete. Part of Project Cost Was Covered by Subcontractor Warranty So the Project Cost Less Than Expected. Facp Corrections in Building 56 at the Denver Federal Center in Lakewood Colorado. https://www.usaspending.gov/award/CONT_AWD_47PJ0023F0336_4740_47PJ0019D0001_4740/
- 47PJ0023F0339 (delivery order): -$42,207, PBS R8 Acquisition Management Division. Mod to Descope the Task Order to the Original Sow and the Original Amount. the Original Task Order Part Has Already Been Completed. Carrier Chiller #1 Overhaul in Building 810 at the Denver Federal Center in Lakewood Colorado. https://www.usaspending.gov/award/CONT_AWD_47PJ0023F0339_4740_47PJ0019D0001_4740/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://abierto.us/vendors/ncs-eml-joint-venture-ii-llc-qxg5bgv1cq61.