# Black Horse Bridge Construction Inc.

Canonical: https://abierto.us/vendors/black-horse-bridge-construction-inc-unjrnkflr778

- UEI: UNJRNKFLR778
- CAGE: 8AQQ0
- Location: Norton, OH
- Awards in window: 2 (7 transactions), $8,331,210 obligated, May 31, 2024 to May 15, 2026

## Awarding agencies

- Department of the Army: 1 awards, $6,228,657
- National Park Service: 1 awards, $2,102,553

## Industries

- 237990 Other Heavy and Civil Engineering Construction: $6,228,657
- 238910 Site Preparation Contractors: $2,102,553

## Competition

- Full and Open Competition After Exclusion of Sources: 2 awards

## Solicitations won

- Magnolia Levee Dam Safety Modification (W9123724B0006), $11,324,795. https://abierto.us/opportunities/w9123724b0006
- Brandywine Culvert Replacement (140P6424B0001), $2,045,405. https://abierto.us/opportunities/140p6424b0001

## Largest awards

- W9123724C0006 (definitive contract): $6,228,657, W072 Endist Huntington. Magnolia Levee Dam Safety Modification. https://www.usaspending.gov/award/CONT_AWD_W9123724C0006_9700_-NONE-_-NONE-/
- 140P6424C0006 (definitive contract): $2,102,553, MWR Ohio. Other Construction, Brandywine Culvert Replacement. https://www.usaspending.gov/award/CONT_AWD_140P6424C0006_1443_-NONE-_-NONE-/

---
Source: USAspending.gov award data, keyed by UEI. Obligations in the window only. Cite https://abierto.us/vendors/black-horse-bridge-construction-inc-unjrnkflr778.