# 19SA7024Q0015 - Design and reconfigure an open-plan office space . (ISC)

Canonical: https://abierto.us/opportunities/19sa7024q0015qa

- Solicitation number: 19SA7024Q0015QA
- Notice type: Special notice
- Status: Closed. Deadline was May 23, 2024 at 10:00 AM EDT
- Department: Department of State
- Contracting office: U.S. Embassy Riyadh (19SA70)
- NAICS: 3372 Office Furniture (including Fixtures) Manufacturing
- Product or service code: N071 Installation of Equipment: Furniture
- Place of performance: SAU
- First posted: May 14, 2024
- Last posted: May 14, 2024
- SAM.gov: https://sam.gov/workspace/contract/opp/1bc38a20a664417d9c88b7345d21c96b/view

## Description

QUESTION AND ANSWER - FOR - SOLICITATION NUMBER 19SA7024Q0015 (ISC Workstation) 1. Please provide us office layout plan-dimensional drawing and material requirement list for bidding for this RFQ Answer: A floor layout was provided, and the material requirements are all mentioned in the SOW. 2. What are the specific requirements for the design reconfiguration proposal?

**Answer:** The main requirements are mentioned in the SOW; one main thing is the accommodation of the two window counters located beside the entrance door. 3. Is there any type of information regarding access to buildings, like ramps, parking zones, elevators and such?

**Answer:** We can arrange access for the vendor for the delivery and installation of the furniture once the final schedule is set with the end user. 4. How many crew members are allowed to perform work inside the facilities?

**Answer:** The vendor will determine the number of staff needed for the installation to be completed within the set timeframe. 5. Is it a good assumption to say that working hours would be mostly night shift?

**Answer:** Weekends and night shifts only from 5:00–10:00 p.m. 6. Please send Room size/layout plan specially door entrance location/locations (if more than ONE door) for designing purpose of these 13 workstations.

**Answer:** The layout is provided with the SOW. 7. How many persons workstation is required together as minimum in one cluster, Two or Four?

**Answer:** The layout is provided with the SOW.

## Publications

- May 14, 2024: Special notice, due May 23, 2024 at 10:00 AM EDT. Notice 1bc38a20a664417d9c88b7345d21c96b. https://sam.gov/workspace/contract/opp/1bc38a20a664417d9c88b7345d21c96b/view

## Points of contact

- ATTN: Contracting Officer, Riyadhcontracting@state.gov

---
Source: SAM.gov Contract Opportunities bulk extract. Confirm deadlines on SAM.gov before responding. Cite https://abierto.us/opportunities/19sa7024q0015qa.