# 633 Refrigeration unit

Canonical: https://abierto.us/opportunities/f2q4015099aw01

- Solicitation number: F2Q4015099AW01
- Notice type: Solicitation
- Status: Closed. Deadline was May 7, 2025 at 12:00 PM EDT
- Department: Department of the Air Force
- Agency: Department of the Air Force
- Contracting office: FA4800 633 Cons PKP (FA4800)
- NAICS: 333415 Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment Manufacturing
- Product or service code: 4110 Refrigeration Equipment
- Place of performance: Langley AFB, Virginia
- First posted: April 24, 2025
- Last posted: April 28, 2025
- SAM.gov: https://sam.gov/workspace/contract/opp/a3139fb7cb85417288ef2e7c84134a40/view

## Description

Contractor to provide all parts, labor, tools, materials, facilities and transportation necessary for:Request to replace the existing non-functioning refrigeration unit with a new system, ensuring proper operation and compatibility with the existing setup. The vendor will be required to provide all necessary labor and materials to complete the follow:

**Objective:** To replace the existing non-functioning Heatcraft PTN128H2C refrigeration unit with a new split system, ensuring proper operation and compatibility with the existing setup .

**1. Initial Site Visit and Assessment:** Conduct a thorough site assessment to evaluate the current setup and identify any potential challenges. Confirm the box dimensions to ensure compatibility with the new split system.

**2. Equipment Procurement:** Procure a new split system refrigeration unit to replace the discontinued Heatcraft PTN128H2C unit. Ensure that the new system meets all necessary specifications and requirements for the site. Ensure that the new system will meet necessary requirements for needed temperature levels for walk in fridge.

**3. Preparation:** Disconnect and safely remove the existing Heatcraft PTN128H2C refrigeration unit. Prepare the site for the installation of the new split system, including any necessary modifications to the existing infrastructure .

**4. Installation:** Install the new split system refrigeration unit, ensuring all components are properly connected and secured. Connect the new system to existing duct connections, drain lines, refrigerant lines, and electrical connections as needed.

**5. System Testing:** Pressure test the new system and charge it according to the manufacturer's specifications. Start, test, and ensure proper operation of the new split system.

**6. Final Verification:** Confirm that the new system is functioning correctly and efficiently. Verify that all connections and components are secure and meet safety standards.

**7. Documentation:** Provide detailed documentation of the installation process, including any modifications made to the existing setup. Include a final report confirming the successful replacement and operation of the new split system.

8. We will be hosting a prebid site visit on 1 May 2025 and 0900. please reach out for form to fill out for base access if you plan on attending.

## Publications

- April 24, 2025: Solicitation, due May 2, 2025 at 12:00 PM EDT. Notice 42181cea46054261b647442bc941759a. https://sam.gov/workspace/contract/opp/42181cea46054261b647442bc941759a/view
- April 28, 2025: Solicitation, due May 7, 2025 at 12:00 PM EDT. Notice a3139fb7cb85417288ef2e7c84134a40. https://sam.gov/workspace/contract/opp/a3139fb7cb85417288ef2e7c84134a40/view

## Points of contact

- Nathan Palmer, nathan.palmer.11@us.af.mil, 7577642920
- TSgt Austin Rodriguez, austin.rodriguez.4@us.af.mil, 7577647033

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://abierto.us/opportunities/f2q4015099aw01.