# Plating Shop Renovation Industry Day

Canonical: https://abierto.us/opportunities/5525f3adefe546d48a257afb74152a96

- Notice type: Special notice
- Status: Closed. Deadline was October 22, 2025 at 3:00 PM EDT
- Department: Department of the Army
- Agency: Department of the Army
- Contracting office: W075 Endist Sacramento (W91238)
- NAICS: 236210 Industrial Building Construction
- Product or service code: Z2EZ Repair Or Alteration Of Other Industrial Buildings
- Place of performance: Layton, Utah
- County: Davis County (FIPS 49011). https://abierto.us/counties/davis-county-ut-49011
- City: Layton. https://abierto.us/cities/layton-ut-4943660
- First posted: October 2, 2025
- Last posted: October 2, 2025
- SAM.gov: https://sam.gov/workspace/contract/opp/c3407c8f15db4cec8bd44efbee62304b/view

## Description

Project Title: Plating Shop Renovation &ndash; Hill AFB, Utah

Sponsor: U.S. Air Force

Executing Agency: U.S. Army Corps of Engineers, Sacramento District (SPK)

Project Type: Renovation and New Construction

Delivery Method: Design-Bid-Build (DBB)

Contract Type: Firm-Fixed Price (FFP), Single Award Task Order Contract (SATOC)

Ordering Period: 1,825 calendar days (5 years)

Bonding: Required at the task order level for awarded/active work only

Location: Buildings 505 & 507, Hill AFB, Utah

Estimated Magnitude of Construction: $100,000,000 &ndash; $250,000,000

Purpose of Industry Day

The U.S. Army Corps of Engineers, Sacramento District &ndash; Utah Satellite Office is conducting an Industry Day to provide interested Offerors with a clear understanding of the Government&rsquo;s requirements and project timelines.

The event will:

	Present upcoming project requirements and anticipated milestones.

	Facilitate Q&A sessions to address technical, schedule, and procurement questions.

	Promote networking between industry representatives and the USACE Hill Team.

	Provide a tour of the Plating Shop.

Key USACE Staff Available: Project Manager, Technical Lead, Discipline Design Leads, Environmental Leads, and Contracting Officers.

Project Overview

The Plating Shop Renovation project will modernize and expand existing facilities located in Building 505 (B505) and Building 507 (B507) at Hill AFB, Utah, ensuring continued depot-level maintenance capability for multiple aircraft platforms. The renovation addresses compliance with OSHA and environmental standards, enhances safety and ergonomics, improves energy efficiency, reduces maintenance costs, and provides a robust, modernized facility to ensure reliable aircraft part finishing in support of Air Force readiness.

The project includes both the comprehensive renovation of 20,000 square feet of existing shop space and the construction of a new 2,800-square-foot Pre-Engineered Metal Building (PEMB) to accommodate expanded operations.

Renovation &ndash; Building 505/507 (20,000 SF)

	Structural Upgrades: Reinforce basement slabs, footings, and CMU walls. Replace structural platforms, columns, and grating for plating tanks. Modify roof structure to support overhead cranes.

	Mechanical & Process Systems: Replace HVAC and ventilation systems for chemical processes and fume exhaust. Refurbish chemical-resistant coatings on floors, walls, and ceilings.

	Electrical & Controls: Upgrade panelboards, busways, circuits, instrumentation, and lighting to support automated, traceable plating operations.

	Fire & Life Safety: Install updated fire suppression systems, emergency eyewash/shower stations, and life safety signage.

	Integration with GFE: Install Government-Furnished Equipment (GFE) tanks and connect process plumbing to the Industrial Waste Treatment Plant (IWTP).

Key Plating Processes:

	Electroless Nickel

	Cadmium Plating

	Chrome and High Velocity Oxygen Fuel (HVOF) Strip

	Chrome Plating

	Anodize / Alodine (Type II & III)

	Zinc Nickel Plating

	Nickel Sulfamate Plating

	Phosphate / Temper Etch / Passivate

	Aluminum Conversion Coat

	Titanium Pickle

	Fluorescent Penetrant Inspection (FPI)

	Aqueous Degrease / Future Lines

New Construction &ndash; Pre-Engineered Metal Building (PEMB) (2,800 SF)

	Constructed adjacent to Building 505 to accommodate ovens that extend beyond the building footprint.

	Design Features: Insulated steel panels, standing seam metal roof, polyisocyanurate insulation, snow guards.

	Basement & Platforms: Cast-in-place basement, equipment platforms, steel stairs, service utility routing.

	Integration: Structural opening and expansion joint between B505 and PEMB for seamless operational flow.

Ordering Period & Phased Construction Approach

	Ordering Period: 1,825 calendar days (5 years) to accommodate phased construction, complex equipment installation, testing, and commissioning.

	Task Orders: Each phase executed under a separate pre-priced task order with its own Notice-To-Proceed (NTP).

Phased Construction Schedule:

Phase 1:

	Demolition: 'A' tank line (B507), ovens (B505)

	Installation: Type II Anodize (B507); Chrome, Type III Anodize, Phosphate/Passivate (B505)

Phase 2:

	Demolition: Chrome, Anodize, Phosphate lines

	Installation: Cadmium, Zinc Nickel, Temper Etch, Nickel, Electroless Nickel

Phase 3:

	Demolition: Cadmium, Iridate, Zinc Nickel, Temper Etch, Nickel lines

	Installation: Chrome Strip, FPI, Degrease, Future lines

Phase 4:

	Demolition: Chrome and FPI lines

	Installation: New Chrome tank line

Each task order includes labor, equipment, supervision, and materials and is issued within the 5-year ordering period.

Occupancy of Premises

	Work occurs in active, secure facilities. Contractors must maintain security, protect Government property, provide dust enclosures, and coordinate with ongoing operations.

Industry Day Details

	Date: Friday, November 07, 2025

	Time: 0900 &ndash; 1100 MDT (Briefing); 1300 &ndash; 1430 MDT (Site Visit &ndash; Building 505)

	Briefing Location: USACE Utah Layton Satellite Office, 523 S. Heritage Park Blvd, Suite 1, Layton, UT 84041

	Site Visit Location: Building 505, Hill Air Force Base, Utah

RSVP Instructions:

Submit by 1200 PDT on 22 October 2025 with:

	Full Name

	Company Name

	Email Address

Email RSVP to:

Melita S. Doyle &ndash; melita.s.doyle@usace.army.mil

Amelia K. Bryant &ndash; amelia.k.bryant@usace.army.mil

## Open now in the same industry

3 open in NAICS 236210.

- Sources Sought - POST TEST LITHIUM BATTERY STORAGE (N00167-27-RFPREQ-CD-102-0002), due November 18, 2026 at 5:00 PM EST. https://abierto.us/opportunities/n0016727rfpreqcd1020002
- IE181 - WHS Greenhouse Construction (140A2327Q0297), due November 19, 2026 at 2:00 PM EST. https://abierto.us/opportunities/140a2327q0297
- Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB (RFP-376508-CD), due December 17, 2026 at 5:00 PM EST. https://abierto.us/opportunities/rfp376508cd

## Publications

- October 2, 2025: Special notice, due October 22, 2025 at 3:00 PM EDT. Notice c3407c8f15db4cec8bd44efbee62304b. https://sam.gov/workspace/contract/opp/c3407c8f15db4cec8bd44efbee62304b/view

## Points of contact

- Melita Doyle, melita.s.doyle@usace.army.mil
- Amelia K. Bryant, amelia.k.bryant@usace.army.mil

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://abierto.us/opportunities/5525f3adefe546d48a257afb74152a96.