# MKG and GRR TRACON Realignment and Refurbishment

Canonical: https://abierto.us/opportunities/697dck24r00243

- Solicitation number: 697DCK-24-R-00243
- Notice type: Solicitation
- Status: Awarded to Addon Services LLC
- Department: Department of Transportation
- Agency: Federal Aviation Administration
- Contracting office: 697DCK Regional Acquisitions SVCS (697DCK)
- NAICS: 236220 Commercial and Institutional Building Construction
- Product or service code: Z1BA Maintenance Of Air Traffic Control Towers
- Set-aside: Total small business set-aside
- Place of performance: Grand Rapids, Michigan
- County: Kent County (FIPS 26081). https://abierto.us/counties/kent-county-mi-26081
- City: Grand Rapids. https://abierto.us/cities/grand-rapids-mi-2634000
- First posted: April 10, 2024
- Last posted: May 9, 2024
- SAM.gov: https://sam.gov/workspace/contract/opp/adcfaf40597b48979408c3f879efddfd/view

## Description

This requirement is for MKG and GRR TRACON realignment and replacement at the Muskegon County Airport (MKG) located in Muskegon, Michigan and the Gerald R. Ford International Airport (GRR) located in Grand Rapids, Michigan. The scope of work includes, but is not limited to, removal of existing obsolete consoles, carpets, ceilings and other work; providing partitions, carpets, ceilings and other work; providing HVAC and electrical work as specified in drawings and specifications. See specifications and drawing in Section J for complete scope of work.

Amendment 0001 is to incorporate the Question and Answer (Q&A) document and Site Visit sign-in sheets for both facilities as described below:

**FIRST:** The following attachments are hereby released to interested parties as described below:

1. J-6_ Contractor Sign-in sheet-1 2. J-6A_ Contractor Sign-in Sheet-2 3. J-7 Q&A for GRR & MKG Second: The due date for proposals remains the same.

**Third:** All other terms and conditions remain unchanged and in full effect.

Amendment 0002 is to delete Selective Demolition Section 1.6D from the specifications and update the due date of the proposals as described in the following:

**FIRST:** An additional question was received after the Q&A session had ended. That question is the following:

• Line D.1 in section 1.6 “Field Conditions,” on pg. 16 of the solicitation states: “Hazardous materials will be removed by Owner before start of the Work.” However, the plans show areas where asbestos containing materials are to be removed so I just wanted to check and see if we are to follow the solicitation and assume that any asbestos containing materials and other hazardous materials will be removed by the owner or if we are responsible for performing this work.

Based on this question, section 02 41 19 Selective Demolition Section 1.6D is hereby deleted from the specifications as the contractor will be responsible for the removal of hazardous materials identified in the specifications. Updated Specifications are hereby included in this amendment reflecting these changes.

**SECOND:** Due to "FIRST" above, additional time to propose is hereby granted. The new proposal date is updated below:

**FROM:**

**May 10, 2024, by Noon EST TO:**

May 15, 2024, by Noon EST

**THIRD:** All other terms and conditions remain unchanged and in full effect.

## Award on USAspending

- Recipient: Addon Services LLC (UEI C1J1B6AJTQK4)
- Contract: 697DCK24C00245, definitive contract
- Obligated: $1,353,116.17
- Competition: Competed Under SAP, 6 offers received
- Link: solicitation number 697DCK24R00243 equals the FPDS solicitation identifier; same awarding office 697DCK (high confidence)
- Record: https://www.usaspending.gov/award/CONT_AWD_697DCK24C00245_6920_-NONE-_-NONE-/


## Publications

- April 10, 2024: Solicitation, due May 10, 2024 at 12:00 PM EDT. Notice 0bbb3bbe4547472c8cee79272657717f. https://sam.gov/workspace/contract/opp/0bbb3bbe4547472c8cee79272657717f/view
- April 10, 2024: Solicitation, due May 10, 2024 at 12:00 PM EDT. Notice b6b9cab8136240c4b03fbf94d7d54627. https://sam.gov/workspace/contract/opp/b6b9cab8136240c4b03fbf94d7d54627/view
- May 1, 2024: Solicitation, due May 10, 2024 at 12:00 PM EDT. Notice 23409d040a3d4545906c2cfadea3f05d. https://sam.gov/workspace/contract/opp/23409d040a3d4545906c2cfadea3f05d/view
- May 9, 2024: Solicitation, due May 15, 2024 at 12:00 PM EDT. Notice adcfaf40597b48979408c3f879efddfd. https://sam.gov/workspace/contract/opp/adcfaf40597b48979408c3f879efddfd/view

## Points of contact

- Ms. Joni Haynes, joni.l.haynes@faa.gov
- STEVIE TABB, STEVIE.CTR.TABB@FAA.GOV

---
Source: SAM.gov Contract Opportunities bulk extract and USAspending.gov award data. Confirm deadlines on SAM.gov before responding. Cite https://abierto.us/opportunities/697dck24r00243.