# EGYN121012E Repair Outdated Electrical Switchgear Study B820-830

Canonical: https://abierto.us/opportunities/egyn121012e

- Solicitation number: EGYN121012E
- Notice type: Presolicitation (first published as sources sought)
- Status: Closed. Deadline was July 11, 2024 at 5:00 PM EDT
- Department: Department of the Air Force
- Agency: Department of the Air Force
- Contracting office: FA4659 319 Cons PK (FA4659)
- NAICS: 541330 Engineering Services
- Product or service code: C1JZ Architect And Engineering- Construction: Miscellaneous Buildings
- Set-aside: Total small business set-aside
- Place of performance: Cavalier, North Dakota
- County: Pembina County (FIPS 38067). https://abierto.us/counties/pembina-county-nd-38067
- City: Cavalier. https://abierto.us/cities/cavalier-nd-3812940
- First posted: May 21, 2024
- Last posted: June 13, 2024
- SAM.gov: https://sam.gov/workspace/contract/opp/d11036a64642408088527f27949981fe/view

## Description

**Scope of Work:** The Architect-Engineer (A-E) shall conduct an engineering design study, to include a Class 4 cost estimate (accuracy defined as – 20% to +30%) and provide recommendations to upgrade and/or replace the existing outdated switchgear and motor control center equipment in Mission Buildings B820 and B830 at Cavalier Space Force Station (CSFS), North Dakota.

**Goal:** Provide cost effective, feasible, and sustainable options that will upgrade the Tactical Support Switchgear (SWGR) and Motor Control Centers (MCC) while optimizing the p[power distributions system’s energy efficiency, reliability, resiliency and performance. The upgraded equipment, SWGE and MCC’s must retain their local and remote controls, their voltage and current protection and monitoring as well as any existing capabilities.

Additionally, the study must be conducted within the context of the defined short-term and long-term mission requirements of CSFS. Given that existing manufactured parts are no longer available to conduct routine and preventative maintenance on the switchgear and corresponding equipment, the study must explore both upgrading the existing equipment with modernized technology as well as replacing the existing equipment via reengineering. Questions are due by email NLT 27 June 2024 at 4:00PM CDT.

## Publications

- May 21, 2024: Sources sought, due June 11, 2024 at 5:00 PM EDT. Notice 21a011e3034345d1a38e1e9796b0f00a. https://sam.gov/workspace/contract/opp/21a011e3034345d1a38e1e9796b0f00a/view
- June 13, 2024: Presolicitation, due July 11, 2024 at 5:00 PM EDT. Notice d11036a64642408088527f27949981fe. https://sam.gov/workspace/contract/opp/d11036a64642408088527f27949981fe/view

## Points of contact

- TSgt Nicholas Cameron, nicholas.cameron.3@us.af.mil, 70174752585
- Harold Anderson, harold.anderson.11@us.af.mil, 7017475297

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://abierto.us/opportunities/egyn121012e.